| Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
| 001.06.002 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) |
0.05
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| 001.06.003 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.05
| 5 | MTH | $500.00 | $500.00 |
$2,500.00
| $500.00 | $500.00 |
| 001.06.007 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
0.02
| 1 | LS | $1,000.00 | $1,000.00 |
$1,000.00
| $1,000.00 | $1,000.00 |
| 001.06.011 | IMPLEMENTATION OF THE LTWHP |
0.66
| 1 | LS | $10,000.00 | $35,000.00 |
$35,000.00
| $16,505.00 | $12,525.00 |
| 001.07.003 | IMPLEMENTATION OF BMPS |
0.66
| 1 | LS | $20,000.00 | $35,000.00 |
$35,000.00
| $32,399.00 | $35,000.00 |
| 001.07.023 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) |
0.06
| 1 | LS | $3,000.00 | $3,000.00 |
$3,000.00
| $3,000.00 | $3,000.00 |
| 001.07.025 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN |
0.66
| 1 | LS | $45,000.00 | $35,000.00 |
$35,000.00
| $19,879.00 | $15,000.00 |
| 001.07.043 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) |
0.06
| 1 | LS | $3,000.00 | $3,000.00 |
$3,000.00
| $3,000.00 | $3,000.00 |
| 001.07.045 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN |
0.38
| 1 | LS | $25,000.00 | $20,000.00 |
$20,000.00
| $14,275.80 | $15,000.00 |
| 001.08.005 | OFFICE FACILITIES |
0.57
| 6 | MTH | $20,000.00 | $5,000.00 |
$30,000.00
| $5,727.80 | $5,000.00 |
| 001.09.003 | MOBILIZATION |
5.66
| 1 | LS | $500,000.00 | $300,000.00 |
$300,000.00
| $422,358.80 | $450,000.00 |
| 300.01.003 | CLEARING AND GRUBBING |
3.78
| 1 | LS | $500.00 | $200,000.00 |
$200,000.00
| $46,171.00 | $6,800.00 |
| 303.01.003 | STRUCTURE CONCRETE |
0.57
| 4 | CY | $7,000.00 | $7,500.00 |
$30,000.00
| $7,474.40 | $8,000.00 |
| 303.01.115 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) |
0.49
| 129 | LF | $290.00 | $200.00 |
$25,800.00
| $180.60 | $200.00 |
| 601.09.011 | TRAFFIC CONTROL |
0.66
| 1 | LS | $24,500.00 | $35,000.00 |
$35,000.00
| $120,889.40 | $90,000.00 |
| 801.04.021 | LANDSCAPING |
0.38
| 1 | LS | $2,950.00 | $20,000.00 |
$20,000.00
| $10,440.00 | $3,900.00 |
| 801.05.003 | IRRIGATION SYSTEM |
0.45
| 1 | LS | $16,000.00 | $24,000.00 |
$24,000.00
| $19,666.80 | $24,000.00 |
| | REMOVE EXISTING CONCRETE |
0.19
| 1 | LS | $32,000.00 | $10,000.00 |
$10,000.00
| $57,887.00 | $10,000.00 |
| | REPLACE ROOFING MATERIALS |
0.71
| 375 | SF | $46.00 | $100.00 |
$37,500.00
| $128.80 | $100.00 |
| | SHORING OF OPEN EXCAVATIONS FOR NAPLES PUMP STATION |
2.83
| 1 | LS | $45,000.00 | $150,000.00 |
$150,000.00
| $47,839.60 | $20,000.00 |
| | SHORT CIRCUIT, COORDINATION, AND ARC-FLASH STUDY |
0.38
| 2 | EA | $5,000.00 | $10,000.00 |
$20,000.00
| $8,349.20 | $6,996.00 |
| | SHORING OF OPEN EXCAVATIONS FOR CORDOVA WALK PUMP STATION |
2.27
| 1 | LS | $40,000.00 | $120,000.00 |
$120,000.00
| $40,619.80 | $20,000.00 |
| | SOUTHERN CALIFORNIA EDISON WORK (ALLOWANCE OF $20,000) |
0.38
| 20000 | AL | $1.00 | $1.00 |
$20,000.00
| $1.00 | $1.00 |
| | TELEMETRY CABINET WITH ANTENNA AND WIRE/CONDUIT |
0.94
| 2 | EA | $31,000.00 | $25,000.00 |
$50,000.00
| $14,499.00 | $11,751.00 |
| | SUMP PUMP CONTROL PANEL AND WIRE/CONDUIT |
1.89
| 2 | EA | $50,000.00 | $50,000.00 |
$100,000.00
| $37,316.80 | $35,000.00 |
| | TEMPORARY PUMP CONTROL PANEL AND WIRE/CONDUIT FOR CORDOVA WALK PUMP STATION |
0.19
| 1 | LS | $75,000.00 | $10,000.00 |
$10,000.00
| $18,731.60 | $20,000.00 |
| | TEMPORARY PUMP CONTROL PANEL AND WIRE/CONDUIT FOR NAPLES PUMP STATION |
0.19
| 1 | LS | $60,000.00 | $10,000.00 |
$10,000.00
| $18,731.60 | $20,000.00 |
| | TEMPORARY SUMP PUMP CONTROL PANEL AND WIRE/CONDUIT FOR CORDOVA WALK PUMP STATION |
