LA County Public Works
Toggle navigation
dpw.lacounty.gov
  • Menu 
    • DPW Home
    • Do Business with Public Works
    • Local Small Business Enterprise | LSBE
    • Disabled Veteran Business Enterprise | DVBE
    • Social Enterprise | SE
    • Prime Contractor
    • Local and Targeted Worker Hire Program
    • Community Workforce Agreement
    • Get Contracts
    • Opportunities
    • Active As-Needed
    • Active JOC Contracts
    • Get Informed
    • Calendar of Events
    • Contact Us
    • Resources
  1. Home
  2. Business Opportunities
  3. Project Summary

Project Summary

RDC0016069
STPL-5953(730)
Allen Avenue, et al.
Vicinity maps:
  • Mariposa Street - Lake Avenue to Maiden Lane
  • Allen Avenue - Altadena Drive to New York Drive
Roadway Resurfacing
5/1/2018
6/27/2018
6/20/2018
10/16/2018
8/9/2019
Altadena
Colin S McCarter
(626) 458-7892
Send Email
$1,431,495.25 View Bid Results
Access Pacific, Inc.
2835 Sierra Grande Street
Pasadena CA 91107
View Plan Holders
Payments
Period EndingPayment Type
12/16/2019 Retention
09/03/2019 Progress
08/05/2019 Progress
07/08/2019 Progress
05/06/2019 Progress
04/11/2019 Progress
03/06/2019 Progress
02/06/2019 Progress
01/06/2019 Progress
12/11/2018 Progress
Documents
DocumentNotesDatePagesSize
Bid Summary
  • Access Pacific, Inc.
  • $1.43M
6/4/2018 10
Adopt, Advertise, & Award
  • SD 5
  • $1.3-1.7 Million
  • Road Fund and Measure R Local Return Fund '17-'18
5/1/2018 5
Addendum Addendum No. 1 - Davis-Bacon Wage Determinations Update 5/22/2018 1 26.09 kb
Special Provisions Notice Inviting Bids, Special Provisions, & Sample Agreement 5/1/2018 222 5.51 Mb
Notice Inviting Bids Notice Inviting Bids 5/1/2018 5 25.35 kb
Instructions To Bidders Instructions to Bidders (January 2013) 5/1/2018 22 287.08 kb
Bid Proposal Bid Proposal 5/1/2018 28 275.51 kb
Plans (as advertised) Plans 3/5/2018 28 12.65 Mb

