| Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
| 001.06.002 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) |
0.07
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| 001.06.006 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.16
| 11 | MTH | $500.00 | $500.00 |
$5,500.00
| $500.00 | $500.00 |
| 001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
0.03
| 1 | LS | $1,000.00 | $1,000.00 |
$1,000.00
| $1,000.00 | $1,000.00 |
| 001.06.011 | IMPLEMENTATION OF THE LTWHP |
0.30
| 1 | LS | $10,000.00 | $10,000.00 |
$10,000.00
| $21,656.25 | $20,812.50 |
| 001.07.003 | IMPLEMENTATION OF BMPS |
0.15
| 1 | LS | $25,000.00 | $5,000.00 |
$5,000.00
| $23,125.00 | $18,750.00 |
| 001.07.021 | SHORING OF OPEN EXCAVATIONS |
0.30
| 1 | LS | $28,000.00 | $10,000.00 |
$10,000.00
| $23,750.00 | $17,500.00 |
| 001.07.023 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) |
0.09
| 1 | LS | $3,000.00 | $3,000.00 |
$3,000.00
| $3,000.00 | $3,000.00 |
| 001.07.025 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN |
0.06
| 1 | LS | $15,000.00 | $2,000.00 |
$2,000.00
| $10,500.00 | $7,500.00 |
| 001.07.037 | REMOVAL AND DISPOSAL OF LBP/LCP |
1.56
| 1 | LS | $10,000.00 | $52,500.00 |
$52,500.00
| $51,562.50 | $51,250.00 |
| 001.07.043 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) |
0.09
| 1 | LS | $3,000.00 | $3,000.00 |
$3,000.00
| $3,000.00 | $3,000.00 |
| 001.07.045 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN |
0.09
| 1 | LS | $20,000.00 | $3,000.00 |
$3,000.00
| $25,875.00 | $26,250.00 |
| 001.07.047 | PREPARATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $3000) |
0.09
| 1 | LS | $3,000.00 | $3,000.00 |
$3,000.00
| $3,000.00 | $3,000.00 |
| 001.07.049 | IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN |
0.15
| 1 | LS | $10,000.00 | $5,000.00 |
$5,000.00
| $46,875.00 | $21,250.00 |
| 001.07.051 | REMOVAL AND DISPOSAL OF NON-HAZARDOUS ASBESTOS WASTE |
4.54
| 1 | LS | $5,000.00 | $152,800.00 |
$152,800.00
| $124,075.00 | $153,150.00 |
| 001.08.005 | OFFICE FACILITIES |
0.71
| 12 | MTH | $2,400.00 | $2,000.00 |
$24,000.00
| $3,750.00 | $3,000.00 |
| 001.09.003 | MOBILIZATION |
9.80
| 1 | LS | $200,000.00 | $330,000.00 |
$330,000.00
| $328,750.00 | $262,500.00 |
| 300.01.003 | CLEARING AND GRUBBING |
0.59
| 1 | LS | $7,500.00 | $20,000.00 |
$20,000.00
| $82,625.00 | $67,500.00 |
| 300.02.003 | UNCLASSIFIED EXCAVATION |
1.03
| 290 | CY | $175.00 | $120.00 |
$34,800.00
| $148.75 | $160.00 |
| 300.04.023 | STRUCTURE BACKFILL |
2.12
| 595 | CY | $190.00 | $120.00 |
$71,400.00
| $148.75 | $147.50 |
| 302.05.013 | AC PAVEMENT |
2.02
| 170 | TON | $600.00 | $400.00 |
$68,000.00
| $430.25 | $400.00 |
| 303.01.368 | PARKWAY DRAIN PER STD PLAN 151, S=48", INLET TYPE 2 |
0.18
| 1 | EA | $17,600.00 | $6,000.00 |
$6,000.00
| $31,500.00 | $35,000.00 |
| 306.01.225 | BUTTERFLY VALVE, 300 PSI WWP, 6" |
0.06
| 1 | EA | $3,500.00 | $2,000.00 |
$2,000.00
| $5,275.00 | $5,750.00 |
| 306.01.227 | GATE VALVE, 150 PSI WWP, 10" |
0.59
| 4 | EA | $5,750.00 | $5,000.00 |
$20,000.00
| $6,178.50 | $6,250.00 |
| 306.01.227 | GATE VALVE, 150 PSI WWP, 12" |
0.83
| 4 | EA | $6,000.00 | $7,000.00 |
$28,000.00
| $7,200.00 | $7,500.00 |
| 306.01.227 | GATE VALVE, 150 PSI WWP, 4" |
0.18
| 3 | EA | $2,300.00 | $2,000.00 |
$6,000.00
| $3,775.00 | $2,750.00 |
| 500.00.015 | VIDEO INSPECTION |
0.15
| 1 | LS | $3,500.00 | $5,000.00 |
$5,000.00
| $6,875.00 | $6,250.00 |
| 601.09.011 | TRAFFIC CONTROL |
0.89
| 1 | LS | $70,000.00 | $30,000.00 |
$30,000.00
| $25,000.00 | $27,500.00 |
| 801.04.021 | LANDSCAPING |
0.62
| 1 | LS | $8,600.00 | $21,000.00 |
$21,000.00
| $27,000.00 | $23,000.00 |
| 801.05.003 | IRRIGATION SYSTEM |
0.36
| 1 | LS | $30,650.00 | $12,000.00 |
$12,000.00
