Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.20
| 0.00 | 0.20 | $10,600.00 | $2,120.00 |
6 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.20
| 0.00 | 0.20 | $7,000.00 | $1,400.00 |
7 | OFFICE FACILITIES | 6.00 | MTH |
1.00
| 0.00 | 1.00 | $4,000.00 | $4,000.00 |
8 | MOBILIZATION | 1.00 | LS |
0.75
| 0.00 | 0.75 | $110,000.00 | $82,500.00 |
11 | TRENCH BACKFILL SLURRY (CLASS 140-S-100) | 2,113.00 | CY |
320.00
| 0.00 | 320.00 | $104.00 | $33,280.00 |
13 | 24" WATERMAIN, 0.25" THICK STEEL, CML&C, WELDED | 5,331.00 | LF |
800.00
| 0.00 | 800.00 | $274.00 | $219,200.00 |
22 | TRAFFIC CONTROL - STAGE 1 | 1.00 | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
26 | CHANGEABLE MESSAGE SIGN | 4.00 | EA |
4.00
| 0.00 | 4.00 | $9,800.00 | $39,200.00 |
27 | FLASHING ARROW SIGN | 4.00 | EA |
4.00
| 0.00 | 4.00 | $2,360.00 | $9,440.00 |