Bid Price History

Live Oak Dam and Reservoir - Inlet/Outlet Works Rehabilitation Project
$1,954,800.00
09/04/2018
571 (A5)
7
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.05 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.07.003IMPLEMENTATION OF BMPS 2.56 1LS$50,000.00$50,000.00 $50,000.00 $44,371.43$45,000.00
001.08.005OFFICE FACILITIES 0.92 6MTH$2,500.00$3,000.00 $18,000.00 $2,654.57$2,962.00
001.09.003MOBILIZATION 5.12 1LS$90,000.00$100,000.00 $100,000.00 $144,979.57$150,000.00
300.01.003CLEARING AND GRUBBING 1.28 1LS$15,000.00$25,000.00 $25,000.00 $33,553.43$27,174.00
300.01.067CONCRETE REMOVAL (REINFORCED) 0.10 2CY$2,600.00$1,000.00 $2,000.00 $2,922.14$2,000.00
300.02.003UNCLASSIFIED EXCAVATION 5.12 2500CY$40.00$40.00 $100,000.00 $55.14$40.00
300.03.003UNCLASSIFIED FILL 1.53 600CY$20.00$50.00 $30,000.00 $44.00$50.00
300.10.003STABILIZATION GEOTEXTILE 0.52 410SY$25.00$25.00 $10,250.00 $33.16$20.00
300.12.0031" CRUSHED ROCK 0.48 62CY$60.00$150.00 $9,300.00 $127.43$150.00
301.02.003CRUSHED AGGREGATE BASE 0.69 135CY$150.00$100.00 $13,500.00 $111.57$120.00
302.06.003PCC PAVEMENT 3.07 120CY$500.00$500.00 $60,000.00 $598.71$500.00
304.02.007METAL HAND RAILINGS PER STD PLAN 606 2.18 213LF$200.00$200.00 $42,600.00 $188.00$200.00
 CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH) 0.15 6MTH$500.00$500.00 $3,000.00 $500.00$500.00
 CONTROL PANELS 1.28 1LS$116,600.00$25,000.00 $25,000.00 $39,368.86$39,082.00
 DAVIT HOIST 0.51 1LS$10,000.00$10,000.00 $10,000.00 $15,768.29$10,000.00
 DRILL AND GROUT DOWEL OR ANCHOR 1.18 154LF$70.00$150.00 $23,100.00 $160.43$150.00
 DRILL AND BOND ANCHOR (EPOXY CARTRIDGE) 0.35 45LF$125.00$150.00 $6,750.00 $224.57$142.00
 DISPOSAL OF LEAD CONTAINING WASTE/DEBRIS 0.77 1LS$1,500.00$15,000.00 $15,000.00 $14,366.00$10,782.00
 EXISTING TRASH RACK REHABILITATION 1.28 1LS$27,000.00$25,000.00 $25,000.00 $29,664.43$25,000.00
 EXPANDED METAL ENCLOSURE 2.56 1LS$46,000.00$50,000.00 $50,000.00 $64,562.14$50,000.00
 ENVIRONMENTALLY SENSITIVE AREA (ESA) FENCING 0.22 215LF$3.80$20.00 $4,300.00 $55.14$12.00
 ELECTRICAL WORK 12.79 1LS$252,810.00$250,000.00 $250,000.00 $214,747.86$248,500.00
 ELECTRIC MOTOR OPERATORS AND APPURTENANCES 1.28 1LS$50,000.00$25,000.00 $25,000.00 $31,857.29$28,669.00
 GEOGRID 0.90 500SY$20.00$35.00 $17,500.00 $32.17$15.00
 2-1/2" TO 5" ROCK 4.22 550CY$100.00$150.00 $82,500.00 $131.57$150.00
 IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN 0.26 1LS$5,000.00$5,000.00 $5,000.00 $27,183.14$26,642.00
 IMPLEMENTATION OF THE SURFACE WATER DIVERSION AND DEWATERING PLAN 7.67 1LS$100,000.00$150,000.00 $150,000.00 $126,022.71$135,380.00
