Bid Price History

Eaton Wash Dam Inlet Works Emergency Restoration Project
$1,158,900.00
12/16/2025
(-)
4
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.07.003IMPLEMENTATION OF BMPS 4.31 1LS$10,000.00$50,000.00 $50,000.00 $52,500.00$42,500.00
300.01.065CONCRETE REMOVAL (NON-REINFORCED) 1.73 20CY$300.00$1,000.00 $20,000.00 $1,237.50$1,175.00
300.01.067CONCRETE REMOVAL (REINFORCED) 0.26 1CY$2,000.00$3,000.00 $3,000.00 $5,562.50$6,000.00
300.04.003STRUCTURE EXCAVATION 3.13 242CY$150.00$150.00 $36,300.00 $718.75$637.50
300.04.023STRUCTURE BACKFILL 4.12 159CY$200.00$300.00 $47,700.00 $552.50$550.00
304.02.007METAL HAND RAILINGS PER STD PLAN 606 7.48 510LF$200.00$170.00 $86,700.00 $211.25$187.50
 SUPPLEMENTAL INCLINED OUTLET PIPE 17.24 222LF$400.00$900.00 $199,800.00 $812.50$850.00
 PREPARATION OF THE RESEVOIR DEWATERING PLAN (STIPULATED UNIT PRICE OF $2,500) 0.22 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 RESERVOIR DEWATERING AND NUISANCE SEDIMENT REMOVAL (ALLOWANCE OF $310,000) 26.75 310000AL$1.00$1.00 $310,000.00 $1.00$1.00
 PREPARATION OF THE SPILL PREVENTION AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) 0.22 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 REINFORCED CONCRETE (FACING SLAB INCL STAIRWAY) 34.55 286CY$1,200.00$1,400.00 $400,400.00 $1,650.00$1,350.00
 Total Percent100   Total Amount$1,158,900.00