Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.50
| 0.20 | 0.30 | $10,600.00 | $3,180.00 |
6 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.50
| 0.20 | 0.30 | $7,000.00 | $2,100.00 |
7 | OFFICE FACILITIES | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $4,000.00 | $4,000.00 |
8 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $110,000.00 | $22,000.00 |
11 | TRENCH BACKFILL SLURRY (CLASS 140-S-100) | 2,113.00 | CY |
1,290.00
| 320.00 | 970.00 | $104.00 | $100,880.00 |
13 | 24" WATERMAIN, 0.25" THICK STEEL, CML&C, WELDED | 5,331.00 | LF |
2,549.00
| 800.00 | 1,749.00 | $274.00 | $479,226.00 |
15 | AIR RELEASE AND VACUUM VALVE ASSEMBLY, 4" | 4.00 | EA |
1.00
| 0.00 | 1.00 | $11,400.00 | $11,400.00 |
16 | BUTTERFLY VALVE, 150 PSI WWP, 24" | 4.00 | EA |
1.00
| 0.00 | 1.00 | $9,400.00 | $9,400.00 |
21 | VIDEO INSPECTION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $5,000.00 | $2,500.00 |
23 | TRAFFIC CONTROL - STAGE 2 | 1.00 | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
24 | TRAFFIC CONTROL - STAGE 3 | 1.00 | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |