Bid Price History

La Tuna Fire - Sunset Upper Debris Basin Dam Modification
$599,800.00
11/07/2017
534 (A4)
4
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.07.021SHORING OF OPEN EXCAVATIONS 0.50 1LS$10,000.00$3,000.00 $3,000.00 $32,550.00$31,100.00
300.02.003UNCLASSIFIED EXCAVATION 5.51 245CY$145.00$135.00 $33,075.00 $152.78$175.00
300.04.013STRUCTURE EXCAVATION (RETAINING WALL) 4.10 182CY$120.00$135.00 $24,570.00 $568.75$300.00
300.04.033STRUCTURE BACKFILL (RETAINING WALL) 2.40 120CY$120.00$120.00 $14,400.00 $324.50$235.00
300.05.002IMPORTED BORROW 1.07 80CY$70.00$80.00 $6,400.00 $64.00$60.00
301.02.005CRUSHED MISCELLANEOUS BASE 1.50 130CY$130.00$69.00 $8,970.00 $158.50$150.00
302.06.003PCC PAVEMENT 5.42 130CY$370.00$250.00 $32,500.00 $470.00$515.00
304.02.007METAL HAND RAILINGS PER STD PLAN 606 0.61 22LF$300.00$167.00 $3,674.00 $276.25$300.00
304.06.003REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) 0.46 250LF$45.00$11.00 $2,750.00 $23.08$25.65
304.06.019MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK) 3.30 150LF$100.00$132.00 $19,800.00 $165.50$153.50
 REINFORCED CONCRETE LEFT ABUTMENT EXTENSION PER SHEET 4 5.59 22CY$1,200.00$1,525.00 $33,550.00 $2,353.75$1,612.50
 REMOVE AND REINSTALL EXISTING BARRIERS 0.42 10LF$240.00$250.00 $2,500.00 $656.50$688.00
 REMOVE METAL HAND RAILINGS 0.16 22LF$15.00$43.00 $946.00 $73.98$76.45
 SLOPE PROTECTION GUTTER PER DETAIL "N", SHEET 6 1.21 104LF$40.00$70.00 $7,280.00 $155.00$175.00
 CONCRETE REMOVAL (REINFORCED) (SPILLWAY) 4.39 34CY$450.00$775.00 $26,350.00 $1,698.50$1,309.50
 REINFORCED CONCRETE RETAINING WALL PER CALTRANS STD. PLAN B3-4A (MODIFIED) 14.99 81CY$1,100.00$1,110.00 $89,910.00 $1,677.50$1,500.00
 REINFORCED CONCRETE PARAPET WALL EXTENSION PER SECTION D-D, SHEET 3 3.63 13CY$1,730.00$1,675.00 $21,775.00 $2,808.75$2,087.50
 REINFORCED CONCRETE PARAPET WALL EXTENSION PER SECTION C-C, SHEET 3 4.47 16CY$1,700.00$1,675.00 $26,800.00 $2,723.75$1,987.50
 REINFORCED CONCRETE OUTLET TOWER EXTENSION 3.67 1LS$9,000.00$22,000.00 $22,000.00 $60,341.25$50,682.50
 REINFORCED CONCRETE SPILLWAY EXTENSION 34.72 75CY$1,140.00$2,777.00 $208,275.00 $2,744.25$2,188.50
 REINFORCED CONCRETE RIGHT ABUTMENT EXTENSION PER SHEET 4 1.27 5CY$1,200.00$1,525.00 $7,625.00 $3,051.25$2,800.00
 OBJECT MARKERS PER CALTRANS STD. PLAN A73A, TYPE L-2 0.61 10EA$240.00$365.00 $3,650.00 $264.00$318.00
 Total Percent100   Total Amount$599,800.00