Los Angeles County Public Works
Project Management Division III
Progress Payment 6
Project Name: Avenue K Transmission Main Phase IV 20th Street East to 30th Street East
Contractor: Christensen Brothers General Engineering, Inc.
P.O. Box 1286
Apple Valley, CA 92307
Project ID: WWD4004013
Federal Number(s): None
Original Contract: $2,427,548.60
Awarded: 11/13/2018
Period Ending: 1/7/2020
Board Accepted: 12/7/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)6.00MTH 4.00 2.002.00$500.00$1,000.00
5IMPLEMENTATION OF BMPS1.00LS 0.90 0.850.05$10,600.00$530.00
7OFFICE FACILITIES6.00MTH 5.00 4.001.00$4,000.00$4,000.00
1212" WATERMAIN, 0.25" THICK STEEL, CML&C35.00LF 9.00 0.009.00$184.00$1,656.00
17GATE VALVE, 200 PSI WWP, 12"5.00EA 2.00 0.002.00$3,500.00$7,000.00
S-11DELAY - CONFLICTING GAS LINE STA. 37+50 T&M 2,641.47 0.002,641.47$1.00$2,641.47
S-15DELAY - UNMARKED STORM DRAIN STA. 63+00 T&M 10,227.22 0.0010,227.22$1.00$10,227.22
S-18HOT TAP EXISTING 12" DUCTILE MAIN LS 1.00 0.001.00$10,000.00$10,000.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL & TARGETED WORKER HIRE POLICYWITHHOLDING 24,275.00 18,204.006,071.00$1.00 $6,071.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,296,772.72 $2,259,718.03 $37,054.69
Retained $114,838.64 $112,985.91 $1,852.73
Deducted $25,175.00 $19,104.00 $6,071.00
Due $2,156,759.08 $2,127,628.12 $29,130.96



Contact Office Engineer
Gerardo Castillo Jaramillo (626) 458-3197
Contractor Copy  