Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
4.00
| 2.00 | 2.00 | $500.00 | $1,000.00 |
5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.90
| 0.85 | 0.05 | $10,600.00 | $530.00 |
7 | OFFICE FACILITIES | 6.00 | MTH |
5.00
| 4.00 | 1.00 | $4,000.00 | $4,000.00 |
12 | 12" WATERMAIN, 0.25" THICK STEEL, CML&C | 35.00 | LF |
9.00
| 0.00 | 9.00 | $184.00 | $1,656.00 |
17 | GATE VALVE, 200 PSI WWP, 12" | 5.00 | EA |
2.00
| 0.00 | 2.00 | $3,500.00 | $7,000.00 |
S-11 | DELAY - CONFLICTING GAS LINE STA. 37+50 | | T&M |
2,641.47
| 0.00 | 2,641.47 | $1.00 | $2,641.47 |
S-15 | DELAY - UNMARKED STORM DRAIN STA. 63+00 | | T&M |
10,227.22
| 0.00 | 10,227.22 | $1.00 | $10,227.22 |
S-18 | HOT TAP EXISTING 12" DUCTILE MAIN | | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |