Bid Price History

MTD 768 Soffit Repairs
$469,700.00
03/31/2026
(-)
2
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.53 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.003CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.11 1MTH$500.00$500.00 $500.00 $500.00$500.00
001.06.007CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.21 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.07.003IMPLEMENTATION OF BMPS 3.19 1LS$15,000.00$15,000.00 $15,000.00 $10,000.00$10,000.00
001.08.005OFFICE FACILITIES 4.26 2MTH$8,000.00$10,000.00 $20,000.00 $7,500.00$7,500.00
001.09.003MOBILIZATION 9.79 1LS$21,700.00$46,000.00 $46,000.00 $49,000.00$49,000.00
300.04.003STRUCTURE EXCAVATION 8.30 65CY$250.00$600.00 $39,000.00 $600.00$600.00
300.04.023STRUCTURE BACKFILL 4.47 28CY$300.00$750.00 $21,000.00 $675.00$675.00
302.05.013AC PAVEMENT 4.77 28TON$500.00$800.00 $22,400.00 $900.00$900.00
302.06.003PCC PAVEMENT 5.96 25CY$1,000.00$1,120.00 $28,000.00 $1,060.00$1,060.00
303.01.065WATERPROOFING MEMBRANE 1.26 591SF$6.00$10.00 $5,910.00 $15.00$15.00
303.01.113DRILL AND BOND DOWEL 0.47 40LF$200.00$55.00 $2,200.00 $477.50$477.50
601.09.011TRAFFIC CONTROL 20.55 1LS$60,000.00$96,512.00 $96,512.00 $90,256.00$90,256.00
 PREPARATION OF THE BMP PLAN (STIPULATED UNIT PRICE OF $2,500) 0.53 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 STRUCTURE CONCRETE (RCB DRAIN) 10.25 16CY$3,000.00$3,010.00 $48,160.00 $4,505.00$4,505.00
 BAR REINFORCING STEEL (SIDEWALK) 0.64 499LB$3.00$6.00 $2,994.00 $8.00$8.00
 STRUCTURE CONCRETE (SIDEWALK) 3.83 3CY$3,000.00$6,000.00 $18,000.00 $5,500.00$5,500.00
 TEMPORARY SHORING (RCB DRAIN) 6.39 1LS$20,000.00$30,000.00 $30,000.00 $27,500.00$27,500.00
 TEMPORARY SHORING (SIDEWALK) 4.26 1LS$10,000.00$20,000.00 $20,000.00 $12,500.00$12,500.00
 CONCRETE REMOVAL (REINFORCED) (RCB DRAIN) 4.80 16CY$1,000.00$1,410.00 $22,560.00 $2,705.00$2,705.00
 CONCRETE REMOVAL (REINFORCED) (SIDEWALK) 1.66 3CY$1,000.00$2,600.00 $7,800.00 $2,800.00$2,800.00
 BAR REINFORCING STEEL (RCB DRAIN) 3.76 3680LB$3.00$4.80 $17,664.00 $7.40$7.40
 Total Percent100   Total Amount$469,700.00