| Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
| 001.06.002 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) |
0.09
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| 001.06.006 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.09
| 5 | MTH | $500.00 | $500.00 |
$2,500.00
| $500.00 | $500.00 |
| 001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
0.04
| 1 | LS | $1,000.00 | $1,000.00 |
$1,000.00
| $1,000.00 | $1,000.00 |
| 001.06.011 | IMPLEMENTATION OF THE LTWHP |
1.29
| 1 | LS | $20,000.00 | $35,000.00 |
$35,000.00
| $12,476.67 | $8,000.00 |
| 001.07.003 | IMPLEMENTATION OF BMPS |
1.66
| 1 | LS | $38,500.00 | $45,000.00 |
$45,000.00
| $36,165.50 | $38,000.00 |
| 001.08.005 | OFFICE FACILITIES |
3.54
| 6 | MTH | $9,900.00 | $16,000.00 |
$96,000.00
| $11,211.67 | $12,100.00 |
| 001.09.003 | MOBILIZATION |
6.65
| 1 | LS | $297,000.00 | $180,000.00 |
$180,000.00
| $219,699.17 | $200,000.00 |
| 300.01.003 | CLEARING AND GRUBBING |
1.70
| 1 | LS | $66,000.00 | $46,000.00 |
$46,000.00
| $84,770.67 | $70,709.00 |
| 300.02.003 | UNCLASSIFIED EXCAVATION |
4.18
| 539 | CY | $583.00 | $210.00 |
$113,190.00
| $342.17 | $402.50 |
| 302.05.013 | AC PAVEMENT |
2.98
| 195 | TON | $517.00 | $413.45 |
$80,622.75
| $805.24 | $857.50 |
| 304.06.003 | REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) |
3.24
| 6269 | LF | $33.00 | $14.00 |
$87,766.00
| $24.33 | $14.50 |
| 304.06.009 | TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE |
1.62
| 87793 | LB | $1.10 | $0.50 |
$43,896.50
| $0.62 | $0.60 |
| 304.06.019 | MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK) |
18.98
| 5300 | LF | $110.00 | $97.00 |
$514,100.00
| $128.26 | $106.50 |
| 304.06.043 | MIDWEST GUARDRAIL SYSTEM END ANCHOR ASSEMBLY (TYPE SFT) PER STD PLAN A77S1 |
1.77
| 10 | EA | $4,125.00 | $4,800.00 |
$48,000.00
| $4,109.50 | $3,718.50 |
| 304.06.047 | MIDWEST GUARDRAIL SYSTEM BURIED POST END ANCHOR PER STD PLAN A77T2 |
1.66
| 6 | EA | $6,187.50 | $7,500.00 |
$45,000.00
| $5,724.67 | $6,555.00 |
| 304.06.049 | RAILING DELINEATION PER CALTRANS STD PLAN A77N4 |
0.48
| 261 | EA | $55.00 | $50.00 |
$13,050.00
| $61.00 | $57.00 |
| 601.09.011 | TRAFFIC CONTROL |
10.34
| 1 | LS | $330,000.00 | $280,000.00 |
$280,000.00
| $507,081.50 | $421,955.50 |
| | IN-LINE TERMINAL SYSTEM (MSKT TL-3) |
1.55
| 4 | EA | $22,000.00 | $10,500.00 |
$42,000.00
| $7,854.00 | $8,256.50 |
| | PREPARATION OF THE BMP PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.09
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | PREPARATION OF THE TREATED WOOD WASTE (TWW) PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.09
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | RELOCATE EXISTING K-RAIL |
0.14
| 4 | EA | $55.00 | $915.00 |
$3,660.00
| $1,244.83 | $1,000.00 |
| | IN-LINE TERMINAL SYSTEM (MSKT TL-2) |
9.41
| 30 | EA | $12,375.00 | $8,500.00 |
$255,000.00
| $6,501.83 | $6,864.00 |
| | IN-LINE TERMINAL SYSTEM (MAX-TENSION TL-2) |
7.31
| 11 | EA | $12,375.00 | $18,000.00 |
$198,000.00
| $10,195.17 | $9,429.50 |
| | TRANSITION RAILING (TYPE AGT) |
1.11
| 3 | EA | $12,375.00 | $10,000.00 |
$30,000.00
| $7,207.17 | $7,530.00 |
| | IN-LINE TERMINAL SYSTEM (SOFTSTOP TL-2) |
1.27
| 4 | EA | $12,375.00 | $8,600.00 |
$34,400.00
| $7,762.17 | $8,050.00 |
| | MIDWEST GUARDRAIL SYSTEM END CAP PER CALTRANS STANDARD PLAN A77M1 (TYPE A) |
0.04
| 1 | EA | $1,034.00 | $1,200.00 |
$1,200.00
| $1,376.67 | $1,200.00 |
| | MINOR CONCRETE AND BLOCK-OUT MATERIAL PER CALTRANS STD PLAN A77N5 |
0.68
| 213 | EA | $220.00 | $86.00 |
$18,318.00
| $332.67 | $235.50 |
| | MINOR CONCRETE VEGETATION CONTROL |
16
| 4335 | SY | $100.00 | $100.00 |
$433,500.00
| $124.57 | $116.00 |
| | AC DIKE PER CALTRANS STD PLAN A87B |
1.99
| 2698 | LF | $66.00 | $20.00 |
$53,960.00
| $34.21 | $34.13 |
| | Total Percent | 100 | | | | Total Amount | $2,708,663.25 | | |