Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
5.00
| 3.00 | 2.00 | $500.00 | $1,000.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.55
| 0.44 | 0.11 | $6,000.00 | $660.00 |
6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.55
| 0.44 | 0.11 | $32,000.00 | $3,520.00 |
7 | OFFICE FACILITIES | 9.00 | MTH |
5.50
| 4.50 | 1.00 | $3,000.00 | $3,000.00 |
8 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $846,000.00 | $169,200.00 |
27 | PCC PAVEMENT | 213.00 | CY |
245.00
| 234.55 | 10.45 | $600.00 | $6,270.00 |
S-3 | DELIVERY OF MANHOLE FRAME/COVER/FACE PLATE MATERIAL | | LS |
1.00
| 0.00 | 1.00 | $4,150.00 | $4,150.00 |