Item |
Description |
Unit of Measure |
Estimated Quantity |
1 |
CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) |
LS |
1 |
2 |
CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
MTH |
3 |
3 |
CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
LS |
1 |
4 |
PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) |
LS |
1 |
5 |
IMPLEMENTATION OF THE SWPPP |
LS |
1 |
6 |
MOBILIZATION |
LS |
1 |
7 |
CLEARING AND GRUBBING |
LS |
1 |
8 |
CONCRETE REMOVAL (NON-REINFORCED) |
CY |
2 |
9 |
UNCLASSIFIED EXCAVATION |
CY |
940 |
10 |
SHOULDER GRADING |
MI |
3 |
11 |
IMPORTED BORROW |
CY |
505 |
12 |
CRUSHED MISCELLANEOUS BASE |
CY |
46 |
13 |
COLD MILL AC PAVEMENT (0 - 1-1/2") |
SF |
7,805 |
14 |
COLD MILL AC PAVEMENT (> 1-1/2 - 3") |
SF |
241,863 |
15 |
AC DIKE, TYPE A PER CALTRANS STD PLAN A87B |
LF |
40 |
16 |
AC DIKE, TYPE C PER CALTRANS STD PLAN A87B |
LF |
433 |
17 |
AC PAVEMENT |
TON |
1,066 |
18 |
AC PAVEMENT(DRIVEWAYS) |
TON |
137 |
19 |
AC PAVEMENT(INVERTED SHOULDERS) |
TON |
534 |
20 |
AC PAVEMENT(DIGOUTS) |
TON |
42 |
21 |
AC DIKE, TYPE F PER CALTRANS STD PLAN A87B |
LF |
446 |
22 |
DOUBLE ADJUST MANHOLE |
EA |
12 |
23 |
ASPHALT RUBBER HOT MIX |
TON |
14,201 |
24 |
ASPHALT RUBBER HOT MIX (TEST STRIP) |
TON |
500 |
25 |
ASPHALT RUBBER AND AGGREGATE MEMBRANE |
SY |
26,333 |
26 |
CIR AC PAVEMENT, 3" THICK |
SY |
116,830 |
27 |
EMULSIFIED RECYCLING AGENT |
TON |
698 |
28 |
CIRACP MIX DESIGN (STIPULATED UNIT PRICE OF $10,000) |
LS |
1 |
29 |
REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) |
LF |
2,565 |
30 |
TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE |
LB |
42,640 |
31 |
ADJUST GUARDRAIL |
LF |
3,208 |
32 |
ADJUST GUARDRAIL AT BURIED END POST |
EA |
4 |
33 |
METAL BEAM GUARD RAILING (STEEL POST W/ PLASTIC BLOCK) |
LF |
414 |
34 |
MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK) |
LF |
620 |
35 |
FLARED TERMINAL SYSTEM (TYPE X-TENSION- W/ STEEL POSTS) |
EA |
3 |
36 |
IN-LINE TERMINAL SYSTEM (TYPE X-TENSION - W/ STEEL POST) |
EA |
51 |
37 |
IN-LINE TERMINAL SYSTEM (TYPE SKT-SP-MGS) |
EA |
4 |
38 |
MIDWEST GUARDRAIL SYSTEM END ANCHOR ASSEMBLY (TYPE SFT) PER STD PLAN A77S1 |
EA |
1 |
39 |
MIDWEST GUARDRAIL SYSTEM BURIED POST END ANCHOR PER STD PLAN A77T2 |
EA |
1 |
40 |
TRANSITION RAILING (TYPE WB) |
EA |
4 |
41 |
ANCHOR BLOCK FOR TRANSITION RAILING CONNECTION PER STD PLAN A77U3 |
EA |
4 |
42 |
INSTALL FIRE HYDRANT LOCATION RPM |
EA |
25 |
43 |
TRAFFIC CONTROL |
LS |
1 |
44 |
FLASHING ARROW SIGN |
EA |
1 |
45 |
CHANGEABLE MESSAGE SIGN |
EA |
2 |