Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.06.002 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) |
0.14
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
001.06.003 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.06
| 2 | MTH | $500.00 | $500.00 |
$1,000.00
| $500.00 | $500.00 |
001.06.007 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
0.06
| 1 | LS | $1,000.00 | $1,000.00 |
$1,000.00
| $1,000.00 | $1,000.00 |
001.06.011 | IMPLEMENTATION OF THE LTWHP |
0.35
| 1 | LS | $15,000.00 | $6,210.00 |
$6,210.00
| $15,842.43 | $10,000.00 |
001.07.003 | IMPLEMENTATION OF BMPS |
2.20
| 1 | LS | $15,600.00 | $39,400.00 |
$39,400.00
| $22,348.57 | $16,000.00 |
001.07.021 | SHORING OF OPEN EXCAVATIONS |
4.32
| 1 | LS | $42,900.00 | $77,500.00 |
$77,500.00
| $108,208.00 | $60,000.00 |
001.08.005 | OFFICE FACILITIES |
1.78
| 3 | MTH | $13,000.00 | $10,667.00 |
$32,001.00
| $9,543.14 | $9,000.00 |
001.09.003 | MOBILIZATION |
9.89
| 1 | LS | $128,700.00 | $177,300.00 |
$177,300.00
| $166,860.00 | $150,000.00 |
601.09.011 | TRAFFIC CONTROL |
2.45
| 1 | LS | $58,500.00 | $44,000.00 |
$44,000.00
| $52,740.00 | $38,180.00 |
| IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN |
0.56
| 1 | LS | $26,000.00 | $10,000.00 |
$10,000.00
| $34,067.86 | $20,000.00 |
| PREPARATION OF SOIL MANAGEMENT PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.14
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| PREPARATION OF DEWATERING PLAN |
0.14
| 1 | LS | $3,900.00 | $2,500.00 |
$2,500.00
| $5,616.57 | $4,000.00 |
| DIVERSION STRUCTURES |
12.10
| 1 | LS | $156,000.00 | $216,900.00 |
$216,900.00
| $252,252.57 | $212,568.00 |
| RESTORATION OF EX. IMPROVEMENTS |
6.39
| 1 | LS | $120,900.00 | $114,600.00 |
$114,600.00
| $125,285.71 | $114,600.00 |
| IMPLEMENTATION OF DEWATERING PLAN |
2.23
| 1 | LS | $52,000.00 | $40,000.00 |
$40,000.00
| $148,637.86 | $75,000.00 |
| STORMWATER FILTRATION DEVICES |
25.47
| 1 | LS | $439,400.00 | $456,826.00 |
$456,826.00
| $700,629.43 | $560,000.00 |
| STORM DRAIN |
19.07
| 1 | LS | $181,610.00 | $341,990.00 |
$341,990.00
| $395,028.86 | $406,722.00 |
| SITE PREPARATION AND DEMOLITION |
5.95
| 1 | LS | $130,000.00 | $106,774.00 |
$106,774.00
| $164,535.71 | $139,950.00 |
| TRANSPORTATION AND DISPOSAL OF PETROLEUM IMPACTED SOIL (CLASS III LANDFILL) |
6.57
| 380 | TONS | $175.00 | $310.00 |
$117,800.00
| $249.00 | $250.00 |
| PREPARATION OF THE SURFACE WATER DIVERSION PLAN |
0.14
| 1 | LS | $13,000.00 | $2,500.00 |
$2,500.00
| $4,902.29 | $2,500.00 |
| Total Percent | 100 | | | | Total Amount | $1,793,301.00 | | |