| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 15.00 | MTH |
13.00
| 12.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.92
| 0.84 | 0.08 | $324,000.00 | $25,920.00 |
| 8 | NOISE MONITORING AND REPORTING | 15.00 | MTH |
13.00
| 12.00 | 1.00 | $4,000.00 | $4,000.00 |
| 20 | WATER TRUCK | 260.00 | DAY |
247.50
| 227.50 | 20.00 | $1,800.00 | $36,000.00 |
| 25 | NEW STAFF GAGE BOARDS | 6.00 | EA |
3.00
| 0.00 | 3.00 | $2,800.00 | $8,400.00 |
| 27 | OFFICE FACILITIES | 15.00 | MTH |
13.00
| 12.00 | 1.00 | $5,000.00 | $5,000.00 |
| 39 | BUTTRESS FILL | 16,505.00 | CY |
15,788.40
| 15,362.40 | 426.00 | $55.00 | $23,430.00 |
| 40 | DOWNSTREAM RIPRAP (CLASS IV) | 7,571.00 | CY |
5,732.08
| 5,715.08 | 17.00 | $75.00 | $1,275.00 |
| 41 | UPSTREAM RIPRAP (CLASS V) | 8,792.00 | CY |
4,376.37
| 3,436.45 | 939.92 | $50.00 | $46,996.00 |
| 43 | PCC PAVEMENT & PCC WALKWAY | 1,202.00 | CY |
480.58
| 278.39 | 202.19 | $550.00 | $111,204.50 |
| 51 | 6" DUCTILE IRON PIPE | 50.00 | LF |
25.00
| 0.00 | 25.00 | $520.00 | $13,000.00 |
| 57 | INTAKE TRASH RACK | 5.00 | EA |
4.00
| 0.00 | 4.00 | $25,000.00 | $100,000.00 |
| 71 | CHANNEL WALL REPAIR | 1.00 | LS |
1.00
| 0.00 | 1.00 | $7,500.00 | $7,500.00 |
| 72 | TOE DRAIN WEIR VAULT | 1.00 | LS |
0.95
| 0.09 | 0.86 | $22,000.00 | $18,920.00 |
| 73 | OGEE WEIR COMPLETE IN PLACE | 1.00 | LS |
0.25
| 0.16 | 0.09 | $410,000.00 | $36,900.00 |
| 74 | SPILLWAY WALL BUTTRESS COMPLETE IN PLACE | 1.00 | LS |
1.00
| 0.95 | 0.05 | $6,000,000.00 | $300,000.00 |
| 75 | INTAKE TOWER COMPLETE IN PLACE | 1.00 | LS |
0.97
| 0.70 | 0.27 | $1,500,000.00 | $405,000.00 |
| 76 | DAVIT CRANE | 1.00 | LS |
0.97
| 0.12 | 0.85 | $9,000.00 | $7,650.00 |
| 79 | CATWALK STRUCTURAL (STEEL, PLATE, HANDRAILING) | 1.00 | LS |
0.95
| 0.20 | 0.75 | $550,000.00 | $412,500.00 |
| 80 | CONTROL BUILDING | 1.00 | LS |
0.97
| 0.80 | 0.17 | $700,000.00 | $119,000.00 |
| 81 | INTAKE TOWER GATE & ACTUATOR | 1.00 | LS |
0.97
| 0.92 | 0.05 | $230,000.00 | $11,500.00 |
| 82 | ELECTRICAL WORK | 1.00 | LS |
0.97
| 0.65 | 0.32 | $454,000.00 | $145,280.00 |
| 83 | INSTRUMENTATION | 1.00 | LS |
0.85
| 0.65 | 0.20 | $425,000.00 | $85,000.00 |
| 84 | AUTOMATED DATA ACQUISITION SYSTEM (ADAS) | 1.00 | LS |
0.50
| 0.14 | 0.36 | $72,000.00 | $25,920.00 |
| S-06 | REMOVABLE LOUVER & ADDED REBAR AT CONTROL BLDG. | | LS |
1.00
| 0.50 | 0.50 | $20,200.00 | $10,100.00 |
| S-09 | SUPPLEMENTAL BAT EXCLUSION DEVICES | | T&M |
59,687.96
| 0.00 | 59,687.96 | $1.00 | $59,687.96 |
|