| Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
| 001.06.002 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) |
0.53
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| 001.06.003 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.11
| 1 | MTH | $500.00 | $500.00 |
$500.00
| $500.00 | $500.00 |
| 001.06.007 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
0.21
| 1 | LS | $1,000.00 | $1,000.00 |
$1,000.00
| $1,000.00 | $1,000.00 |
| 001.07.003 | IMPLEMENTATION OF BMPS |
3.19
| 1 | LS | $15,000.00 | $15,000.00 |
$15,000.00
| $10,000.00 | $10,000.00 |
| 001.08.005 | OFFICE FACILITIES |
4.26
| 2 | MTH | $8,000.00 | $10,000.00 |
$20,000.00
| $7,500.00 | $7,500.00 |
| 001.09.003 | MOBILIZATION |
9.79
| 1 | LS | $21,700.00 | $46,000.00 |
$46,000.00
| $49,000.00 | $49,000.00 |
| 300.04.003 | STRUCTURE EXCAVATION |
8.30
| 65 | CY | $250.00 | $600.00 |
$39,000.00
| $600.00 | $600.00 |
| 300.04.023 | STRUCTURE BACKFILL |
4.47
| 28 | CY | $300.00 | $750.00 |
$21,000.00
| $675.00 | $675.00 |
| 302.05.013 | AC PAVEMENT |
4.77
| 28 | TON | $500.00 | $800.00 |
$22,400.00
| $900.00 | $900.00 |
| 302.06.003 | PCC PAVEMENT |
5.96
| 25 | CY | $1,000.00 | $1,120.00 |
$28,000.00
| $1,060.00 | $1,060.00 |
| 303.01.065 | WATERPROOFING MEMBRANE |
1.26
| 591 | SF | $6.00 | $10.00 |
$5,910.00
| $15.00 | $15.00 |
| 303.01.113 | DRILL AND BOND DOWEL |
0.47
| 40 | LF | $200.00 | $55.00 |
$2,200.00
| $477.50 | $477.50 |
| 601.09.011 | TRAFFIC CONTROL |
20.55
| 1 | LS | $60,000.00 | $96,512.00 |
$96,512.00
| $90,256.00 | $90,256.00 |
| | PREPARATION OF THE BMP PLAN (STIPULATED UNIT PRICE OF $2,500) |
0.53
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | STRUCTURE CONCRETE (RCB DRAIN) |
10.25
| 16 | CY | $3,000.00 | $3,010.00 |
$48,160.00
| $4,505.00 | $4,505.00 |
| | BAR REINFORCING STEEL (SIDEWALK) |
0.64
| 499 | LB | $3.00 | $6.00 |
$2,994.00
| $8.00 | $8.00 |
| | STRUCTURE CONCRETE (SIDEWALK) |
3.83
| 3 | CY | $3,000.00 | $6,000.00 |
$18,000.00
| $5,500.00 | $5,500.00 |
| | TEMPORARY SHORING (RCB DRAIN) |
6.39
| 1 | LS | $20,000.00 | $30,000.00 |
$30,000.00
| $27,500.00 | $27,500.00 |
| | TEMPORARY SHORING (SIDEWALK) |
4.26
| 1 | LS | $10,000.00 | $20,000.00 |
$20,000.00
| $12,500.00 | $12,500.00 |
| | CONCRETE REMOVAL (REINFORCED) (RCB DRAIN) |
4.80
| 16 | CY | $1,000.00 | $1,410.00 |
$22,560.00
| $2,705.00 | $2,705.00 |
| | CONCRETE REMOVAL (REINFORCED) (SIDEWALK) |
1.66
| 3 | CY | $1,000.00 | $2,600.00 |
$7,800.00
| $2,800.00 | $2,800.00 |
| | BAR REINFORCING STEEL (RCB DRAIN) |
3.76
| 3680 | LB | $3.00 | $4.80 |
$17,664.00
| $7.40 | $7.40 |
| | Total Percent | 100 | | | | Total Amount | $469,700.00 | | |