The Old Rd over Santa Clara River and SPT CO Bridge et al Phase I
$14,719,345.89
02/03/2026
4550 (A1),4550 (C2),4460 (A7),4459 (J7),4550 (B2),4550 (B1)
7
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.02 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.003CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.07 22MTH$500.00$500.00 $11,000.00 $500.00$500.00
001.06.007CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.01 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.24 1LS$15,000.00$35,000.00 $35,000.00 $65,571.43$50,000.00
001.07.004PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $15,000) 0.10 1LS$15,000.00$15,000.00 $15,000.00 $15,000.00$15,000.00
001.07.007IMPLEMENTATION OF THE SWPPP 0.99 1LS$50,000.00$146,000.00 $146,000.00 $362,855.51$240,000.00
001.07.021SHORING OF OPEN EXCAVATIONS 0.69 1LS$220,000.00$101,050.00 $101,050.00 $99,334.29$100,000.00
001.08.005OFFICE FACILITIES 1.01 22MTH$5,000.00$6,750.00 $148,500.00 $8,240.71$6,750.00
001.09.003MOBILIZATION 9.85 1LS$1,112,000.00$1,450,000.00 $1,450,000.00 $1,633,125.16$1,681,000.00
300.01.003CLEARING AND GRUBBING 0.24 1LS$150,000.00$35,000.00 $35,000.00 $139,428.57$126,000.00
300.01.013TREE REMOVAL (6"-12" DIAMETER) 0.14 7EA$1,000.00$3,000.00 $21,000.00 $1,211.14$1,000.00
300.01.014TREE REMOVAL (13"-24" DIAMETER) 0.18 5EA$1,500.00$5,200.00 $26,000.00 $1,978.43$1,500.00
300.01.015TREE REMOVAL (25"+ DIAMETER) 0.05 1EA$2,000.00$6,800.00 $6,800.00 $2,932.43$2,500.00
300.01.057REMOVE EXISTING CHAIN LINK FENCE 0.07 1431LF$20.00$7.00 $10,017.00 $14.22$15.00
300.01.065CONCRETE REMOVAL (NON-REINFORCED) 2.79 4773CY$250.00$86.00 $410,478.00 $254.13$131.40
300.01.067CONCRETE REMOVAL (REINFORCED) 0.18 36CY$1,500.00$755.00 $27,180.00 $851.71$755.00
300.02.003UNCLASSIFIED EXCAVATION 2.34 17632CY$100.00$19.50 $343,824.00 $50.84$40.00
300.03.003UNCLASSIFIED FILL 0.38 7988CY$50.00$7.00 $55,916.00 $30.61$18.00
301.02.003CRUSHED AGGREGATE BASE 0.32 527CY$140.00$88.00 $46,376.00 $192.14$150.00
301.02.005CRUSHED MISCELLANEOUS BASE 6.41 17155CY$110.00$55.00 $943,525.00 $75.31$76.00
302.01.009COLD MILL AC PAVEMENT (> 3") 1.51 297179SF$0.70$0.75 $222,884.25 $1.26$0.90
302.05.013AC PAVEMENT 7.91 9101TON$150.00$128.00 $1,164,928.00 $146.43$149.00
302.05.023RECONSTRUCT MANHOLE 0.49 5EA$3,500.00$14,320.00 $71,600.00 $11,067.14$10,050.00
302.13.003PMAC PAVEMENT 4.15 3994TON$150.00$153.00 $611,082.00 $158.14$153.00
302.13.005PMAC PAVEMENT (TEST STRIP) 0.58 500TON$150.00$171.00 $85,500.00 $200.86$200.00
