Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
3.00
| 2.00 | 1.00 | $700.00 | $700.00 |
4 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.50
| 0.40 | 0.10 | $48,000.00 | $4,800.00 |
5 | TRAFFIC CONTROL | 1.00 | LS |
0.45
| 0.35 | 0.10 | $69,000.00 | $6,900.00 |
6 | OFFICE FACILITIES | 1.00 | LS |
0.55
| 0.45 | 0.10 | $17,000.00 | $1,700.00 |
8 | CLEARING AND GRUBBING | 1.00 | LS |
0.50
| 0.35 | 0.15 | $6,500.00 | $975.00 |
9 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 68.00 | EA |
37.00
| 26.00 | 11.00 | $169.00 | $1,859.00 |
12 | CROWN REDUCTION, TREE (13" - 24" DIAMETER) | 59.00 | EA |
36.00
| 22.00 | 14.00 | $295.00 | $4,130.00 |
13 | CONCRETE REMOVAL (NON-REINFORCED) | 1,330.00 | CY |
1,500.00
| 1,310.73 | 189.27 | $129.00 | $24,415.83 |
14 | UNCLASSIFIED EXCAVATION | 9,105.00 | CY |
1,617.38
| 1,397.75 | 219.63 | $48.00 | $10,542.24 |
15 | CRUSHED MISCELLANEOUS BASE | 1,525.00 | CY |
1,599.84
| 1,380.21 | 219.63 | $58.00 | $12,738.54 |
28 | PCC CURB, TYPE A1-8 | 670.00 | LF |
670.00
| 257.00 | 413.00 | $15.00 | $6,195.00 |
30 | PCC CURB & GUTTER, TYPE A2-8 | 1,717.00 | LF |
2,577.00
| 2,017.00 | 560.00 | $18.00 | $10,080.00 |
31 | PCC WALK, DRIVES & CURB RAMPS, 4" THICK | 49,973.00 | SF |
55,373.00
| 43,328.18 | 12,044.82 | $3.35 | $40,350.15 |
32 | PCC DRIVEWAYS, 6" THICK | 2,114.00 | SF |
1,641.50
| 962.00 | 679.50 | $5.00 | $3,397.50 |
33 | DETECTABLE WARNING SURFACE | 1,620.00 | SF |
1,512.00
| 882.00 | 630.00 | $27.00 | $17,010.00 |
35 | ALLEY INTERSECTION | 104.00 | CY |
99.80
| 38.44 | 61.36 | $210.00 | $12,885.60 |
S-3 | ADDITIONAL TREE REMOVAL | | EA |
13.00
| 9.00 | 4.00 | $640.00 | $2,560.00 |
|