| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 15.00 | MTH |
14.00
| 13.00 | 1.00 | $500.00 | $500.00 |
| 8 | NOISE MONITORING AND REPORTING | 15.00 | MTH |
14.00
| 13.00 | 1.00 | $4,000.00 | $4,000.00 |
| 12 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
1.00
| 0.50 | 0.50 | $10,000.00 | $5,000.00 |
| 20 | WATER TRUCK | 260.00 | DAY |
260.00
| 247.50 | 12.50 | $1,800.00 | $22,500.00 |
| 23 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.92
| 0.84 | 0.08 | $34,000.00 | $2,720.00 |
| 24 | REMOVAL AND DISPOSAL OF LBP/LCP WASTE | 1.00 | LS |
1.00
| 0.50 | 0.50 | $14,000.00 | $7,000.00 |
| 25 | NEW STAFF GAGE BOARDS | 6.00 | EA |
6.00
| 3.00 | 3.00 | $2,800.00 | $8,400.00 |
| 27 | OFFICE FACILITIES | 15.00 | MTH |
14.00
| 13.00 | 1.00 | $5,000.00 | $5,000.00 |
| 40 | DOWNSTREAM RIPRAP (CLASS IV) | 7,571.00 | CY |
5,852.52
| 5,732.08 | 120.44 | $75.00 | $9,033.00 |
| 41 | UPSTREAM RIPRAP (CLASS V) | 8,792.00 | CY |
5,098.17
| 4,376.37 | 721.80 | $50.00 | $36,090.00 |
| 43 | PCC PAVEMENT & PCC WALKWAY | 1,202.00 | CY |
1,090.91
| 480.58 | 610.33 | $550.00 | $335,681.50 |
| 44 | PCC CURB & GUTTER, TYPE B2 | 124.00 | LF |
124.00
| 0.00 | 124.00 | $106.00 | $13,144.00 |
| 46 | CABLE RAILING (CALTRANS STD PLAN B11-47) | 71.00 | LF |
65.00
| 0.00 | 65.00 | $150.00 | $9,750.00 |
| 47 | METAL BEAM GUARD RAILING | 405.00 | LF |
320.00
| 0.00 | 320.00 | $131.00 | $41,920.00 |
| 51 | 6" DUCTILE IRON PIPE | 50.00 | LF |
50.00
| 25.00 | 25.00 | $520.00 | $13,000.00 |
| 56 | REMOVABLE BOLLARD | 2.00 | EA |
2.00
| 0.00 | 2.00 | $3,000.00 | $6,000.00 |
| 57 | INTAKE TRASH RACK | 5.00 | EA |
5.00
| 4.00 | 1.00 | $25,000.00 | $25,000.00 |
| 62 | FIXED METAL BOLLARD | 5.00 | EA |
4.00
| 0.00 | 4.00 | $1,830.00 | $7,320.00 |
| 65 | 48" POOL DRAIN CIPP LINER | 330.00 | LF |
330.00
| 279.00 | 51.00 | $893.00 | $45,543.00 |
| 72 | TOE DRAIN WEIR VAULT | 1.00 | LS |
0.99
| 0.95 | 0.04 | $22,000.00 | $880.00 |
| 75 | INTAKE TOWER COMPLETE IN PLACE | 1.00 | LS |
0.99
| 0.97 | 0.02 | $1,500,000.00 | $30,000.00 |
| 76 | DAVIT CRANE | 1.00 | LS |
0.99
| 0.97 | 0.02 | $9,000.00 | $180.00 |
| 77 | INTAKE TOWER TRASH RACK COMPLETE IN PLACE | 1.00 | LS |
1.00
| 0.97 | 0.03 | $445,000.00 | $13,350.00 |
| 79 | CATWALK STRUCTURAL (STEEL, PLATE, HANDRAILING) | 1.00 | LS |
1.00
| 0.95 | 0.05 | $550,000.00 | $27,500.00 |
| 80 | CONTROL BUILDING | 1.00 | LS |
0.99
| 0.97 | 0.02 | $700,000.00 | $14,000.00 |
| 81 | INTAKE TOWER GATE & ACTUATOR | 1.00 | LS |
0.99
| 0.97 | 0.02 | $230,000.00 | $4,600.00 |
| 82 | ELECTRICAL WORK | 1.00 | LS |
0.99
| 0.97 | 0.02 | $454,000.00 | $9,080.00 |
| 83 | INSTRUMENTATION | 1.00 | LS |
0.95
| 0.85 | 0.10 | $425,000.00 | $42,500.00 |
| 84 | AUTOMATED DATA ACQUISITION SYSTEM (ADAS) | 1.00 | LS |
0.75
| 0.50 | 0.25 | $72,000.00 | $18,000.00 |
| 90 | 5' TALL CHAIN LINK FENCE | 170.00 | LF |
92.60
| 0.00 | 92.60 | $170.00 | $15,742.00 |
| S-10 | ROUGHENING OF CONCRETE SURFACES | | T&M |
50,181.61
| 0.00 | 50,181.61 | $1.00 | $50,181.61 |
|