303.01.309CATCH BASIN PER STD PLAN 300, W=7 0.99 5EA$15,000.00$29,230.00 $146,150.00 $18,400.00$15,600.00
303.01.309CATCH BASIN PER STD PLAN 300, W=14 0.68 3EA$20,000.00$33,300.00 $99,900.00 $25,450.00$22,000.00
303.01.309CATCH BASIN PER STD PLAN 300, W=10 0.48 2EA$17,500.00$35,600.00 $71,200.00 $21,862.86$19,500.00
303.01.329PIPE CONNECTION PER STD PLAN 335, CASE 1 0.09 2EA$2,000.00$6,600.00 $13,200.00 $6,675.57$6,600.00
303.01.339JUNCTION STRUCTURE PER STD PLAN 331 0.17 3EA$5,000.00$8,175.00 $24,525.00 $5,886.57$5,100.00
303.01.347MANHOLE PER STD PLAN 321 1.69 8EA$15,000.00$31,180.00 $249,440.00 $19,580.71$18,000.00
303.01.365CURB DRAIN PER STD PLAN 150, N=1, CASE 2 INLET 0.23 8EA$500.00$4,320.00 $34,560.00 $9,896.86$5,508.00
303.01.368PARKWAY DRAIN PER STD PLAN 151, S=36", INLET TYPE 2 0.06 1EA$4,000.00$9,420.00 $9,420.00 $11,435.00$9,420.00
303.01.368PARKWAY DRAIN PER STD PLAN 151, S=18", INLET TYPE 2 0.06 1EA$3,500.00$9,120.00 $9,120.00 $10,787.43$9,120.00
303.05.004PCC CURB, TYPE A1-8 0.06 146LF$30.00$63.50 $9,271.00 $60.89$63.50
303.05.010PCC CURB & GUTTER, TYPE A2-8 1.98 6560LF$45.00$44.50 $291,920.00 $56.64$46.50
303.05.047PCC WALK & DRIVEWAYS, 4" THICK 3.80 48618SF$10.00$11.50 $559,107.00 $10.89$10.00
303.05.050PCC CURB RAMPS 0.03 3CY$2,000.00$1,460.00 $4,380.00 $1,956.71$2,000.00
303.05.055PCC DRIVEWAYS, 6" THICK 0.61 5803SF$15.00$15.50 $89,946.50 $15.86$15.50
303.05.059DETECTABLE WARNING SURFACE 0.01 15SF$60.00$78.00 $1,170.00 $86.66$78.00
304.06.009TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE 0.02 2828LB$5.00$1.00 $2,828.00 $2.96$2.00
306.01.1076' - 0" W X 2' - 0" H RCB 1.10 65LF$1,780.00$2,500.00 $162,500.00 $2,362.86$2,500.00
306.01.10713' - 7" W X 10' - 0" H RCB 1.72 47LF$8,920.00$5,400.00 $253,800.00 $7,040.71$7,000.00
306.01.12924" RCP, 2000 D 2.35 1164LF$550.00$297.00 $345,708.00 $349.43$329.00
306.01.12918" RCP, 2000 D 2.64 1268LF$500.00$306.00 $388,008.00 $296.14$306.00
306.01.139CONCRETE BACKFILL FOR CONNECTOR PIPE 0.11 18CY$500.00$879.00 $15,822.00 $633.86$450.00
307.02.0071-1/2" CONDUIT (SCH 80 PVC) 0.07 480LF$70.00$22.50 $10,800.00 $44.63$35.00
307.02.0112" CONDUIT (SCH 80 PVC) 0.23 1275LF$100.00$26.00 $33,150.00 $51.19$50.00
307.02.0213" CONDUIT (SCH 80 PVC) 2.51 7860LF$110.00$47.00 $369,420.00 $62.17$46.66
307.02.0312-PAIR DETECTOR LEAD-IN CABLE 0.03 2430LF$4.00$1.75 $4,252.50 $5.12$2.00
307.02.03912-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) 0.04 1065LF$10.00$5.15 $5,484.75 $7.94$5.15