Bid Items
Item Description Unit of Measure Estimated Quantity
1 CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) LS 1
2 CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) MTH 4
3 CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) LS 1
4 PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) LS 1
5 IMPLEMENTATION OF THE SWPPP LS 1
6 OFFICE FACILITIES LS 1
7 MOBILIZATION LS 1
8 CLEARING AND GRUBBING LS 1
9 ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) EA 1
10 CROWN REDUCTION, TREE (13" - 24" DIAMETER) EA 1
11 REMOVE EXISTING CHAIN LINK FENCE LF 120
12 CONCRETE REMOVAL (NON-REINFORCED) CY 206
13 CONCRETE REMOVAL (REINFORCED) CY 188
14 UNCLASSIFIED EXCAVATION CY 525
15 STRUCTURE EXCAVATION CY 51
16 CRUSHED MISCELLANEOUS BASE CY 149
17 TRENCH BACKFILL SLURRY (CLASS 270-E-500) CY 29
18 COLD MILL AC PAVEMENT (0 - 1-1/2") SF 159,091
19 COLD MILL AC PAVEMENT (> 3") SF 28,497
20 AC CURB, TYPE D1-8 LF 376
21 AC CURB, TYPE D2 LF 36
22 AC PAVEMENT TON 535
23 AC PAVEMENT(PATCH BACK) TON 56
24 AC PAVEMENT(DRIVEWAYS) TON 1
25 AC PAVEMENT (SIDEWALK) TON 59
26 AC PAVEMENT (SHOULDERS AT GUARDRAIL) TON 84
27 RECONSTRUCT MANHOLE EA 3
28 DOUBLE ADJUST MANHOLE EA 9
29 PCC PAVEMENT CY 122
30 ASPHALT RUBBER HOT MIX TON 1,833
31 DRILL AND BOND DOWEL LF 30
32 DOWEL BAR LB 161
33 RE-ESTABLISH CURB DRAIN OUTLET LS 1
34 CURB DRAIN PER STD PLAN 150, N=1, CASE 3 INLET EA 1
35 CURB DRAIN PER DETAIL SHEET 17, N=1 EA 2
36 PARKWAY DRAIN PER STD PLAN 151, S=28", INLET TYPE 2 EA 1
37 SAWCUT AND SEAL 6" CMP PIPE LS 1
38 CHANNEL COVER (PER SHEET 18, CHANNEL COVER STRUCTURAL DETAILS) CY 282
39 PCC CURB, TYPE A1-6 LF 10
40 PCC CURB, TYPE A1-VAR LF 402
41 PCC CURB & GUTTER, TYPE A2-6 LF 849
42 PCC CURB & GUTTER, TYPE A2-8 LF 1,248
43 PCC CURB & GUTTER, TYPE A2-8, W=2.5' LF 310
44 PCC CURB & GUTTER, TYPE A2-8, W=VAR LF 29
45 PCC CURB & GUTTER, TYPE A2-VAR LF 38
46 PCC GUTTER, 2' WIDE LF 357
47 PCC WALK & DRIVEWAYS, 4" THICK SF 8,331
48 PCC CURB RAMPS CY 38
49 PCC DRIVEWAYS, 6" THICK SF 622
50 DETECTABLE WARNING SURFACE SF 695
51 CROSS GUTTER CY 38
52 REMOVE AND DISPOSE OF EXISTING METAL HAND RAILINGS LF 18
53 METAL HAND RAILINGS PER STD PLAN 606 LF 27
54 REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) LF 1,711
55 TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE LB 23,000
56 MIDWEST GUARDRAIL SYSTEM (STEEL POST WITH PLASTIC BLOCK) LF 1,270
57 IN-LINE TERMINAL SYSTEM EA 12
58 MIDWEST GUARDRAIL SYSTEM END ANCHOR ASSEMBLY PER CALTRANS STANDARD PLAN A77S1 EA 9
59 MIDWEST GUARDRAIL SYSTEM END CAP PER CALTRANS STANDARD PLAN A77M1 (TYPE A) EA 10
60 CHAIN LINK FENCE, 4' HIGH LF 124
61 NO. 6 PULL BOX INCL PCC COVER EA 1
62 INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT LF 255
63 DETAIL 2 (THERMOPLASTIC) LF 2,270
64 DETAIL 22 (THERMOPLASTIC) LF 1,555
65 DETAIL 38 (THERMOPLASTIC) LF 70
66 PAVEMENT MARKINGS (THERMOPLASTIC) SF 502
67 12" STRIPING (THERMOPLASTIC) LF 590
68 24" STRIPING (THERMOPLASTIC) LF 75
69 CURB MARKINGS (ONE-COAT PAINT) LF 355
70 REMOVE 12" STRIPING (THERMOPLASTIC) LF 325
71 BLUE RAISED PAVEMENT MARKER (RETROREFLECTIVE) EA 12
72 SIGN PANEL EA 16
73 SIGN POST (ROADSIDE SIGN) EA 8
74 RELOCATE SIGN EA 1
75 REMOVE SIGN EA 7
76 SHREDDED MULCH, 3" THICK CY 6
77 CLASS "A" TOPSOIL CY 14
78 TRAFFIC CONTROL - MARIPOSA ST LS 1
79 TRAFFIC CONTROL - ALLEN AVE LS 1
Adobe Acrobat Reader is required to view (.pdf) documents.
Click on logo below to download Adobe Acrobat Reader.
Adobe Acrobat
  • lacounty.gov
  • Public Works FAQ
  • Privacy - Terms of Use
  • ADA / Accessibility
  • Feedback
  • Feedback

Translate