| $24,750.00 | $18,500.00 |
| 801.06.003 | PLANT ESTABLISHMENT PERIOD |
0.15
| 1 | LS | $3,750.00 | $5,000.00 |
$5,000.00
| $5,750.00 | $5,000.00 |
| | ELECTRICAL WORK |
2.94
| 1 | LS | $250,000.00 | $99,000.00 |
$99,000.00
| $232,875.00 | $266,250.00 |
| | DELETED |
0
| 1 | --- | $0.01 | $1.00 |
$1.00
| $1.00 | $1.00 |
| | DEMOLITION OF EXISTING FACILITIES |
4.16
| 1 | LS | $85,000.00 | $140,000.00 |
$140,000.00
| $177,812.50 | $173,125.00 |
| | CONCRETE RINGWALL FOUNDATION |
8.32
| 1 | LS | $155,000.00 | $280,000.00 |
$280,000.00
| $206,000.00 | $205,000.00 |
| | CONCRETE SLABS (FOR TEMPORARY TANKS) |
0.56
| 1 | LS | $17,500.00 | $19,000.00 |
$19,000.00
| $32,250.00 | $30,000.00 |
| | CONCRETE SLABS (FOR STAIRWAY LANDING) |
0.06
| 1 | LS | $7,500.00 | $2,000.00 |
$2,000.00
| $6,375.00 | $6,750.00 |
| | CONCRETE SLABS (FOR INLET/OUTLET PIPING) |
0.59
| 2 | EA | $9,500.00 | $10,000.00 |
$20,000.00
| $13,312.50 | $12,500.00 |
| | CONNECTION PIPING TO EXISTING SYSTEM |
0.95
| 4 | EA | $4,500.00 | $8,000.00 |
$32,000.00
| $19,125.00 | $11,250.00 |
| | CATHODIC PROTECTION SYSTEM |
0.89
| 1 | LS | $39,500.00 | $30,000.00 |
$30,000.00
| $35,250.00 | $28,000.00 |
| | CONCRETE CURB AND GUTTER PER STD PLAN |
2.03
| 341 | LF | $105.00 | $200.00 |
$68,200.00
| $152.50 | $155.00 |
| | 6' H ARCHITECTURAL PRIVACY FENCE |
3.86
| 191 | LF | $195.00 | $680.00 |
$129,880.00
| $821.25 | $720.00 |
| | 6" WATERMAIN AND FITTINGS, STD. WT. STEEL, 300 PSI WWP |
0.67
| 75 | LF | $350.00 | $300.00 |
$22,500.00
| $520.75 | $426.50 |
| | 8'H. VEHICLE ACCESS GATE |
0.71
| 2 | EA | $6,000.00 | $12,000.00 |
$24,000.00
| $24,875.00 | $25,000.00 |
| | 8'H. ARCHITECTURAL PRIVACY FENCE |
2.08
| 68 | LF | $549.00 | $1,030.00 |
$70,040.00
| $1,113.50 | $804.50 |
| | 0.5 HP BLOWER SYSTEM |
0.59
| 1 | LS | $17,500.00 | $20,000.00 |
$20,000.00
| $25,500.00 | $17,500.00 |
| | 0.385 MG WELDED STEEL TANK AND APPURTENANCES |
21.92
| 1 | LS | $795,000.00 | $738,000.00 |
$738,000.00
| $859,504.50 | $847,500.00 |
| | 12" WATERMAIN AND FITTINGS, STD. WT. STEEL, 150 PSI WWP |
2.08
| 70 | LF | $475.00 | $1,000.00 |
$70,000.00
| $964.25 | $928.50 |
| | TANK INTERIOR PAINTING |
2.97
| 1 | LS | $118,000.00 | $100,000.00 |
$100,000.00
| $271,912.50 | $142,500.00 |
| | TREE REMOVAL |
0.45
| 1 | LS | $9,500.00 | $15,000.00 |
$15,000.00
| $12,375.00 | $10,000.00 |
| | TANK INLET PIPING SYSTEM |
1.81
| 1 | LS | $46,000.00 | $61,000.00 |
$61,000.00
| $133,125.00 | $110,750.00 |
| | TANK EXTERIOR PAINTING |
2.02
| 1 | LS | $95,000.00 | $68,000.00 |
$68,000.00
| $105,625.00 | $94,000.00 |
| | TEMPORARY STORAGE TANKS AND BYPASS PIPING SYSTEM |
1.25
| 1 | LS | $29,000.00 | $42,000.00 |
$42,000.00
| $121,900.00 | $135,300.00 |
| | SCAQMD PERMIT FOR GENERATOR (ALLOWANCE OF $15,000) |
0.45
| 15000 | AL | $1.00 | $1.00 |
$15,000.00
| $1.00 | $1.00 |
| | 10" WATERMAIN AND FITTINGS, STD. WT. STEEL, 150 PSI WWP |
0.58
| 52 | LF | $425.00 | $375.00 |
$19,500.00
| $701.50 | $665.50 |
| | PUMP CONNECTION PIPING SYSTEM |
1.13
| 1 | LS | $18,000.00 | $38,000.00 |
$38,000.00
| $43,975.00 | $44,000.00 |
| | RELOCATE 4-INCH BYPASS PIPING AND BOLLARDS |
0.59
| 1 | LS | $4,500.00 | $20,000.00 |
$20,000.00
| $22,500.00 | $22,500.00 |
| | PERMIT AND INSPECTION FEES (ALLOWANCE OF $15,000) |
0.45
| 15000 | AL | $1.00 | $1.00 |
$15,000.00
| $1.00 | $1.00 |
| | PREPARATION OF BMP PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.07
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | MOBILE GENERATOR |
5.64
| 1 | LS | $350,000.00 | $190,000.00 |
$190,000.00
| $208,125.00 | $199,000.00 |
| | TANK OUTLET PIPING SYSTEM |
2.22
| 1 | LS | $59,700.00 | $74,800.00 |
$74,800.00
| $136,950.00 | $136,500.00 |
| | Total Percent | 100 | | | | Total Amount | $3,366,921.00 | | |