307.02.0393-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) 0.01 465LF$6.00$2.70 $1,255.50 $5.84$3.30
307.02.0395-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) 0.01 250LF$8.00$3.30 $825.00 $10.67$5.00
307.02.049INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT 0.12 383LF$25.00$44.50 $17,043.50 $34.48$38.00
307.02.122REMOVE TYPE 15 STANDARD (COMPLETE) (EXCL. FOUND.) 0.01 1EA$2,000.00$1,090.00 $1,090.00 $1,448.77$952.00
307.02.122REMOVE TYPE 1 STANDARD (COMPLETE) (EXCL. FOUND.) 0.01 2EA$1,300.00$435.00 $870.00 $1,161.20$525.00
307.02.122REMOVE TYPE 26 STANDARD (COMPLETE) (EXCL. FOUND.) 0.01 1EA$5,000.00$1,235.00 $1,235.00 $1,804.37$1,397.00
307.02.132REMOVE VEHICLE HEAD (COMPLETE) 0 18EA$300.00$36.50 $657.00 $761.67$55.00
307.02.138REMOVE PEDESTRIAN PUSH BUTTON 0 2EA$150.00$24.50 $49.00 $820.54$55.00
307.02.156REMOVE TYPE 1 FOUNDATION 0 2EA$2,000.00$270.00 $540.00 $1,475.87$985.11
307.02.156REMOVE TYPE 26 FOUNDATION 0 1EA$7,000.00$540.00 $540.00 $1,288.81$1,000.67
307.02.156REMOVE TYPE 15 FOUNDATION 0 1EA$2,500.00$270.00 $270.00 $1,581.56$1,399.89
307.04.317TYPE 2070 CONTROLLER 0.14 2EA$11,000.00$9,985.00 $19,970.00 $9,011.16$9,950.00
307.04.3932-CHANNEL ILD SENSOR UNIT 0.01 4EA$400.00$388.00 $1,552.00 $784.13$350.00
307.04.469TYPE III-BF SERVICE CABINET 0.12 2EA$8,000.00$8,810.00 $17,620.00 $9,427.43$8,810.00
307.04.501TYPE 61 STANDARD 0.29 1EA$40,000.00$42,520.00 $42,520.00 $36,991.88$37,070.00
307.04.501TYPE 17 STANDARD 0.11 1EA$14,000.00$16,680.00 $16,680.00 $16,665.12$15,035.84
307.04.501TYPE 1 STANDARD 0.02 1EA$3,000.00$2,465.00 $2,465.00 $3,123.95$2,150.00
307.04.503TYPE 61 STANDARD FOUNDATION 0.09 1EA$13,000.00$12,800.00 $12,800.00 $12,419.10$12,800.00
307.04.503TYPE 17 STANDARD FOUNDATION 0.05 1EA$8,000.00$6,815.00 $6,815.00 $7,254.02$6,815.00
307.04.503TYPE 1 STANDARD FOUNDATION 0.01 1EA$3,500.00$1,995.00 $1,995.00 $3,269.59$3,270.00
307.04.50420' SIGNAL MAST ARM 0.02 1EA$5,000.00$3,640.00 $3,640.00 $4,266.07$3,577.49
307.04.50465' SIGNAL MAST ARM 0.12 1EA$30,000.00$17,150.00 $17,150.00 $17,794.67$15,507.66
307.04.5104' LUMINAIRE MAST ARM 0.15 48EA$550.00$470.00 $22,560.00 $741.21$470.00
307.04.51012' LUMINAIRE MAST ARM 0.02 2EA$1,500.00$1,820.00 $3,640.00 $2,051.24$1,731.71
307.04.519PEDESTRIAN PUSH BUTTON POST 0.01 1EA$2,000.00$928.00 $928.00 $1,631.84$809.00
307.04.521PEDESTRIAN PUSH BUTTON POST FOUNDATION 0 1EA$1,000.00$599.00 $599.00 $1,679.82$777.71
