Los Angeles County Public Works
Project Management Division III
Progress Payment 2
Project Name: Avenue K Transmission Main Phase IV 20th Street East to 30th Street East
Contractor: Christensen Brothers General Engineering, Inc.
P.O. Box 1286
Apple Valley, CA 92307
Project ID: WWD4004013
Federal Number(s): None
Original Contract: $2,427,548.60
Awarded: 11/13/2018
Period Ending: 9/6/2019
Board Accepted: 12/7/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $3,000)1.00LS 1.00 0.001.00$3,000.00$3,000.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)6.00MTH 1.00 0.001.00$500.00$500.00
5IMPLEMENTATION OF BMPS1.00LS 0.20 0.000.20$10,600.00$2,120.00
6SHORING OF OPEN EXCAVATIONS1.00LS 0.20 0.000.20$7,000.00$1,400.00
7OFFICE FACILITIES6.00MTH 1.00 0.001.00$4,000.00$4,000.00
8MOBILIZATION1.00LS 0.75 0.000.75$110,000.00$82,500.00
11TRENCH BACKFILL SLURRY (CLASS 140-S-100)2,113.00CY 320.00 0.00320.00$104.00$33,280.00
1324" WATERMAIN, 0.25" THICK STEEL, CML&C, WELDED5,331.00LF 800.00 0.00800.00$274.00$219,200.00
22TRAFFIC CONTROL - STAGE 11.00LS 1.00 0.001.00$25,000.00$25,000.00
26CHANGEABLE MESSAGE SIGN4.00EA 4.00 0.004.00$9,800.00$39,200.00
27FLASHING ARROW SIGN4.00EA 4.00 0.004.00$2,360.00$9,440.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $452,144.00 $32,504.00 $419,640.00
Retained $22,607.20 $1,625.20 $20,982.00
Deducted $0.00 $0.00 $0.00
Due $429,536.80 $30,878.80 $398,658.00



Contact Office Engineer
Gerardo Castillo Jaramillo (626) 458-3197
Contractor Copy  
P Please consider the environment before printing this report.