| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 12.00 | MTH |
8.00
| 6.00 | 2.00 | $500.00 | $1,000.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.90
| 0.82 | 0.08 | $35,000.00 | $2,800.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.90
| 0.82 | 0.08 | $90,000.00 | $7,200.00 |
| 7 | OFFICE FACILITIES | 12.00 | MTH |
8.00
| 7.00 | 1.00 | $6,900.00 | $6,900.00 |
| 11 | TREE ESTABLISHMENT BY TRUCK WATERING | 1.00 | LS |
1.00
| 0.60 | 0.40 | $18,000.00 | $7,200.00 |
| 36 | PCC CURB & GUTTER, TYPE A2-VAR | 2,174.00 | LF |
1,844.00
| 1,640.00 | 204.00 | $75.00 | $15,300.00 |
| 97 | 12" STRIPING (THERMOPLASTIC) | 1,251.00 | LF |
1,234.00
| 1,191.00 | 43.00 | $6.10 | $262.30 |
| 98 | CURB MARKINGS (ONE-COAT PAINT) | 1,302.00 | LF |
1,072.00
| 0.00 | 1,072.00 | $2.85 | $3,055.20 |
| 102 | SIGN POST (ROADSIDE SIGN) | 15.00 | EA |
14.00
| 11.00 | 3.00 | $235.00 | $705.00 |
| 111 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.82 | 0.08 | $750,000.00 | $60,000.00 |
| 121 | 24" STRIPING (THERMOPLASTIC) | 8,520.00 | LF |
8,417.00
| 7,400.00 | 1,017.00 | $8.90 | $9,051.30 |