| Item |
Description |
Unit of Measure |
Estimated Quantity |
| 1 |
CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) |
LS |
1 |
| 2 |
CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
MTH |
5 |
| 3 |
CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
LS |
1 |
| 4 |
IMPLEMENTATION OF THE LTWHP |
LS |
1 |
| 5 |
IMPLEMENTATION OF BMPS |
LS |
1 |
| 6 |
PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) |
LS |
1 |
| 7 |
IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN |
LS |
1 |
| 8 |
REMOVAL AND DISPOSAL OF LBP/LCP |
LS |
1 |
| 9 |
REMOVAL AND DISPOSAL OF ASBESTOS-CONTAINING MATERIAL |
LS |
1 |
| 10 |
PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) |
LS |
1 |
| 11 |
IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN |
LS |
1 |
| 12 |
PREPARATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $3,000) |
LS |
1 |
| 13 |
IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN |
LS |
1 |
| 14 |
OFFICE FACILITIES |
MTH |
6 |
| 15 |
MOBILIZATION |
LS |
1 |
| 16 |
DEMOLITION |
LS |
1 |
| 17 |
OPERATIONAL TESTS |
LS |
1 |
| 18 |
TRASH RACK |
LS |
1 |
| 19 |
MISCELLANEOUS MECHANICAL WORKS |
LS |
1 |
| 20 |
48 INCHES VERTICAL AXIAL FLOW PROPELLER PUMP WITH ELECTRIC MOTOR |
EA |
3 |
| 21 |
36 INCHES VERTICAL AXIAL FLOW PROPELLER PUMP WITH EXISTING RIGHT ANGLE GEAR DRIVE |
EA |
2 |
| 22 |
ELECTRICAL WORK |
LS |
1 |
| 23 |
SWITCHBOARD, MOTOR CONTROL CENTER, AND BUSDUCT |
LS |
1 |
| 24 |
REMOVAL OF EXISTING STEEL STRUCTURES |
LS |
1 |
| 25 |
STRUCTURAL STEEL* |
LB |
28,317 |
| 26 |
STAIR TREADS |
LS |
1 |
| 27 |
FIBERGLASS REINFORCED POLYMER GRATING |
SF |
1,002 |
| 28 |
FIBERGLASS REINFORCED POLYMER HANDRAIL |
LF |
296 |
| 29 |
DRILL AND BOND DOWEL (EPOXY CARTRIDGE)* |
LF |
159 |
| 30 |
ACCESS HATCH |
LS |
1 |
| 31 |
STRUCTURE CONCRETE* |
CY |
2 |
| 32 |
BAR REINFORCING STEEL* |
LB |
474 |
| 33 |
CONCRETE REMOVAL (REINFORCED)* |
CY |
1 |
| 34 |
DAVIT SLEEVE |
LS |
1 |
| 35 |
TRAFFIC CONTROL |
LS |
1 |