Los Angeles County Public Works
Project Management Division III
Progress Payment 9
Project Name: Avenue K Transmission Main Phase IV 20th Street East to 30th Street East
Contractor: Christensen Brothers General Engineering, Inc.
P.O. Box 1286
Apple Valley, CA 92307
Project ID: WWD4004013
Federal Number(s): None
Original Contract: $2,427,548.60
Awarded: 11/13/2018
Period Ending: 4/6/2020
Board Accepted: 12/7/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
9COLD MILL AC PAVEMENT (> 1-1/2 - 3")65,340.00SF 70,807.00 65,340.005,467.00$0.39$2,132.13
10AC PAVEMENT(SURFACE COURSE)790.00TON 1,176.12 790.00386.12$147.00$56,759.64
28JOBS COORDINATOR (ALLOWANCE OF $10,000)10,000.00AL 10,000.00 0.0010,000.00$1.00$10,000.00
S-20REMOVE & REINSTALL 24" WATER MAIN SECTION FOR INTERCONNECTION 1 LS 1.00 0.001.00$19,000.00$19,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,601,877.93 $2,513,986.16 $87,891.77
Retained $130,093.90 $125,699.31 $4,394.59
Deducted $25,175.00 $25,175.00 $0.00
Due $2,446,609.03 $2,363,111.85 $83,497.18



Contact Office Engineer
Gerardo Castillo Jaramillo (626) 458-3197