| Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
| 001.06.001 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) |
0.01
| 1 | LS | $5,000.00 | $5,000.00 |
$5,000.00
| $5,000.00 | $5,000.00 |
| 001.06.006 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.02
| 18 | MTH | $500.00 | $500.00 |
$9,000.00
| $500.00 | $500.00 |
| 001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $2,000) |
0
| 1 | LS | $2,000.00 | $2,000.00 |
$2,000.00
| $2,000.00 | $2,000.00 |
| 001.06.013 | PARTNERING (ALLOWANCE OF $25,000) |
0.05
| 25000 | AL | $1.00 | $1.00 |
$25,000.00
| $1.00 | $1.00 |
| 001.07.001 | IMPLEMENTATION OF BMPS |
0.72
| 18 | MTH | $3,500.00 | $21,000.00 |
$378,000.00
| $32,090.00 | $21,000.00 |
| 001.07.009 | RESTORATION OF EXISTING IMPROVEMENTS |
0.15
| 1 | LS | $10,000.00 | $80,000.00 |
$80,000.00
| $256,233.50 | $200,000.00 |
| 001.07.021 | SHORING OF OPEN EXCAVATIONS |
0.38
| 1 | LS | $25,000.00 | $200,000.00 |
$200,000.00
| $153,333.33 | $200,000.00 |
| 001.08.005 | OFFICE FACILITIES |
0.41
| 36 | MTH | $2,500.00 | $6,000.00 |
$216,000.00
| $7,766.67 | $6,000.00 |
| 300.01.057 | REMOVE EXISTING CHAIN LINK FENCE |
0.02
| 440 | LF | $15.00 | $25.00 |
$11,000.00
| $18.33 | $20.00 |
| 300.01.067 | CONCRETE REMOVAL (REINFORCED) |
0.17
| 435 | CY | $250.00 | $200.00 |
$87,000.00
| $137.33 | $150.00 |
| 300.02.003 | UNCLASSIFIED EXCAVATION |
0
| 2 | CY | $65.00 | $550.00 |
$1,100.00
| $583.33 | $550.00 |
| 300.08.003 | DRAINAGE GEOTEXTILE |
0
| 695 | SY | $5.00 | $2.00 |
$1,390.00
| $2.98 | $2.00 |
| 301.02.005 | CRUSHED MISCELLANEOUS BASE |
0.59
| 4660 | CY | $135.00 | $67.00 |
$312,220.00
| $106.67 | $90.00 |
| 302.05.008 | AC CURB, TYPE D1-8 |
0.08
| 5095 | LF | $5.00 | $8.40 |
$42,798.00
| $8.13 | $8.00 |
| 302.05.013 | AC PAVEMENT |
0.79
| 3490 | TON | $130.00 | $120.00 |
$418,800.00
| $131.67 | $125.00 |
| 306.01.121 | 8" PERFORATED CSP, 16 GAGE |
0.24
| 2085 | LF | $18.70 | $60.00 |
$125,100.00
| $52.00 | $50.00 |
| | PREPARATION OF THE RESERVOIR DEWATERING PLAN (STIPULATED UNIT PRICE OF $10,000) |
0.02
| 1 | LS | $10,000.00 | $10,000.00 |
$10,000.00
| $10,000.00 | $10,000.00 |
| | PREPARATION OF THE FUGITIVE DUST CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) |
0
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | PREPARATION OF THE SURFACE WATER DIVERSION PLAN (STIPULATED UNIT PRICE OF $10,000) |
0.02
| 1 | LS | $10,000.00 | $10,000.00 |
$10,000.00
| $10,000.00 | $10,000.00 |
| | REMOVAL AND DISPOSAL OF EXISTING 60" CSP AND SEAL |
0.05
| 1 | LS | $2,300.00 | $24,000.00 |
$24,000.00
| $16,616.67 | $24,000.00 |
| | REMOVAL AND DISPOSAL OF EXISTING 84" CSP AND SEAL |
0.02
| 1 | LS | $3,000.00 | $11,500.00 |
$11,500.00
| $13,500.00 | $11,500.00 |
| | RESERVOIR EXCAVATION, AND TRANSPORTATION AND DISPOSAL OF SEDIMENT (2021) |
7.59
| 400000 | CY | $14.10 | $10.00 |
$4,000,000.00
| $15.83 | $14.50 |
| | RESERVOIR EXCAVATION, AND TRANSPORTATION AND DISPOSAL OF SEDIMENT (2022) |
16.35
| 800000 | CY | $14.30 | $10.77 |
$8,616,000.00
| $12.92 | $14.00 |
| | RESERVOIR EXCAVATION, AND TRANSPORTATION AND DISPOSAL OF SEDIMENT (2023) |
16.90
| 800000 | CY | $14.60 | $11.13 |
$8,904,000.00
| $13.04 | $14.00 |
| | REPAIR ACCESS ROAD (2023) |
0.05
| 25000 | SF | $0.30 | $1.10 |
$27,500.00
| $2.14 | $2.33 |
| | SEPARATION AND DISPOSAL OF ORGANIC MATERIAL AND DEBRIS (2021) |
0.64
| 12000 | TON | $65.00 | $28.00 |
$336,000.00
| $21.50 | $28.00 |
| | SEPARATION AND DISPOSAL OF ORGANIC MATERIAL AND DEBRIS (2022) |
0.64
