Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
300.01.065 | CONCRETE REMOVAL (NON-REINFORCED) |
0.05
| 2 | CY | $500.00 | $400.00 |
$800.00
| $1,130.50 | $561.00 |
300.02.003 | UNCLASSIFIED EXCAVATION |
0.81
| 89 | CY | $150.00 | $150.00 |
$13,350.00
| $242.80 | $209.10 |
301.02.005 | CRUSHED MISCELLANEOUS BASE |
0.33
| 54 | CY | $200.00 | $100.00 |
$5,400.00
| $174.65 | $150.00 |
302.05.013 | AC PAVEMENT |
0.12
| 4 | TON | $210.00 | $500.00 |
$2,000.00
| $1,012.50 | $575.00 |
302.05.014 | AC PAVEMENT(PATCH BACK) |
0.93
| 44 | TON | $210.00 | $350.00 |
$15,400.00
| $539.00 | $403.00 |
303.01.003 | STRUCTURE CONCRETE |
0.55
| 13 | CY | $1,950.00 | $700.00 |
$9,100.00
| $2,400.00 | $2,450.00 |
303.01.041 | BAR REINFORCING STEEL |
0.33
| 1080 | LB | $5.00 | $5.00 |
$5,400.00
| $5.20 | $5.00 |
303.05.003 | PCC CURB, TYPE A1-6 |
3.45
| 877 | LF | $20.00 | $65.00 |
$57,005.00
| $79.70 | $77.50 |
303.08.067 | PERVIOUS CONCRETE, 6" THICK |
4.09
| 2216 | SF | $13.00 | $30.50 |
$67,588.00
| $36.33 | $32.65 |
304.01.003 | CLEAN & PAINT STRUCTURAL STEEL |
0.60
| 1 | LS | $18,800.00 | $10,000.00 |
$10,000.00
| $15,200.00 | $15,000.00 |
304.01.015 | STRUCTURAL STEEL |
6.23
| 5150 | LB | $15.00 | $20.00 |
$103,000.00
| $18.84 | $16.67 |
305.01.009 | DRILL PILE HOLES, 18" DIA |
6.07
| 118 | CY | $100.00 | $850.00 |
$100,300.00
| $1,043.50 | $1,025.00 |
310.05.034 | PAVEMENT MARKINGS (THERMOPLASTIC) |
0.27
| 378 | SF | $8.00 | $12.00 |
$4,536.00
| $28.77 | $29.50 |
310.05.040 | 4" STRIPING (THERMOPLASTIC) |
2.15
| 5067 | LF | $2.00 | $7.00 |
$35,469.00
| $7.19 | $7.39 |
310.05.131 | REMOVE STRIPING AND MARKINGS (THERMOPLASTIC) |
0.30
| 2000 | SF | $7.00 | $2.50 |
$5,000.00
| $3.86 | $3.47 |
315.06.003 | SIGN PANEL |
0.20
| 11 | EA | $200.00 | $300.00 |
$3,300.00
| $482.50 | $320.00 |
315.06.005 | FURNISH ONE-POST (ROADSIDE SIGN) |
0.21
| 11 | EA | $150.00 | $320.00 |
$3,520.00
| $540.25 | $420.50 |
| LID RIVER ROCK COBBLE SWALE |
0.56
| 46 | TON | $138.00 | $200.00 |
$9,200.00
| $362.74 | $325.48 |
| LIGHT POLES 25' |
0.48
| 1 | EA | $20,000.00 | $8,000.00 |
$8,000.00
| $14,832.50 | $8,640.00 |
| MOBILIZATION |
3.63
| 1 | LS | $75,000.00 | $60,000.00 |
$60,000.00
| $289,745.00 | $185,490.00 |
| OFFICE FACILITIES |
1.81
| 6 | MO | $7,000.00 | $5,000.00 |
$30,000.00
| $5,526.25 | $4,302.50 |
| PREFAB GUARD BOOTH |
9.07
| 1 | LS | $40,000.00 | $150,000.00 |
$150,000.00
| $81,165.00 | $72,330.00 |
| PLANT ESTABLISHMENT PERIOD |
0.91
| 1 | LS | $22,925.00 | $15,000.00 |
$15,000.00
| $11,227.38 | $10,500.00 |
| TRASH RECEPTACLE (W/ NEW 6" THICK PERVIOUS CONCRETE PAD) |
1.39
| 10 | EA | $1,811.25 | $2,300.00 |
$23,000.00
| $3,423.00 | $2,650.00 |
| UNCLASSIFIED EXCAVATION LANDSCAPE |
7.30
| 1207 | CY | $172.50 | $100.00 |
$120,700.00
| $155.55 | $159.10 |
| LANDSCAPING |
4.84
| 1 | LS | $164,722.00 | $80,000.00 |
$80,000.00
| $70,010.00 | $67,500.00 |
| INTERPRETIVE SIGNAGE |
0.30
| 1 | EA | $1,850.00 | $5,000.00 |
$5,000.00
| $6,490.00 | $5,980.00 |
| IRRIGATION |
4.84
| 1 | LS | $255,662.00 | $80,000.00 |
$80,000.00
| $188,455.00 | $170,160.00 |
| IMPLEMENTATION OF THE LTWHP |
1.51
| 1 | LS | $20,000.00 | $25,000.00 |
$25,000.00
| $17,990.00 | $20,000.00 |
| IMPLEMENTATION OF BMPS |
0.60
| 1 | LS | $5,000.00 | $10,000.00 |
$10,000.00
| $22,095.00 | $15,440.00 |
| FURNISH AND PLANT 24 INCH BOX TREE |
1.33
| 55 | EA | $683.00 | $400.00 |
$22,000.00
| $768.15 | $586.30 |
| ELECTRICAL WORK |
21.17
| 1 | LS | $631,271.00 | $350,000.00 |
$350,000.00
| $377,827.50 | $381,125.00 |
| DECORATIVE BOULDERS |
2.15
| 79 | EA | $365.00 | $450.00 |
$35,550.00
| $303.06 | $315.00 |
| CRUSHED AGGREGATE BASE (CAB) |
0.30
| 41 | CY | $120.00 | $120.00 |
$4,920.00
| $203.20 | $135.00 |
| CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.15
| 5 | MO | $500.00 | $500.00 |
$2,500.00
| $500.00 | $500.00 |
| CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) |
0.15
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1000) |
0.06
| 1 | LS | $1,000.00 | $1,000.00 |
$1,000.00
| $1,000.00 | $1,000.00 |
| CONCRETE SEATWALL W/ANTI-SKATE BUMPS |
0.60
| 1 | LS | $3,786.00 | $10,000.00 |
$10,000.00
| $13,340.00 | $11,750.00 |
| CLASS "D" BIOSWALE SOIL |
6.72
| 741 | CY | $90.00 | $150.00 |
$111,150.00
| $144.31 | $147.50 |
| BIKE RACK |
0.58
| 8 | EA | $1,000.00 | $1,200.00 |
$9,600.00
| $1,369.00 | $1,238.00 |
| BUS SHELTER |
1.51
| 1 | LS | $45,000.00 | $25,000.00 |
$25,000.00
| $31,576.70 | $24,000.00 |
| AGRONOMIC SOIL REPORTS |
0.11
| 6 | EA | $580.00 | $300.00 |
$1,800.00
| $568.50 | $300.00 |
| WHEEL STOP |
1.24
| 186 | EA | $100.00 | $110.00 |
$20,460.00
| $162.50 | $145.00 |
| Total Percent | 100 | | | | Total Amount | $1,653,548.00 | | |