307.04.5323-12" LED VEHICLE HEAD (COMPLETE) 0.30 25EA$2,000.00$1,760.00 $44,000.00 $2,166.00$2,100.00
307.04.5344-12" LED VEHICLE HEAD (COMPLETE) 0.03 2EA$2,300.00$2,350.00 $4,700.00 $2,666.32$2,350.00
307.04.5383-SECTION PV LED VEHICLE HEAD (COMPLETE) 0.03 1EA$5,000.00$3,760.00 $3,760.00 $7,030.53$7,000.00
307.04.803SALVAGE EQUIPMENT 0.07 1LS$4,000.00$10,570.00 $10,570.00 $8,567.82$9,220.00
310.05.007DETAIL 38 (THERMOPLASTIC) 0.02 1084LF$6.00$3.29 $3,566.36 $2.94$3.00
310.05.007DETAIL 39 (THERMOPLASTIC) 0.08 13631LF$4.00$0.88 $11,995.28 $1.11$1.00
310.05.007DETAIL 25 (THERMOPLASTIC) 0.04 6942LF$6.00$0.93 $6,456.06 $1.38$1.45
310.05.007DETAIL 29 (THERMOPLASTIC) 0.01 240LF$8.00$6.57 $1,576.80 $5.82$6.00
310.05.007DETAIL 12 (THERMOPLASTIC) 0.07 11191LF$5.00$0.88 $9,848.08 $0.96$0.88
310.05.014DETAIL 39A (THERMOPLASTIC) 0.01 1156LF$4.00$0.88 $1,017.28 $1.01$0.90
310.05.022DETAIL 37B (THERMOPLASTIC) 0.01 287LF$6.00$3.30 $947.10 $3.20$3.00
310.05.022DETAIL 27B (THERMOPLASTIC) 0 250LF$4.00$0.88 $220.00 $1.54$1.27
310.05.022DETAIL 36B (THERMOPLASTIC) 0.01 374LF$8.00$3.30 $1,234.20 $4.21$3.30
310.05.034PAVEMENT MARKINGS (THERMOPLASTIC) 0.26 3455SF$10.00$11.00 $38,005.00 $9.82$10.00
310.05.04012" STRIPING (THERMOPLASTIC) 0.10 2312LF$6.00$6.60 $15,259.20 $6.39$6.10
310.05.04024" STRIPING (THERMOPLASTIC) 0.04 485LF$12.00$13.30 $6,450.50 $11.55$12.00
310.05.0406" STRIPING (THERMOPLASTIC) 0.01 400LF$4.00$5.50 $2,200.00 $4.36$5.00
310.05.043CURB MARKINGS (ONE-COAT PAINT) 0 92LF$5.00$3.29 $302.68 $14.28$3.70
312.01.017INSTALL FIRE HYDRANT LOCATION RPM 0 8EA$20.00$11.00 $88.00 $23.51$21.00
315.06.003SIGN PANEL 0.15 80EA$300.00$274.00 $21,920.00 $238.29$250.00
315.06.025REMOVE SIGN 0.02 58EA$100.00$55.00 $3,190.00 $69.09$56.00
315.06.029REMOVE SIGN POST 0.01 39EA$150.00$55.50 $2,164.50 $101.91$89.25
601.09.011TRAFFIC CONTROL 5.39 1LS$1,295,700.00$793,000.00 $793,000.00 $1,160,328.71$980,000.00
801.04.015FURNISH AND PLANT 24" BOX TREE 0.68 183EA$683.00$546.00 $99,918.00 $659.86$739.00
801.04.017EROSION CONTROL BLANKET 0.44 3110SY$5.75$21.00 $65,310.00 $5.95$2.80
801.04.021LANDSCAPING 1.49 1LS$437,428.04$219,000.00 $219,000.00 $291,865.29$269,000.00
801.05.003IRRIGATION SYSTEM 4.40 1LS$1,126,177.00$647,000.00 $647,000.00 $559,464.14$536,489.00
801.06.003PLANT ESTABLISHMENT PERIOD 0.09 1LS$152,140.78$13,660.00 $13,660.00 $13,367.00$12,400.00
801.06.015DECOMPOSED GRANITE, 4" THICK 0.07 1272SF$7.88$8.00 $10,176.00 $9.50$8.30
