| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 2.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.66
| 0.33 | 0.33 | $9,150.00 | $3,019.50 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.66
| 0.33 | 0.33 | $21,800.00 | $7,194.00 |
| 8 | 1-CAMERA VIDEO/RADAR DETECTION SYSTEM (COMPLETE) | 1.00 | EA |
1.00
| 0.00 | 1.00 | $2,640.00 | $2,640.00 |
| 11 | REMOVE PULL BOX | 5.00 | EA |
2.00
| 0.00 | 2.00 | $87.00 | $174.00 |
| 29 | SERVICE PEDESTAL AND CONCRETE FOUNDATION | 2.00 | EA |
1.00
| 0.00 | 1.00 | $14,300.00 | $14,300.00 |
| 35 | COMPOSITE TYPE 3 PULL BOX INCL COVER | 1.00 | EA |
1.00
| 0.00 | 1.00 | $1,430.00 | $1,430.00 |
| 42 | TRAFFIC CONTROL | 1.00 | LS |
0.60
| 0.30 | 0.30 | $43,000.00 | $12,900.00 |
| S-2 | CITY OF AZUSA WATER METERS | | LS |
1.00
| 0.00 | 1.00 | $65,000.00 | $65,000.00 |