Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Lark Ellen Av Median Improvements, et al., Phase I
Contractor: CT & T Concrete Paving, Inc.
324 South Diamond Bar Boulevard, PMB #275
Diamond Bar, CA 91765
Project ID: RDC0016556
Federal Number(s): None
Original Contract: $1,164,030.90
Awarded: 4/20/2026
Period Ending: 10/20/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE LTWHP1.00LS 1.00 0.660.34$9,150.00$3,111.00
5IMPLEMENTATION OF BMPS1.00LS 1.00 0.660.34$21,800.00$7,412.00
6FIRST MOBILIZATION1.00LS 1.00 0.950.05$64,900.00$3,245.00
13TRENCH BACKFILL SLURRY (CLASS 270-E-500)3.00CY 2.00 0.002.00$888.00$1,776.00
15AC PAVEMENT(PATCH BACK)9.00TON 9.00 0.009.00$534.00$4,806.00
21PCC WALK, 4" THICK7,547.00SF 7,203.00 6,115.001,088.00$9.50$10,336.00
23PCC CURB RAMPS2.00CY 2.00 1.001.00$600.00$600.00
24DETECTABLE WARNING SURFACE26.00SF 24.00 12.0012.00$31.00$372.00
263" CONDUIT (SCH 80 PVC)12.00LF 10.00 0.0010.00$110.00$1,100.00
27NO. 5 PULL BOX INCL PCC COVER6.00EA 6.00 3.003.00$1,017.50$3,052.50
28NO. 6 PULL BOX INCL PCC COVER2.00EA 2.00 0.002.00$1,017.50$2,035.00
30SHORT CIRCUIT, COORDINATION AND ARC FLASH STUDY1.00LS 0.50 0.000.50$33,000.00$16,500.00
31GROUND WELL2.00EA 2.00 0.002.00$825.00$1,650.00
32CONDUIT (2 INCH SCHD 80, FITTINGS, SUPPORT)680.00LF 680.00 530.00150.00$82.50$12,375.00
33CONDUIT (EDISON 4 INCH WITH PULL TAPE, FITTINGS, SUPPORTS)125.00LF 125.00 0.00125.00$121.00$15,125.00
393/4" DIAMETER X 10' CU-CLAD GROUND ROD4.00EA 4.00 0.004.00$440.00$1,760.00
42TRAFFIC CONTROL1.00LS 1.00 0.600.40$43,000.00$17,200.00
46AGRONOMIC SOIL REPORT8.00EA 8.00 0.008.00$165.00$1,320.00
48IRRIGATION SYSTEM1.00LS 0.75 0.000.75$200,750.00$150,562.50
S-3BATTERY POWERED IRRIGATION VALVES LS 1.00 0.001.00$7,999.00$7,999.00
S-4IRRIGATION UP SIZING  LS 1.00 0.001.00$4,372.00$4,372.00
S-5BACKFLOW INCREASE TO 2 INCH LS 1.00 0.001.00$5,396.00$5,396.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $799,559.40 $527,454.40 $272,105.00
Retained $39,977.97 $26,372.72 $13,605.25
Deducted $0.00 $0.00 $0.00
Due $759,581.43 $501,081.68 $258,499.75



Contact Office Engineer
Contractor Copy  