| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 18.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.08
| 0.00 | 0.08 | $50,000.00 | $4,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.08
| 0.00 | 0.08 | $625,000.00 | $50,000.00 |
| 7 | IMPLEMENTATION OF THE SOIL MANAGEMENT PLAN | 1.00 | LS |
0.08
| 0.00 | 0.08 | $15,000.00 | $1,200.00 |
| 9 | AIR MONITORING (RULE 1466) | 240.00 | DAYS |
21.00
| 3.00 | 18.00 | $250.00 | $4,500.00 |
| 10 | NPDES MONITORING AND REPORTING | 12.00 | MTH |
1.00
| 0.00 | 1.00 | $4,500.00 | $4,500.00 |
| 12 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.08
| 0.00 | 0.08 | $100,000.00 | $8,000.00 |
| 15 | MAINTENANCE AND REMOVAL OF TEMPORARY SOUND BARRIER | 1.00 | LS |
0.08
| 0.00 | 0.08 | $5,000.00 | $400.00 |
| 16 | SHORING OF OPEN EXCAVATIONS | 5,050.00 | LF |
171.00
| 0.00 | 171.00 | $1.00 | $171.00 |
| 17 | OFFICE FACILITIES | 18.00 | MTH |
2.00
| 1.00 | 1.00 | $4,500.00 | $4,500.00 |
| 23 | IMPLEMENTATION OF THE DEWATERING PLAN | 1.00 | LS |
0.45
| 0.40 | 0.05 | $1,275,000.00 | $63,750.00 |
| 26 | WATER TRUCK | 100.00 | DAY |
6.00
| 0.00 | 6.00 | $1,350.00 | $8,100.00 |
| 27 | PARTNERING (ALLOWANCE OF $30,000) | 30,000.00 | AL |
8,900.00
| 0.00 | 8,900.00 | $1.00 | $8,900.00 |
| 28 | TREE PROTECTION FENCING | 1.00 | LS |
0.55
| 0.50 | 0.05 | $75,000.00 | $3,750.00 |
| 33 | REMOVE EXISTING CHAIN LINK FENCE | 51.00 | LF |
51.00
| 0.00 | 51.00 | $50.00 | $2,550.00 |
| 34 | CONCRETE REMOVAL (REINFORCED) | 16.00 | CY |
11.00
| 0.00 | 11.00 | $650.00 | $7,150.00 |
| 35 | EXCAVATION OF SEDIMENT FROM TULE POND | 8,755.00 | TON |
1,350.00
| 0.00 | 1,350.00 | $25.00 | $33,750.00 |
| 36 | TRANSPORTATION OF SEDIMENT FROM TULE POND (CALIFORNIA HAZARDOUS WASTE) | 8,755.00 | TON |
1,350.00
| 0.00 | 1,350.00 | $110.00 | $148,500.00 |
| 38 | CATCH BASIN PER STD PLAN 300, W=21 | 1.00 | EA |
0.40
| 0.00 | 0.40 | $30,000.00 | $12,000.00 |
| 46 | 36" RCP, 2000 D | 313.00 | LF |
171.00
| 0.00 | 171.00 | $350.00 | $59,850.00 |
| 54 | CLEARING AND GRUBBING | 1.00 | LS |
0.90
| 0.40 | 0.50 | $35,000.00 | $17,500.00 |
| 55 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 35.00 | EA |
1.00
| 0.00 | 1.00 | $1,400.00 | $1,400.00 |
| 56 | TREE REMOVAL (13"-24" DIAMETER) | 48.00 | EA |
34.00
| 20.00 | 14.00 | $2,575.00 | $36,050.00 |
| 89 | TREE REMOVAL (13"-24" DIAMETER) | 128.00 | EA |
77.00
| 50.00 | 27.00 | $4,000.00 | $108,000.00 |
| 111 | GENERAL CONDITIONS | 1.00 | LS |
0.08
| 0.00 | 0.08 | $60,000.00 | $4,800.00 |
|