| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 7.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.32
| 0.16 | 0.16 | $5,000.00 | $800.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.32
| 0.16 | 0.16 | $1,138.00 | $182.08 |
| 6 | MOBILIZATION | 1.00 | LS |
1.00
| 0.50 | 0.50 | $38,000.00 | $19,000.00 |
| 7 | EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $75,000) | 75,000.00 | AL |
7,600.00
| 0.00 | 7,600.00 | $1.00 | $7,600.00 |
| 15 | 2" CONDUIT (SCH 80 PVC) | 710.00 | LF |
710.00
| 692.00 | 18.00 | $56.00 | $1,008.00 |
| 16 | 3" CONDUIT (SCH 80 PVC) | 75.00 | LF |
45.00
| 0.00 | 45.00 | $140.00 | $6,300.00 |
| 24 | COMPOSITE TYPE 2 PULL BOX INCL COVER | 20.00 | EA |
19.00
| 16.00 | 3.00 | $1,952.00 | $5,856.00 |
| 25 | COMPOSITE TYPE 3 PULL BOX INCL COVER | 9.00 | EA |
4.00
| 0.00 | 4.00 | $2,558.00 | $10,232.00 |
| 56 | TYPE 332 CABINET | 2.00 | EA |
1.00
| 0.00 | 1.00 | $26,484.00 | $26,484.00 |
| 61 | TYPE 19 STANDARD | 3.00 | EA |
2.00
| 0.00 | 2.00 | $15,005.00 | $30,010.00 |
| 62 | TYPE 24 STANDARD | 2.00 | EA |
1.00
| 0.00 | 1.00 | $16,530.00 | $16,530.00 |
| 68 | TYPE 19 STANDARD FOUNDATION | 3.00 | EA |
2.00
| 0.00 | 2.00 | $6,965.00 | $13,930.00 |
| 69 | TYPE 24 STANDARD FOUNDATION | 4.00 | EA |
2.00
| 0.00 | 2.00 | $7,095.00 | $14,190.00 |
| 70 | TYPE 26 STANDARD FOUNDATION | 3.00 | EA |
1.00
| 0.00 | 1.00 | $7,775.00 | $7,775.00 |
| 71 | TYPE 29 STANDARD FOUNDATION | 2.00 | EA |
2.00
| 0.00 | 2.00 | $8,120.00 | $16,240.00 |
| 97 | TRAFFIC CONTROL | 1.00 | LS |
0.32
| 0.16 | 0.16 | $23,000.00 | $3,680.00 |