| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.22
| 0.10 | 0.12 | $25,000.00 | $3,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.22
| 0.10 | 0.12 | $25,000.00 | $3,000.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.22
| 0.10 | 0.12 | $25,000.00 | $3,000.00 |
| 8 | REMOVAL AND DISPOSAL OF LBP/LCP | 1.00 | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| 10 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| 12 | IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN | 1.00 | LS |
0.30
| 0.00 | 0.30 | $25,000.00 | $7,500.00 |
| 13 | REMOVAL AND DISPOSAL OF NON-HAZARDOUS ASBESTOS WASTE | 1.00 | LS |
0.30
| 0.00 | 0.30 | $25,000.00 | $7,500.00 |
| 14 | OFFICE FACILITIES | 9.00 | MTH |
2.00
| 1.00 | 1.00 | $10,000.00 | $10,000.00 |
| 21 | TEMPORARY BYPASS | 1.00 | LS |
0.30
| 0.00 | 0.30 | $50,000.00 | $15,000.00 |
| 22 | EXISTING PUMP STATION BUILDING & SITE DEMOLITION AND REMOVAL | 1.00 | LS |
0.10
| 0.00 | 0.10 | $200,000.00 | $20,000.00 |
| 23 | PUMP STATION BUILDING & ASSOCIATED COMPONENTS | 1.00 | LS |
0.08
| 0.04 | 0.04 | $500,000.00 | $20,000.00 |
| 31 | PORTABLE GENERATOR | 1.00 | LS |
0.83
| 0.00 | 0.83 | $100,000.00 | $83,000.00 |