Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Arrow Highway TSSP - Rennell Avenue to Claremont Boulevard - Mills Avenue
Contractor: California Professional Engineering, Inc.
19062 San Jose Avenue
La Puente, CA 91748
Project ID: TSM0010460
Federal Number(s): None
Original Contract: $1,460,388.32
Awarded: 12/17/2025
Period Ending: 11/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
3CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
4TRAFFIC CONTROL1.00LS 0.08 0.000.08$37,400.00$2,992.00
5MOBILIZATION1.00LS 0.50 0.000.50$51,815.00$25,907.50
6IMPLEMENTATION OF THE LTWHP1.00LS 0.08 0.000.08$2,000.00$160.00
7IMPLEMENTATION OF BMPS1.00LS 0.08 0.000.08$2,500.00$200.00
8EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $35,000)35,000.00AL 12,400.00 0.0012,400.00$1.00$12,400.00
70NO. 6 PULL BOX INCL PCC COVER20.00EA 11.00 0.0011.00$980.00$10,780.00
722" CONDUIT (SCH 80 PVC)100.00LF 50.00 0.0050.00$90.00$4,500.00
733" CONDUIT (SCH 80 PVC)480.00LF 460.00 0.00460.00$100.00$46,000.00
744" CONDUIT (SCH 80 PVC)565.00LF 180.00 0.00180.00$110.00$19,800.00
S-1POMONA LUMINAIRE UPGRADES LS 1.00 0.001.00$4,185.00$4,185.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $129,424.50 $0.00 $129,424.50
Retained $6,471.23 $0.00 $6,471.23
Deducted $0.00 $0.00 $0.00
Due $122,953.27 $0.00 $122,953.27



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.