Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.80
| 0.50 | 0.30 | $10,600.00 | $3,180.00 |
6 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.80
| 0.50 | 0.30 | $7,000.00 | $2,100.00 |
7 | OFFICE FACILITIES | 6.00 | MTH |
3.00
| 2.00 | 1.00 | $4,000.00 | $4,000.00 |
8 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $110,000.00 | $5,500.00 |
11 | TRENCH BACKFILL SLURRY (CLASS 140-S-100) | 2,113.00 | CY |
2,113.00
| 1,290.00 | 823.00 | $104.00 | $85,592.00 |
13 | 24" WATERMAIN, 0.25" THICK STEEL, CML&C, WELDED | 5,331.00 | LF |
4,766.00
| 2,549.00 | 2,217.00 | $274.00 | $607,458.00 |
14 | 36" STEEL CASING | 83.00 | LF |
51.00
| 0.00 | 51.00 | $570.00 | $29,070.00 |
15 | AIR RELEASE AND VACUUM VALVE ASSEMBLY, 4" | 4.00 | EA |
2.00
| 1.00 | 1.00 | $11,400.00 | $11,400.00 |
16 | BUTTERFLY VALVE, 150 PSI WWP, 24" | 4.00 | EA |
2.00
| 1.00 | 1.00 | $9,400.00 | $9,400.00 |
18 | PUMP WELL ASSEMBLY, TOP DRAINING,STD PLAN W-53, STYLE A | 5.00 | EA |
4.00
| 0.00 | 4.00 | $5,300.00 | $21,200.00 |
20 | CATHODIC PROTECTION ANODE AND TEST STATION | 4.00 | EA |
3.00
| 0.00 | 3.00 | $5,200.00 | $15,600.00 |
21 | VIDEO INSPECTION | 1.00 | LS |
0.80
| 0.50 | 0.30 | $5,000.00 | $1,500.00 |
25 | TRAFFIC CONTROL - STAGE 4 | 1.00 | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
S-2 | UNMARKED UTILITY DELAY STA. 12+05 | | T&M |
3,446.90
| 0.00 | 3,446.90 | $1.00 | $3,446.90 |
S-3 | DELAY - UNMARKED STORM DRAIN STA. 26+70 | | T&M |
5,594.77
| 0.00 | 5,594.77 | $1.00 | $5,594.77 |
S-4 | UTILITY DELAY AT STA. 10+92 | | T&M |
3,698.14
| 0.00 | 3,698.14 | $1.00 | $3,698.14 |
S-5 | MODIFY AIR VAC LATERAL - UTILITY INTERFERENCE STA. 10+92 | | LS |
1.00
| 0.00 | 1.00 | $2,400.00 | $2,400.00 |
S-6 | DESIGN CHANGE AT STA. 36+75 DUE TO SCE LINE CONFLICT | | LS |
1.00
| 0.00 | 1.00 | $22,000.00 | $22,000.00 |
S-7 | DELAY - UNMARKED STORM DRAIN STA. 38+81 | | T&M |
4,884.03
| 0.00 | 4,884.03 | $1.00 | $4,884.03 |
S-8 | DELAY - UNMARKED STORM DRAIN STA. 38+81 | | T&M |
5,294.96
| 0.00 | 5,294.96 | $1.00 | $5,294.96 |
S-10 | POTHOLE EXISTING SERVICE LINES | | LS |
1.00
| 0.00 | 1.00 | $5,900.00 | $5,900.00 |
|