Los Angeles County Public Works
Project Management Division III
Progress Payment 7
Project Name: Marie Canyon Stormwater Disinfection System Upgrade
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001374
Federal Number(s): None
Original Contract: $1,646,300.00
Awarded: 4/15/2025
Period Ending: 9/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF BMPS1.00LS 1.00 0.950.05$22,137.00$1,106.85
10TRAFFIC CONTROL1.00LS 1.00 0.900.10$29,517.00$2,951.70
13OPERATIONAL TESTS1.00LS 0.50 0.000.50$11,069.00$5,534.50
18REMOVAL AND RECYCLING OF UNIVERSAL WASTE1.00LS 1.00 0.950.05$6,641.00$332.05

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LIQUIDATED DAMAGESDAY 50.00 19.0031.00$2,000.00 $62,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,758,675.32 $1,748,750.22 $9,925.10
Retained ($24,690.57) $27,384.33 ($52,074.90)
Deducted $102,000.00 $40,000.00 $62,000.00
Due $1,681,365.89 $1,681,365.89 $0.00



During the initial processing of this Engineer's Monthly Estimate, the current earnings were found to be less than the combined total of the current retention and current deductions resulting in a "negative payment" condition. In order to resolve the condition, the total retention amount for this project has automatically been decreased by $52,074.90

Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.