Bid Price History

Santa Anita Dam Access Road Post-Fire Repairs Project
$3,140,375.00
02/10/2026
(-)
3
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.08 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.003CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.10 6MTH$500.00$500.00 $3,000.00 $500.00$500.00
001.06.007CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.03 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.80 1LS$15,000.00$25,000.00 $25,000.00 $20,666.67$25,000.00
001.07.003IMPLEMENTATION OF BMPS 0.80 1LS$10,000.00$25,000.00 $25,000.00 $40,000.00$25,000.00
001.07.023PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $5000) 0.16 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
001.07.025IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 0.80 1LS$10,000.00$25,000.00 $25,000.00 $46,666.67$25,000.00
001.08.005OFFICE FACILITIES 1.43 6MTH$5,000.00$7,500.00 $45,000.00 $6,000.00$7,500.00
001.09.003MOBILIZATION 3.82 1LS$243,750.00$120,000.00 $120,000.00 $423,333.33$520,000.00
304.02.013CABLE RAILING (CALTRANS STD PLAN B11-47) 0.84 220LF$250.00$120.00 $26,400.00 $113.21$114.38
304.02.013CABLE RAILING (CALTRANS STD PLAN B11-47) 0.36 95LF$250.00$120.00 $11,400.00 $113.21$114.38
 MINOR HOT MIX ASPHALT DIKE (TYPE A) 0.08 5LF$50.00$500.00 $2,500.00 $733.33$500.00
 MIDWEST GUARDRAIL SYSTEM 0.50 210LF$150.00$75.00 $15,750.00 $72.67$75.00
 PRECAST CONCRETE LAGGING 2.92 835SQFT$65.00$110.00 $91,850.00 $127.00$121.00
 PRECAST CONCRETE LAGGING 4.06 1158SQFT$65.00$110.00 $127,380.00 $127.00$121.00
 PRECAST CONCRETE LAGGING 9.29 2652SQFT$65.00$110.00 $291,720.00 $127.00$121.00
 30" DRILLED HOLE 9.47 1190LF$250.00$250.00 $297,500.00 $583.33$500.00
 ROLLED EROSION CONTROL PRODUCT (JUTE MESH) 0.22 700SQFT$5.00$10.00 $7,000.00 $13.33$10.00
 WALL DEMOLITION 1.11 1LS$10,000.00$35,000.00 $35,000.00 $133,333.33$40,000.00
 STEEL SOLDIER PILE (W18X119) 1.96 20468LB$3.75$3.00 $61,404.00 $2.50$2.50
 STEEL SOLDIER PILE (W18X119) 3.27 34213LB$3.75$3.00 $102,639.00 $2.50$2.50
 STEEL SOLDIER PILE (W18X143) 6.01 62920LB$3.75$3.00 $188,760.00 $2.50$2.50
 STEEL SOLDIER PILE (W18X192) 3.48 36480LB$3.75$3.00 $109,440.00 $2.50$2.50
 STEEL SOLDIER PILE (W18X86) 4.80 50224LB$3.75$3.00 $150,672.00 $2.50$2.50
 SITE 4 REPAIRS (ALLOWANCE OF $500,000) 15.92 500000AL$1.00$1.00 $500,000.00 $1.00$1.00
 STRUCTURE EXCAVATION (SOLDIER PILE WALL) 2.28 358CY$80.00$200.00 $71,600.00 $239.00$250.00
 STRUCTURE EXCAVATION (SOLDIER PILE WALL) 0.94 147CY$80.00$200.00 $29,400.00 $239.00$250.00
 STRUCTURE BACKFILL (SOLDIER PILE WALL) 1.37 215CY$80.00$200.00 $43,000.00 $233.33$200.00
 STRUCTURE BACKFILL (SOLDIER PILE WALL) 0.66 104CY$80.00$200.00 $20,800.00 $233.33$200.00
 TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE 0.96 15TON$200.00$2,000.00 $30,000.00 $1,100.00$850.00
 TRANSPORTATION AND DELIVERY OF TREATED WOOD WASTE MAINTAINTENACE YARD (ALLOWANCE OF $5,000) 0.16 5000AL$1.00$1.00 $5,000.00 $1.00$1.00
 MINOR CONCRETE (560-C-3250 W/ 6" X 6" - 10/10 GAGE W.W.F) 2.23 40CY$2,250.00$1,750.00 $70,000.00 $1,916.67$2,000.00
 MINOR CONCRETE (560-C-3250 W/ 6" X 6" - 10/10 GAGE W.W.F) 0.56 10CY$2,250.00$1,750.00 $17,500.00 $1,916.67$2,000.00
 LEAN CONCRETE BACKFILL (SOLDIER PILE WALL) 0.96 20CY$400.00$1,500.00 $30,000.00 $985.67$1,200.00
 LEAN CONCRETE BACKFILL (SOLDIER PILE WALL) 3.49 73CY$400.00$1,500.00 $109,500.00 $985.67$1,200.00
 FIBER ROLLS 1.21 760LF$20.00$50.00 $38,000.00 $28.33$25.00
 FIBER ROLLS 1.50 940LF$20.00$50.00 $47,000.00 $28.33$25.00
 CONCRETE BACKFILL (SOLDIER PILE WALL) 4.59 144CY$500.00$1,000.00 $144,000.00 $938.00$1,000.00
 CONCRETE BACKFILL (SOLDIER PILE WALL) 2.10 66CY$500.00$1,000.00 $66,000.00 $938.00$1,000.00
 CONCRETE BACKFILL (MGS EMBEDMENT) 0.54 10CY$500.00$1,700.00 $17,000.00 $1,958.33$1,700.00
 ROLLED EROSION CONTROL PRODUCT (JUTE MESH) 0.34 1066SQFT$5.00$10.00 $10,660.00 $13.33$10.00
 30" DRILLED HOLE 3.74 470LF$250.00$250.00 $117,500.00 $583.33$500.00
 PREPARATION OF THE TREATED WOOD WASTE PLAN (STIPULATED UNIT PRICE OF $2,500) 0.08 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 Total Percent100   Total Amount$3,140,375.00