| 12000 | TON | $65.00 | $28.00 |
$336,000.00
| $21.50 | $28.00 |
| | SEPARATION AND DISPOSAL OF ORGANIC MATERIAL AND DEBRIS (2023) |
0.64
| 12000 | TON | $65.00 | $28.00 |
$336,000.00
| $21.50 | $28.00 |
| | SLURRY FILL(100-E-100 OR 1 SACK SAND) |
0.68
| 2050 | CY | $160.00 | $175.00 |
$358,750.00
| $151.67 | $170.00 |
| | SITE A-1,DRAINAGE SYSTEM 1 INLET |
0.07
| 1 | EA | $235,000.00 | $38,000.00 |
$38,000.00
| $153,666.67 | $148,000.00 |
| | SITE A-1,DRAINAGE SYSTEM 2 INLET |
0.06
| 1 | EA | $165,000.00 | $31,000.00 |
$31,000.00
| $118,000.00 | $148,000.00 |
| | SITE A-2,DRAINAGE SYSTEM 1 INLET |
0.05
| 1 | EA | $160,000.00 | $27,000.00 |
$27,000.00
| $125,666.67 | $140,000.00 |
| | SITE A-2,DRAINAGE SYSTEM 2 INLET |
0.05
| 1 | EA | $105,000.00 | $27,000.00 |
$27,000.00
| $98,333.33 | $130,000.00 |
| | SITE B, DRAINAGE SYSTEM 1 INLET |
0.05
| 1 | EA | $112,000.00 | $27,000.00 |
$27,000.00
| $99,000.00 | $130,000.00 |
| | 102" POLYMER COATED CSP, 12 GAGE |
0.60
| 504 | LF | $385.00 | $630.00 |
$317,520.00
| $660.00 | $630.00 |
| | 24" POLYMER COATED CSP, 12 GAGE |
1.75
| 4184 | LF | $80.00 | $220.00 |
$920,480.00
| $163.33 | $135.00 |
| | 24" POLYMER COATED CSP, 12 GAGE, DROP INLETS |
0.08
| 33 | EA | $1,000.00 | $1,200.00 |
$39,600.00
| $3,000.00 | $3,800.00 |
| | 2 WATER TRUCKS |
2.28
| 400 | DAY | $2,400.00 | $3,000.00 |
$1,200,000.00
| $3,033.33 | $3,000.00 |
| | 60" CS SEEP RING, 8 GAGE, 10' X 10' |
0.13
| 7 | EA | $1,500.00 | $9,700.00 |
$67,900.00
| $7,500.00 | $7,200.00 |
| | 60" CSP ACCESS SHAFT WITH SAFETY LEDGE, 12 GAUGE |
0.32
| 6 | EA | $15,000.00 | $28,000.00 |
$168,000.00
| $36,000.00 | $30,000.00 |
| | 60" POLYMER COATED CSP, 12 GAGE |
1.22
| 1818 | LF | $250.00 | $355.00 |
$645,390.00
| $388.00 | $400.00 |
| | 84" CS SEEP RING, 8 GAGE, 12' X 12' |
0.08
| 5 | EA | $2,000.00 | $8,900.00 |
$44,500.00
| $7,866.67 | $8,900.00 |
| | 84" POLYMER COATED CSP, 12 GAGE |
0.60
| 544 | LF | $320.00 | $580.00 |
$315,520.00
| $560.00 | $580.00 |
| | 84" TO 102" POLYMER COATED CSP ECCENTRIC TRANSITION, 12 GAGE |
0.01
| 1 | EA | $3,500.00 | $5,200.00 |
$5,200.00
| $7,233.33 | $6,500.00 |
| | CLEAN UPSTREAM DAM FACING CONCRETE SLAB (2022) |
0.09
| 60000 | SF | $1.11 | $0.80 |
$48,000.00
| $1.06 | $1.00 |
| | CLEAN UPSTREAM DAM FACING CONCRETE SLAB (2023) |
0.05
| 30000 | SF | $1.11 | $0.80 |
$24,000.00
| $1.06 | $1.00 |
| | CLASS "D3" DRAIN MATERIAL |
0.04
| 285 | CY | $100.00 | $80.00 |
$22,800.00
| $88.33 | $85.00 |
| | CLEARING AND GRUBBING (2021) |
0.30
| 32 | AC | $13,000.00 | $5,000.00 |
$160,000.00
| $3,500.00 | $5,000.00 |
| | CLEARING AND GRUBBING (2022) |
0.09
| 32 | AC | $13,000.00 | $1,500.00 |
$48,000.00
| $2,333.33 | $1,500.00 |
| | CLEARING AND GRUBBING (2023) |
0.09
| 32 | AC | $13,000.00 | $1,500.00 |
$48,000.00
| $2,333.33 | $1,500.00 |
| | CLEARING AND GRUBBING (FOR TEMPORARY ACCESS ROADS) |
0.10
| 6 | AC | $4,000.00 | $9,000.00 |
$54,000.00
| $7,666.67 | $9,000.00 |
| | CONSTRUCT AND REMOVE SILT FENCE (2023) |
0.02
| 1450 | LF | $4.50 | $8.00 |
$11,600.00
| $8.00 | $8.00 |
| | CONSTRUCT WORK PAD (2023) |
0.16
| 83500 | SF | $0.50 | $1.00 |
$83,500.00
| $0.63 | $0.50 |
| | CONSTRUCT ACCESS ROAD (2023) |
0.07
| 37500 | SF | $0.50 | $1.00 |
$37,500.00
| $3.34 | $4.00 |
| | CONTACT GUTTER TYPE B |
0.54
| 5665 | LF | $26.60 | $50.00 |
$283,250.00
| $45.67 | $50.00 |
| | DELETED ITEM 67 |
0
| 1 | LS | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DEBRIS REMOVAL AND MAINTENANCE OF WEST FORK ROAD (ALLOWANCE OF $300,000) |
