| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.10
| 0.00 | 0.10 | $25,000.00 | $2,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.10
| 0.00 | 0.10 | $25,000.00 | $2,500.00 |
| 6 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.10
| 0.00 | 0.10 | $25,000.00 | $2,500.00 |
| 9 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 11 | PREPARATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 14 | OFFICE FACILITIES | 9.00 | MTH |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| 15 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $100,000.00 | $50,000.00 |
| 23 | PUMP STATION BUILDING & ASSOCIATED COMPONENTS | 1.00 | LS |
0.04
| 0.00 | 0.04 | $500,000.00 | $20,000.00 |
| 32 | PERMIT AND INSPECTION FEE (ALLOWANCE OF $5,000) | 5,000.00 | AL |
1.00
| 0.00 | 1.00 | $1.00 | $1.00 |
| S-1 | TEMPORARY WATER TANK | | LS |
1.00
| 0.00 | 1.00 | $28,400.00 | $28,400.00 |