Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.85
| 0.80 | 0.05 | $10,600.00 | $530.00 |
6 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.90
| 0.80 | 0.10 | $7,000.00 | $700.00 |
7 | OFFICE FACILITIES | 6.00 | MTH |
4.00
| 3.00 | 1.00 | $4,000.00 | $4,000.00 |
13 | 24" WATERMAIN, 0.25" THICK STEEL, CML&C, WELDED | 5,331.00 | LF |
5,321.00
| 4,766.00 | 555.00 | $274.00 | $152,070.00 |
14 | 36" STEEL CASING | 83.00 | LF |
79.00
| 51.00 | 28.00 | $570.00 | $15,960.00 |
15 | AIR RELEASE AND VACUUM VALVE ASSEMBLY, 4" | 4.00 | EA |
4.00
| 2.00 | 2.00 | $11,400.00 | $22,800.00 |
16 | BUTTERFLY VALVE, 150 PSI WWP, 24" | 4.00 | EA |
4.00
| 2.00 | 2.00 | $9,400.00 | $18,800.00 |
18 | PUMP WELL ASSEMBLY, TOP DRAINING,STD PLAN W-53, STYLE A | 5.00 | EA |
5.00
| 4.00 | 1.00 | $5,300.00 | $5,300.00 |
20 | CATHODIC PROTECTION ANODE AND TEST STATION | 4.00 | EA |
4.00
| 3.00 | 1.00 | $5,200.00 | $5,200.00 |
21 | VIDEO INSPECTION | 1.00 | LS |
1.00
| 0.80 | 0.20 | $5,000.00 | $1,000.00 |
S-9 | DELAY - MIS-MARKED UTILITIY STA. 52+00 | | LS |
1.00
| 0.00 | 1.00 | $12,000.00 | $12,000.00 |
S-12 | MODIFY AIR/VAC LATERAL AT STA. 37+50 | | LS |
1.00
| 0.00 | 1.00 | $2,400.00 | $2,400.00 |
S-13 | DELAY - CONFLICTING WATER & GAS LINES STA. 24+87 | | T&M |
2,609.23
| 0.00 | 2,609.23 | $1.00 | $2,609.23 |
S-14 | MODIFY AIR/VAC LATERAL AT STA. 24+87 | | LS |
1.00
| 0.00 | 1.00 | $2,400.00 | $2,400.00 |
S-17 | MODIFY AIR/VAC LATERAL AT STA. 62+01 | | LS |
1.00
| 0.00 | 1.00 | $2,400.00 | $2,400.00 |