Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
3 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.05
| 0.00 | 0.05 | $11,000.00 | $550.00 |
4 | RESTORATION OF EXISTING IMPROVEMENTS | 1.00 | LS |
0.05
| 0.00 | 0.05 | $10,000.00 | $500.00 |
5 | TRAFFIC CONTROL | 1.00 | LS |
0.08
| 0.00 | 0.08 | $65,000.00 | $5,200.00 |
6 | FLASHING ARROW SIGN | 6.00 | EA |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
7 | CHANGEABLE MESSAGE SIGN | 5.00 | EA |
2.00
| 0.00 | 2.00 | $6,000.00 | $12,000.00 |
10 | OFFICE FACILITIES | 1.00 | LS |
0.05
| 0.00 | 0.05 | $7,500.00 | $375.00 |
11 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $130,000.00 | $65,000.00 |
12 | CLEARING AND GRUBBING | 1.00 | LS |
0.08
| 0.00 | 0.08 | $100,000.00 | $8,000.00 |
14 | CONCRETE REMOVAL (NON-REINFORCED) | 2,271.00 | CY |
304.14
| 0.00 | 304.14 | $65.00 | $19,769.10 |
16 | UNCLASSIFIED EXCAVATION | 6,509.00 | CY |
563.12
| 0.00 | 563.12 | $46.00 | $25,903.52 |
18 | CRUSHED MISCELLANEOUS BASE | 5,465.00 | CY |
488.93
| 0.00 | 488.93 | $55.00 | $26,891.15 |
20 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 153.00 | CY |
19.75
| 0.00 | 19.75 | $220.00 | $4,345.00 |
23 | AC PAVEMENT(PATCH BACK) | 167.00 | TON |
76.13
| 0.00 | 76.13 | $175.00 | $13,322.75 |
44 | PARKWAY DRAIN PER STD PLAN 151, S=12", INLET TYPE 2 | 2.00 | EA |
2.00
| 0.00 | 2.00 | $3,000.00 | $6,000.00 |
45 | PARKWAY DRAIN PER STD PLAN 151, S=18", INLET TYPE 2 | 3.00 | EA |
1.00
| 0.00 | 1.00 | $3,500.00 | $3,500.00 |
50 | PCC CURB & GUTTER, TYPE A2-8 | 4,051.00 | LF |
11.00
| 0.00 | 11.00 | $25.50 | $280.50 |
52 | PCC CURB & GUTTER, TYPE A2-8, W=12" | 1,911.00 | LF |
789.00
| 0.00 | 789.00 | $26.00 | $20,514.00 |
54 | PCC WALK, DRIVES & CURB RAMPS, 4" THICK | 100,163.00 | SF |
19,723.16
| 0.00 | 19,723.16 | $4.50 | $88,754.22 |
55 | PCC DRIVEWAYS, 6" THICK | 10,639.00 | SF |
975.00
| 0.00 | 975.00 | $6.00 | $5,850.00 |
56 | DETECTABLE WARNING SURFACE | 1,275.00 | SF |
81.00
| 0.00 | 81.00 | $25.00 | $2,025.00 |
57 | CROSS GUTTER | 200.00 | CY |
2.47
| 0.00 | 2.47 | $325.00 | $802.75 |
59 | ALLEY INTERSECTION | 40.00 | CY |
4.07
| 0.00 | 4.07 | $325.00 | $1,322.75 |
66 | 3" CONDUIT (SCH 80 PVC) | 765.00 | LF |
15.00
| 0.00 | 15.00 | $30.00 | $450.00 |
91 | TYPE 15 STANDARD FOUNDATION | 7.00 | EA |
4.00
| 0.00 | 4.00 | $1,500.00 | $6,000.00 |
92 | TYPE 19 STANDARD FOUNDATION | 6.00 | EA |
4.00
| 0.00 | 4.00 | $1,900.00 | $7,600.00 |
|