Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: Avenue K Transmission Main Phase IV 20th Street East to 30th Street East
Contractor: Christensen Brothers General Engineering, Inc.
P.O. Box 1286
Apple Valley, CA 92307
Project ID: WWD4004013
Federal Number(s): None
Original Contract: $2,427,548.60
Awarded: 11/13/2018
Period Ending: 3/6/2020
Board Accepted: 12/7/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)6.00MTH 6.00 5.001.00$500.00$500.00
5IMPLEMENTATION OF BMPS1.00LS 1.00 0.900.10$10,600.00$1,060.00
9COLD MILL AC PAVEMENT (> 1-1/2 - 3")65,340.00SF 65,340.00 0.0065,340.00$0.39$25,482.60
10AC PAVEMENT(SURFACE COURSE)790.00TON 790.00 0.00790.00$147.00$116,130.00
1324" WATERMAIN, 0.25" THICK STEEL, CML&C, WELDED5,331.00LF 5,331.00 5,321.0010.00$274.00$2,740.00
S-19REPAIR 4" DAMAGED CONDUITS LS 1.00 0.001.00$1,200.00$1,200.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,513,986.16 $2,366,873.56 $147,112.60
Retained $125,699.31 $118,343.68 $7,355.63
Deducted $25,175.00 $25,175.00 $0.00
Due $2,363,111.85 $2,223,354.88 $139,756.97