| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
16.00
| 15.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.80
| 0.75 | 0.05 | $45,000.00 | $2,250.00 |
| 8 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
1.00
| 0.00 | 1.00 | $220,000.00 | $220,000.00 |
| 16 | OFFICE FACILITIES | 25.00 | MTH |
18.00
| 17.00 | 1.00 | $15,000.00 | $15,000.00 |
| 18 | TRAFFIC CONTROL | 1.00 | LS |
0.80
| 0.75 | 0.05 | $1,700,000.00 | $85,000.00 |
| 25 | TREE REMOVAL (13"-24" DIAMETER) | 87.00 | EA |
70.00
| 69.00 | 1.00 | $550.00 | $550.00 |
| 27 | CONCRETE REMOVAL (NON-REINFORCED) | 3,340.00 | CY |
2,730.14
| 2,683.57 | 46.57 | $240.00 | $11,176.80 |
| 29 | UNCLASSIFIED EXCAVATION | 23,912.00 | CY |
16,376.83
| 15,932.24 | 444.59 | $100.00 | $44,459.00 |
| 30 | CRUSHED AGGREGATE BASE | 2,404.00 | CY |
1,100.10
| 505.73 | 594.37 | $240.00 | $142,648.80 |
| 34 | AC PAVEMENT(PATCH BACK) | 4,524.00 | TON |
1,742.49
| 1,495.81 | 246.68 | $180.00 | $44,402.40 |
| 41 | CATCH BASIN PER STD PLAN 300, W=3.5 | 3.00 | EA |
2.00
| 0.00 | 2.00 | $9,200.00 | $18,400.00 |
| 45 | AC PAVEMENT | 8,126.00 | SF |
3,010.24
| 1,664.00 | 1,346.24 | $8.00 | $10,769.92 |
| 55 | PCC CURB, TYPE A1-8 - CITY STD | 2,690.00 | LF |
105.66
| 0.00 | 105.66 | $34.00 | $3,592.44 |
| 56 | PCC CURB & GUTTER, TYPE A2-8 - CITY STD | 5,196.00 | LF |
3,480.81
| 2,864.32 | 616.49 | $46.00 | $28,358.54 |
| 57 | PCC WALK & DRIVEWAYS, 4" THICK | 38,431.00 | SF |
32,069.51
| 30,692.25 | 1,377.26 | $8.50 | $11,706.71 |
| 59 | PCC DRIVEWAYS, 6" THICK | 4,910.00 | SF |
3,690.85
| 3,154.03 | 536.82 | $13.00 | $6,978.66 |
| 61 | CROSS GUTTER | 75.00 | CY |
55.74
| 28.40 | 27.34 | $615.00 | $16,814.10 |
| 71 | 1" CONDUIT (SCH 80 PVC) | 189.00 | LF |
189.00
| 110.00 | 79.00 | $60.00 | $4,740.00 |
| 79 | NO. 5 PULL BOX INCL PCC COVER | 49.00 | EA |
36.00
| 19.00 | 17.00 | $1,300.00 | $22,100.00 |
| 118 | FURNISH AND INSTALL PHOTOCELL INTERMATIC | 49.00 | EACH |
13.00
| 0.00 | 13.00 | $205.00 | $2,665.00 |
| 125 | FURNISH AND INSTALL #6 ALUMINUM XHHW WIRE | 4,230.00 | LF |
4,230.00
| 0.00 | 4,230.00 | $3.05 | $12,901.50 |
| 144 | TYPE 332 CABINET FOUNDATION | 7.00 | EA |
6.00
| 4.00 | 2.00 | $3,225.00 | $6,450.00 |
| 158 | TYPE 29 STANDARD FOUNDATION | 3.00 | EA |
3.00
| 1.00 | 2.00 | $12,000.00 | $24,000.00 |
| 178 | DETAIL 22 (THERMOPLASTIC) | 3,405.00 | LF |
603.50
| 491.50 | 112.00 | $1.50 | $168.00 |
| 183 | DETAIL 40 (THERMOPLASTIC) | 655.00 | LF |
540.00
| 500.00 | 40.00 | $1.10 | $44.00 |
| 188 | PAVEMENT MARKINGS (THERMOPLASTIC) | 7,434.00 | SF |
3,364.00
| 3,349.00 | 15.00 | $8.05 | $120.75 |
| 189 | 12" STRIPING (THERMOPLASTIC) | 2,575.00 | LF |
1,484.00
| 1,454.00 | 30.00 | $2.70 | $81.00 |
| 222 | TYPE 15TS STANDARD FOUNDATION | 22.00 | EA |
8.00
| 7.00 | 1.00 | $4,010.00 | $4,010.00 |
| 228 | PCC PAVEMENT (HIGH EARLY STRENGTH) | 456.00 | CY |
297.96
| 247.19 | 50.77 | $535.00 | $27,161.95 |
| 248 | LOCAL DEPRESSION PER STD PLAN 313, CASE E | 4.00 | EA |
2.00
| 0.00 | 2.00 | $2,900.00 | $5,800.00 |
| 259 | EDISON 3 INCH NON-METALLIC PVC SCHEDULE 80 WITH PULL TAPE, FITTINGS AND SUPPORTS | 821.00 | LF |
821.00
| 751.00 | 70.00 | $100.00 | $7,000.00 |
| 261 | 2 INCH DIAMETER NON-METALLIC PVC SCHEDULE 80 BRANCH CONDUIT, FITTINGS AND SUPPORTS | 5,124.00 | LF |
3,090.00
| 3,080.00 | 10.00 | $65.00 | $650.00 |
| 262 | SERVICE PEDESTAL AND CONCRETE FOUNDATION | 6.00 | EA |
6.00
| 3.00 | 3.00 | $7,500.00 | $22,500.00 |
| 263 | PULL BOX, 10 INCH BY 17 INCH BY 12 INCH | 35.00 | EA |
3.00
| 1.00 | 2.00 | $475.00 | $950.00 |
|