801.06.017RIVER ROCK PAVING 0.09 1309SF$25.00$10.00 $13,090.00 $26.61$30.00
 2010 ECL CONFLICT MONITOR 0.02 2EA$3,000.00$1,175.00 $2,350.00 $3,136.29$2,650.00
 4" PVC CONDUIT WITH 4-1" INNERDUCT 1.06 2891LF$100.00$54.00 $156,114.00 $93.73$100.00
 6'-0" W X 2'-0" H OUTLET STRUCTURE 0.40 1EA$22,050.00$58,300.00 $58,300.00 $44,094.29$46,300.00
 6" HDPE PIPE 0.05 9LF$100.00$753.00 $6,777.00 $292.29$278.00
 6" PVC SCH 80 PERFORATED PIPE 0.04 40LF$31.05$133.00 $5,320.00 $138.00$150.00
 6" PVC SCH 80 SOLID PIPE 0.04 40LF$36.80$133.00 $5,320.00 $144.00$133.00
 8' STRAIGHT ARM CLAMP-ON FOR STREET NAME SIGN 0.04 2EA$3,400.00$3,290.00 $6,580.00 $4,144.44$3,100.00
 AGRONOMIC SOIL REPORT 0.01 6EA$580.00$243.00 $1,458.00 $649.14$260.00
 AUTOMATIC RETRACTABLE SCREEN (ARS), 8 < W <= 14' 0.30 5EA$3,500.00$8,860.00 $44,300.00 $7,571.57$6,671.00
 ATRIUM GRATE 0.09 4EA$250.00$3,245.00 $12,980.00 $1,373.14$1,050.00
 AUTOMATIC RETRACTABLE SCREEN (ARS), 5 < W <= 8' 0.23 5EA$2,000.00$6,665.00 $33,325.00 $5,843.00$5,916.00
 APS PPB WITH SPECIAL VOICE MESSAGE 0.02 4EA$2,900.00$822.00 $3,288.00 $1,349.45$1,385.00
 CHANNEL EXTENSION STRUCTURE 1.25 1EA$142,760.00$184,000.00 $184,000.00 $126,619.43$125,000.00
 CENTRAL CONTROLLER UNIT APS 0.07 1EA$11,000.00$9,985.00 $9,985.00 $8,350.89$9,500.00
 COMPOSITE TYPE 2 PULL BOX INCL COVER 0.08 10EA$2,000.00$1,210.00 $12,100.00 $1,290.00$1,300.00
 COMPOSITE TYPE 3 PULL BOX INCL COVER 0.10 8EA$2,500.00$1,760.00 $14,080.00 $1,548.71$1,525.00
 CONCRETE STREETLIGHT FOUNDATION (30"X48") 0.52 48EA$1,700.00$1,585.00 $76,080.00 $2,564.71$2,030.00
 CONCRETE SEDIMENT TRAP SPLASH PAD 0.33 8EA$1,725.00$6,000.00 $48,000.00 $2,912.43$3,000.00
 CONSTRUCTION OF TEMPORARY SOUND BARRIER SYSTEM 0.98 1350LF$275.00$107.00 $144,450.00 $181.29$200.00
 CUT-BACK EXISTING MAST ARM 0.01 1EA$3,000.00$1,290.00 $1,290.00 $1,656.00$1,127.00
 DELINEATORS (FLEXIBLE POST) 0.14 180EA$160.00$113.00 $20,340.00 $166.70$152.00
 RIPRAP (CLASS VIII) 0.29 101CY$250.00$420.00 $42,420.00 $400.71$353.00
 RIVER ROCK COBBLE 0.12 95TON$138.00$182.00 $17,290.00 $353.71$256.00
 RIPRAP (CLASS IX) 1.70 1251CY$500.00$200.00 $250,200.00 $301.14$280.00
 SIGN POST (ROADSIDE SIGN) 0.06 31EA$350.00$275.00 $8,525.00 $337.97$275.00
 SUPPORT FOR 24" AND LESS MISC UTILITIES 0.13 8EA$1,000.00$2,350.00 $18,800.00 $8,431.71$6,000.00
 TREE PROTECTION 0.05 1LS$60,000.00$7,000.00 $7,000.00 $22,715.57$15,000.00
 TYPE 2 PULL BOX 0.29 54EA$1,800.00$793.00 $42,822.00 $1,407.71$1,500.00