 IMPLEMENTATION OF THE SITE SPECIFIC HEALTH AND SAFETY PLAN 0.77 1LS$5,000.00$15,000.00 $15,000.00 $22,196.29$14,274.00
 INCLINED TRASH RACK 2.05 1LS$35,000.00$40,000.00 $40,000.00 $41,527.86$40,000.00
 LOW FLOW DISCHARGE VALVES AND PIPING SYSTEM 2.56 1LS$50,000.00$50,000.00 $50,000.00 $85,279.43$80,000.00
 MISCELLANEOUS MECHANICAL WORK 2.05 1LS$46,600.00$40,000.00 $40,000.00 $69,220.57$43,824.00
 OUTLET TUNNEL REPAIR 2.56 1LS$50,000.00$50,000.00 $50,000.00 $76,186.43$55,895.00
 PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $2,500) 0.13 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 PREPARATION OF THE SURFACE WATER DIVERSION AND DEWATERING PLAN (STIPULATED UNIT PRICE OF $5,000) 0.26 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
 PREPARATION OF THE SITE SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $2,500) 0.13 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 REINFORCED CONCRETE ACCESS ROAD 0.77 30CY$1,000.00$500.00 $15,000.00 $862.14$750.00
 REINFORCED CONCRETE RISER 5.12 1LS$60,000.00$100,000.00 $100,000.00 $97,546.00$100,000.00
 REMOVE AND REPLACE CHAIN LINK FENCE 5' HIGH WITH BARBED WIRE 0.10 20LF$150.00$100.00 $2,000.00 $169.29$170.00
 REMOVE EXISTING IMPROVEMENTS 1.79 1LS$51,000.00$35,000.00 $35,000.00 $88,563.29$75,000.00
 SECURITY CAMERA 0.15 1LS$2,000.00$3,000.00 $3,000.00 $4,622.00$3,000.00
 SECURITY GATE AND FENCE 0.97 1LS$20,000.00$19,000.00 $19,000.00 $28,892.57$25,000.00
 SLIPLINE 10" STEEL PIPE WITH 8" STAINLESS STEEL PIPE INCLUDING ANNULAR SPACE GROUTING AND APPURTENANT WORK 2.15 60LF$500.00$700.00 $42,000.00 $759.71$683.00
 STILLING WELL 2.56 1LS$27,000.00$50,000.00 $50,000.00 $84,667.57$60,000.00
 STAINLESS STEEL STEPS PER STD PLAN 635 1.33 52EA$500.00$500.00 $26,000.00 $561.43$500.00
 THROTTLING KNIFE GATE VALVE 2.56 1LS$51,300.00$50,000.00 $50,000.00 $51,783.86$40,000.00
 10-INCH DIAMETER STAINLESS STEEL PIPE 0.26 10LF$300.00$500.00 $5,000.00 $773.00$660.00
 CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $3000) 0.15 1LS$3,000.00$3,000.00 $3,000.00 $3,000.00$3,000.00
 6" DIAMETER PERFORATED PVC PIPE, SCHEDULE 80 0.26 50LF$60.00$100.00 $5,000.00 $101.07$100.00
 6" DIAMETER PVC PIPE, SCHEDULE 80 0.05 10LF$60.00$100.00 $1,000.00 $159.61$100.00
 CLEAN AND PAINT EXISTING STEEL 1.53 1LS$25,000.00$30,000.00 $30,000.00 $39,511.14$33,138.00
 CAST IRON SLIDE GATE REHABILITATION 4.09 1LS$50,000.00$80,000.00 $80,000.00 $85,305.86$78,921.00
 CHAIN GATE 0.26 1LS$500.00$5,000.00 $5,000.00 $4,935.29$2,747.00
 ACCESS PLATFORMS AND STAIRS 6.39 1LS$115,000.00$125,000.00 $125,000.00 $186,320.14$150,000.00
 Total Percent100   Total Amount$1,954,800.00