2308GG-001.01S1 |
Civic Center Central Plant Boilers and Chillers Replacement Project |
$76,338.49 |
Expedite Chiller installation and start-up. |
2308GG-003.01B1 |
Camp Kilpatrick Miller Stormwater Maintenance Work |
$61,021.02 |
Stormwater Maintenance Work. |
2308GG-004.01S1 |
Norwalk Sheriff Station DM-2. |
$298,252.85 |
Air handling units, and fire alarm replacement, fire sprinkler repair. |
2308GG-004.02S1 |
Norwalk Sheriff Station DM-2. |
$389,949.97 |
HVAC Installation, Fire Alarm replacement, and roofing. |
2308GG-004.03S1 |
Norwalk Sheriff Station DM-2 |
$104,198.95 |
HVAC installation, fire alarm replacement, and installation. |
2308GG-005.01S2 |
LAC+USC ER-CT-UPS Project |
$12,012.53 |
Provide material to replace existing refrigerant piping from the condenser unit to FC-1 per RFI 28. |
2308GG-006.01S1 |
West Hollywood Station DM-2 |
$26,102.90 |
Replacement of the fire protection system. |
2308GG-007.01B1 |
MLK BHC Waterproofing |
$5,916.62 |
Repair and restoration of BHC basement waterproofing and hardscape. |
2308GG-008.01B2 |
HOA Seismic Upgrade-Architectural Investigations |
$41,514.42 |
The removal of existing granite and terracotta wall panels at locations selected by the LA County or its representatives to confirm the installation system and status of the panels illustrated on the original as-builts provided to the team; to assess the potential impacts of their removal and reinstallation and to verify the existing conditions of the entire wall cladding assembly (especially below grade). |
2308GG-009.01B1 |
Carolyn Rosas Park - ADA Improvements Project |
$266,852.63 |
Upgrade existing restrooms to meet current ADA, re-stripe ADA parking. |
2308GG-009.02S1 |
Carolyn Rosas Park - ADA Improvements Project |
$9,419.56 |
Demo existing curb alongside path of travel and re-pour per RFI 001. |
2308GG-009.03S1 |
Carolyn Rosas Park - ADA Improvements Project |
$6,392.78 |
Perform restroom wall repairs as directed in RFI 002. |
2308GG-009.04S1 |
Carolyn Rosas Park - ADA Improvements Project |
$2,492.96 |
Replace damaged water shut off valve in women's restroom. |
2308GG-009.05S1 |
Carolyn Rosas Park - ADA Improvements Project |
$8,493.45 |
Remove sink in men's restroom per ADA, relocate hand dryer. |
2308GG-010.01S1 |
Pomona Public Health Center Deferred Maintenance Repairs.. |
$118,765.97 |
Provide and install building signage. |
2308GG-011.01S1 |
Pomona Wellness Community Center |
$31,119.36 |
¿ Complete landscaping modifications ¿ Complete Parktree Suite modifications |
2308GG-012.01B1 |
Brackett Field Sewer Pump & Force Main Replacement. |
$1,201,532.98 |
Replace existing sewer force main and lift station. Construct sewer lift station, and 2,000 feet 4" force main and apparatus directly drilling and open trenching. |
2308GG-013.01B1 |
Sybil Brand Institute Sheriffs Road Storm Drain Repair |
$139,442.61 |
Sybil Brand Institute Sheriffs Road Storm Drain Repair |
2308GG-013.02S1 |
Sybil Brand Institute Sheriff's Road Storm Drain Repair |
$3,359.21 |
Supplemental work order for one (1) tree removal (approximately 25" D.B.H.) near drainage trench. |
2308GG-015.01S1 |
Willowbrook Senior Center ADA Upgrades Project |
$28,538.79 |
Upgrade existing facility to comply current ADA compliance guidelines. |
2308GG-015.02S3 |
Willowbrook Senior Center ADA Upgrades Project |
$6,365.09 |
Upgrade existing facility to comply with current ADA compliance guidelines. |
2308GG-015.03S2 |
Willowbrook Senior Center ADA Upgrades Project.. |
$1,597.60 |
Upgrade existing facility to comply current ADA compliance guidelines. |
2308GG-016.01S1 |
Curtis Tucker Public Health Center Deferred Maintenance Repairs Project |
$49,142.48 |
provide and install additional duct smoke detectors, vision lite, and additional 6 balancing dampers. |