 VIDEO EXTENSION CARD 0.02 1EA$500.00$2,935.00 $2,935.00 $1,741.43$1,245.00
 VANTAGE EDGE CONNECT MODULE 0 1EA$1,000.00$646.00 $646.00 $1,265.43$1,140.00
 UNCLASSIFIED EXCAVATION (ACCESS ROADS) 0.25 738CY$150.00$50.00 $36,900.00 $81.04$55.00
 SURVEYING SERVICES 0.78 1LS$495,000.00$115,000.00 $115,000.00 $194,000.00$190,000.00
 PREPARATION OF THE DIVERSION OF WATER PLAN (STIPULATED UNIT PRICE OF $5,000) 0.03 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
 PREPARATION OF THE FIRE PREVENTION PLAN (STIPULATED PRICE OF $1,500) 0.01 1LS$1,500.00$1,500.00 $1,500.00 $1,500.00$1,500.00
 PREPARATION OF NOISE MITIGATION PLAN (STIPULATED PRICE OF $2,500) 0.02 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 RECONFIG VIDEO DETECTION ZONE - 1 CAMERA 0.08 4EA$2,500.00$2,820.00 $11,280.00 $1,762.82$1,635.00
 RACK MOUNT 17" LCD MONITOR 0.03 2EA$800.00$2,465.00 $4,930.00 $2,171.57$2,100.00
 PREPARATION OF THE TREATED WOOD WASTE WORKPLAN (STIPULATED UNIT PRICE OF $2,500) 0.02 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 RELOCATE RETROREFLECTIVE STREET NAME SIGN 0.01 2EA$1,000.00$999.00 $1,998.00 $1,195.71$871.00
 RECONSTRUCT LOCAL DEPRESSION PER STD PLAN 313-4 CASE E 0.02 1EA$3,500.00$2,520.00 $2,520.00 $6,541.14$3,875.00
 REMOVAL OF TEMPORARY SOUND BARRIER SYSTEM 0.11 1LS$10,000.00$16,710.00 $16,710.00 $39,418.57$44,220.00
 RELOCATE VIDEO DETECTION CAMERA 0 1EA$2,000.00$352.00 $352.00 $3,704.93$5,290.00
 REMOVE 18" CMP 0.13 71LF$200.00$278.00 $19,738.00 $120.71$102.00
 REMOVE 2 - CAMERA VIDEO DETECTION SYSTEM (COMPLETE) 0.01 1EA$2,000.00$846.00 $846.00 $6,101.86$1,575.00
 REMOVE BARBED WIRE FENCE 0.04 1924LF$20.00$3.40 $6,541.60 $13.66$11.00
 REMOVE EXISTING GRATE CATCH BASIN AND SEAL 0.06 2EA$2,500.00$4,485.00 $8,970.00 $4,378.86$4,017.00
 REMOVE PEDESTRIAN PUSH BUTTON AND PLATE HOLE TO SMOOTH FINISH 0 1EA$400.00$446.00 $446.00 $391.43$390.00
 REMOVE PULL BOX 0 12EA$750.00$41.00 $492.00 $218.93$290.00
 REMOVE STRIPING 0.04 1143LF$5.00$5.00 $5,715.00 $5.56$5.00
 REMOVE STREETLIGHT 0.02 11EA$1,000.00$300.00 $3,300.00 $808.14$660.00
 REMOVE STREETLIGHT FOUNDATION 0.02 11EA$1,000.00$270.00 $2,970.00 $1,101.71$880.00
 DECORATIVE BOULDER 0.55 169EA$362.25$475.00 $80,275.00 $217.00$175.00
 D4 PROGRAM FOR 2070 CONTROLLER 0.04 2EA$5,000.00$2,820.00 $5,640.00 $3,583.49$2,820.00
 EROSION CONTROL BLANKET MAINTENANCE AND ESTABLISHMENT 0.12 1LS$15,000.00$17,600.00 $17,600.00 $6,838.71$4,041.00
 ELECTRICAL WORK 0.40 1LS$206,450.00$58,740.00 $58,740.00 $41,036.73$50,000.00