0.57
| 300000 | AL | $1.00 | $1.00 |
$300,000.00
| $1.00 | $1.00 |
| | DELETED ITEM 68 |
0
| 1 | AC | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 69 |
0
| 1 | CY | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 70 |
0
| 1 | TON | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 71 |
0
| 1 | LS | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 72 |
0
| 1 | LS | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 73 |
0
| 1 | LS | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 74 |
0
| 1 | AC | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 75 |
0
| 1 | CY | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 76 |
0
| 1 | TON | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 84 |
0
| 1 | SF | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 85 |
0
| 1 | SF | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 86 |
0
| 1 | SF | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 87 |
0
| 1 | LF | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 88 |
0
| 1 | SF | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 89 |
0
| 1 | SF | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 90 |
0
| 1 | SF | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 91 |
0
| 1 | LF | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 65 |
0
| 1 | LS | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | DELETED ITEM 66 |
0
| 1 | LS | $0.00 | $0.00 |
$0.00
| $0.00 | $0.00 |
| | GUTTER TYPE A1 |
0.69
| 5425 | LF | $34.70 | $67.00 |
$363,475.00
| $67.00 | $67.00 |
| | GUTTER TYPE A2 |
1.25
| 10150 | LF | $34.10 | $65.00 |
$659,750.00
| $66.67 | $65.00 |
| | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN |
0.61
| 18 | MTH | $1,500.00 | $18,000.00 |
$324,000.00
| $10,500.00 | $12,500.00 |
| | IMPLEMENTATION OF THE RESERVOIR DEWATERING PLAN (2021) |
7.21
| 1 | LS | $150,000.00 | $3,800,000.00 |
$3,800,000.00
| $2,835,514.33 | $3,800,000.00 |
| | IMPLEMENTATION OF THE RESERVOIR DEWATERING PLAN (2022) |
3.61
| 1 | LS | $150,000.00 | $1,900,000.00 |
$1,900,000.00
| $1,320,000.00 | $1,740,000.00 |
| | IMPLEMENTATION OF THE RESERVOIR DEWATERING PLAN (2023) |
4.18
| 1 | LS | $150,000.00 | $2,200,000.00 |
$2,200,000.00
| $1,177,240.00 | $1,011,720.00 |
| | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2021) |
7.21
| 1 | LS | $150,000.00 | $3,800,000.00 |
$3,800,000.00
| $2,949,301.67 | $3,800,000.00 |
| | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2022) |
3.61
| 1 | LS | $150,000.00 | $1,900,000.00 |
$1,900,000.00
| $783,333.33 | $350,000.00 |
| | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2023) |
4.18
| 1 | LS | $150,000.00 | $2,200,000.00 |
$2,200,000.00
| $921,175.50 | $463,526.50 |
| | MOBILIZATION (2023) |
0.70
| 1 | LS | $300,000.00 | $370,000.00 |
$370,000.00
| $1,050,659.67 | $1,350,000.00 |
| | MOBILIZATION (2021) |
4.92
| 1 | LS | $300,000.00 | $2,593,000.00 |
$2,593,000.00
| $2,064,333.33 | $2,100,000.00 |
| | MOBILIZATION (2022) |
0.66
| 1 | LS | $300,000.00 | $350,000.00 |
$350,000.00
| $1,266,666.67 | $1,350,000.00 |
| | VEHICLE AND EQUIPMENT EMISSIONS REPORTING |
0.07
| 18 | MTH | $2,000.00 | $2,000.00 |
$36,000.00
| $5,433.33 | $2,000.00 |
| | UTILITY REPAIRS PER PLAN E |
4.08
| 1 | LS | $1,300,000.00 | $2,150,000.00 |
$2,150,000.00
| $4,442,101.58 | $4,976,304.75 |
| | WATER QUALITY MONITORING AND REPORTING |
0.30
| 400 | DAY | $1,000.00 | $400.00 |
$160,000.00
| $283.33 | $250.00 |
| | Total Percent | 100 | | | | Total Amount | $52,687,643.00 | | |