Bid Price History

Eaton Wash Dam Post-fire Emergency Project
$16,000,000.00
02/03/2025
(-)
1
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
 CLEARING AND GRUBBING 3.13 500000TM$1.00$1.00 $500,000.00 $1.00$1.00
 EXCAVATION, TRANSPORTATION, AND DISPOSAL OF SEDIMENT 63.13 10100000TM$1.00$1.00 $10,100,000.00 $1.00$1.00
 IMPLEMENTATION OF BMPS 2.34 375000TM$1.00$1.00 $375,000.00 $1.00$1.00
 IMPLEMENTATON OF THE LTWHP 0.63 100000TM$1.00$1.00 $100,000.00 $1.00$1.00
 OFFICE FACILITIES 0.16 25000TM$1.00$1.00 $25,000.00 $1.00$1.00
 PERMITS AND FEES 27.50 4400000TM$1.00$1.00 $4,400,000.00 $1.00$1.00
 TRAFFIC CONTROL 3.13 500000TM$1.00$1.00 $500,000.00 $1.00$1.00
 Total Percent100   Total Amount$16,000,000.00