 FURNISH AND INSTALL CONNECTOR PIPE SCREEN (CPS) 0.40 10EA$1,500.00$5,920.00 $59,200.00 $3,352.86$2,550.00
 FURNISH STREETLIGHT POLE WITH ANCHOR BOLTS 1.65 48EA$3,300.00$5,050.00 $242,400.00 $5,577.57$4,400.00
 IMPLEMENTATION OF THE DIVERSION WATER PLAN 0.75 1LS$10,000.00$110,000.00 $110,000.00 $105,362.86$115,000.00
 IMPORTED CLASS A TOPSOIL 1.72 3164CY$95.00$80.00 $253,120.00 $64.47$60.00
 INSTALLATION OF ESA FENCING 0.01 1243LF$5.00$1.50 $1,864.50 $13.51$12.20
 INSTALLATION OF WILDLIFE EXCLUSIONARY FENCING 0.14 1175LF$10.00$18.00 $21,150.00 $22.87$20.00
 LED LUMINAIRES (100W HPS EQUIVALENT) 1.21 48EA$1,000.00$3,700.00 $177,600.00 $3,123.00$3,150.00
 LED COUNTDOWN PEDESTRIAN HEAD (COMPLETE) 0.01 1EA$1,700.00$1,470.00 $1,470.00 $2,128.29$1,348.04
 JUNCTION STRUCTURE PER STD PLAN 333 (MOD) 0.13 2EA$5,500.00$9,530.00 $19,060.00 $8,217.00$8,500.00
 MAINTENANCE AND REMOVAL OF WILDLIFE EXCLUSIONARY FENCING 0.03 1175LF$2.00$3.80 $4,465.00 $10.79$5.60
 MAINTENANCE AND REMOVAL OF ESA FENCING 0 1243LF$2.00$0.45 $559.35 $9.16$5.00
 LED LUMINAIRES (310W HPS EQUIVALENT) 0.01 2EA$1,200.00$822.00 $1,644.00 $1,315.57$822.00
 NEW TENON ON EXISTING SIGNAL MAST ARM 0.04 1EA$5,500.00$5,460.00 $5,460.00 $3,122.43$1,825.00
 NO. 6E PULL BOX INCL COVER 0.07 10EA$2,000.00$1,020.00 $10,200.00 $1,398.00$1,070.00
 PCC CURB & GUTTER, TYPE A2-8, W=1' 0.69 2836LF$30.00$36.00 $102,096.00 $50.04$36.00
 PCC CURB & GUTTER, TYPE A2-8, W=1.5' 0.04 130LF$40.00$50.50 $6,565.00 $78.14$85.00
 PCC CURB & GUTTER, TYPE A3-8, W=1' 0.97 3979LF$30.00$36.00 $143,244.00 $50.31$36.00
 PCC GUTTER, TYPE C 0.08 100LF$45.00$114.00 $11,400.00 $116.93$114.00
 PCC, 4" THICK, INTEGRAL COLOR 1.63 11406SF$19.00$21.00 $239,526.00 $18.69$20.00
 PEDESTRIAN PUSH BUTTON PLATE 0.01 4EA$60.00$294.00 $1,176.00 $159.43$200.00
 POTABLE IRRIGATION SYTEM ALTERNATE BID 0 1LS$1,122,200.00$1.00 $1.00 $156,981.43$35,000.00
 PIPE GATE PER STD PLAN 602, W=15' 0.17 2EA$7,000.00$12,700.00 $25,400.00 $19,416.43$11,900.00
 PREPARATION OF THE SPILL PREVENTION AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) 0.02 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 #8 WIRE 0.12 6981LF$2.00$2.60 $18,150.60 $5.13$2.30
 #6 WIRE 0.29 13858LF$5.00$3.10 $42,959.80 $3.93$2.70
 #10 WIRE 0.03 1964LF$3.00$2.25 $4,419.00 $3.59$2.07
 13'-7" W X 10'-0" H RCB OUTLET STRUCTURE 0.82 1EA$330,950.00$121,000.00 $121,000.00 $174,425.71$185,000.00
 Total Percent100   Total Amount$14,719,345.89