Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Avenue K Transmission Main Phase IV 20th Street East to 30th Street East
Contractor: Christensen Brothers General Engineering, Inc.
P.O. Box 1286
Apple Valley, CA 92307
Project ID: WWD4004013
Federal Number(s): None
Original Contract: $2,427,548.60
Awarded: 11/13/2018
Period Ending: 10/6/2019
Board Accepted: 12/7/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
5IMPLEMENTATION OF BMPS1.00LS 0.50 0.200.30$10,600.00$3,180.00
6SHORING OF OPEN EXCAVATIONS1.00LS 0.50 0.200.30$7,000.00$2,100.00
7OFFICE FACILITIES6.00MTH 2.00 1.001.00$4,000.00$4,000.00
8MOBILIZATION1.00LS 0.95 0.750.20$110,000.00$22,000.00
11TRENCH BACKFILL SLURRY (CLASS 140-S-100)2,113.00CY 1,290.00 320.00970.00$104.00$100,880.00
1324" WATERMAIN, 0.25" THICK STEEL, CML&C, WELDED5,331.00LF 2,549.00 800.001,749.00$274.00$479,226.00
15AIR RELEASE AND VACUUM VALVE ASSEMBLY, 4"4.00EA 1.00 0.001.00$11,400.00$11,400.00
16BUTTERFLY VALVE, 150 PSI WWP, 24"4.00EA 1.00 0.001.00$9,400.00$9,400.00
21VIDEO INSPECTION1.00LS 0.50 0.000.50$5,000.00$2,500.00
23TRAFFIC CONTROL - STAGE 21.00LS 1.00 0.001.00$25,000.00$25,000.00
24TRAFFIC CONTROL - STAGE 31.00LS 1.00 0.001.00$25,000.00$25,000.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 1.00 0.001.00$100.00 $100.00
LOCAL & TARGETED WORKER HIRE POLICYWITHHOLDING 6,068.00 0.006,068.00$1.00 $6,068.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,136,830.00 $452,144.00 $684,686.00
Retained $56,841.50 $22,607.20 $34,234.30
Deducted $6,168.00 $0.00 $6,168.00
Due $1,073,820.50 $429,536.80 $644,283.70



Contact Office Engineer
Gerardo Castillo Jaramillo (626) 458-3197
Contractor Copy  
P Please consider the environment before printing this report.