0.19
| 1 | LS | $50,000.00 | $10,000.00 |
$10,000.00
| $15,804.40 | $15,763.00 |
| | TEMPORARY SUMP PUMP CONTROL PANEL AND WIRE/CONDUIT FOR NAPLES PUMP STATION |
0.19
| 1 | LS | $50,000.00 | $10,000.00 |
$10,000.00
| $12,218.00 | $12,000.00 |
| | TRASH RACK |
4.72
| 1 | LS | $450,000.00 | $250,000.00 |
$250,000.00
| $259,648.60 | $250,000.00 |
| | 16-INCHES VERTICAL MIXED FLOW PUMP WITH ELECTRIC MOTOR AT CORDOVA WALK PUMP STATION |
7.55
| 2 | EA | $250,000.00 | $200,000.00 |
$400,000.00
| $230,738.00 | $208,000.00 |
| | 16-INCHES VERTICAL MIXED FLOW PUMP WITH ELECTRIC MOTOR AT NAPLES PUMP STATION |
11.33
| 3 | EA | $300,000.00 | $200,000.00 |
$600,000.00
| $213,691.40 | $200,457.00 |
| | 3-INCH PVC SCHEDULE 80 CONDUIT FOR NAPLES PUMP STATION |
1.76
| 465 | LF | $200.00 | $200.00 |
$93,000.00
| $185.10 | $100.00 |
| | 3" LAYER OF LANDSCAPE MULCH AS TOP DRESS |
0.08
| 400 | SF | $1.50 | $10.00 |
$4,000.00
| $15.20 | $10.00 |
| | 4-INCH PVC SCHEDULE 80 CONDUIT FOR CORDOVA WALK PUMP STATION |
0.32
| 85 | LF | $200.00 | $200.00 |
$17,000.00
| $288.40 | $200.00 |
| | 4-INCH PVC SCHEDULE 80 CONDUIT FOR NAPLES PUMP STATION |
0.60
| 160 | LF | $200.00 | $200.00 |
$32,000.00
| $207.40 | $200.00 |
| | 90 DAY PLANT ESTABLISHMENT PERIOD |
0.09
| 1 | LS | $2,000.00 | $5,000.00 |
$5,000.00
| $5,825.20 | $6,000.00 |
| | ACCESS HATCH |
0.19
| 1 | LS | $120,000.00 | $10,000.00 |
$10,000.00
| $60,214.20 | $24,400.00 |
| | ANNUNCIATOR PANEL AND WIRE/CONDUIT |
0.94
| 2 | EA | $60,000.00 | $25,000.00 |
$50,000.00
| $42,014.20 | $45,000.00 |
| | AGRONOMIC SOIL REPORT |
0.05
| 1 | LS | $300.00 | $2,500.00 |
$2,500.00
| $3,104.20 | $1,021.00 |
| | BUBBLER PANEL AND WIRE/CONDUIT |
0.94
| 2 | EA | $18,000.00 | $25,000.00 |
$50,000.00
| $30,626.40 | $30,000.00 |
| | CLASS A TOPSOIL |
0.14
| 15 | CY | $75.00 | $500.00 |
$7,500.00
| $258.60 | $200.00 |
| | CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $35,000) |
0.66
| 35000 | AL | $1.00 | $1.00 |
$35,000.00
| $1.00 | $1.00 |
| | CENTRAL CONTROLLER AND WIRE/CONDUIT |
1.32
| 2 | EA | $80,000.00 | $35,000.00 |
$70,000.00
| $52,777.00 | $55,000.00 |
| | CONCRETE SEATWALL |
0.40
| 28 | LF | $150.00 | $750.00 |
$21,000.00
| $863.40 | $850.00 |
| | DECORATIVE BOULDERS |
0.09
| 1 | LS | $3,500.00 | $5,000.00 |
$5,000.00
| $7,993.60 | $7,118.00 |
| | DEMOLITION |
2.83
| 1 | LS | $400,000.00 | $150,000.00 |
$150,000.00
| $268,067.20 | $198,250.00 |
| | DISTRIBUTION PANEL AND WIRE/CONDUIT |
3.78
| 2 | EA | $25,000.00 | $100,000.00 |
$200,000.00
| $58,584.20 | $50,000.00 |
| | DISCHARGE PIPES PAINTING AND COATING |
1.13
| 1 | LS | $75,000.00 | $60,000.00 |
$60,000.00
| $87,074.20 | $60,000.00 |
| | GAS DETECTION PANEL WITH COMBUSTIBLE GAS SENSORS AND WIRE/CONDUIT |
1.89
| 2 | EA | $9,500.00 | $50,000.00 |
$100,000.00
| $31,884.00 | $28,750.00 |
| | FURNISH SPARE SUMP PUMP |
1.13
| 2 | EA | $35,000.00 | $30,000.00 |
$60,000.00
| $39,673.40 | $36,000.00 |
| | FURNISH AND INSTALL SUMP PUMP AND ACCESSORIES |
3.11
| 1 | LS | $150,000.00 | $165,000.00 |
$165,000.00
| $132,585.20 | $120,000.00 |
| | FLOAT SWITCH ENCLOSURE AND WIRE/CONDUIT |
0.94
| 2 | EA | $18,000.00 | $25,000.00 |
$50,000.00
| $22,799.40 | $24,572.00 |
| | GROUND ROD COPPER-CLAD (3/4" DIAMETER BY 10') |
0.19
| 4 | EA | $200.00 | $2,500.00 |
$10,000.00
| $1,319.20 | $1,021.00 |
| | GROUND WELL |
0.19
| 2 | EA | $275.00 | $5,000.00 |
$10,000.00
| $2,426.00 | $2,000.00 |
| | GEOTECHNICAL REPORT FOR SHORING AND BRACING FOR NAPLES PUMP STATION |
0.28
| 1 | LS | $20,000.00 | $15,000.00 |
$15,000.00
| $11,651.60 | $15,000.00 |
| | GEOTECHNICAL REPORT FOR SHORING AND BRACING FOR CORDOVA WALK PUMP STATION |
0.28
| 1 | LS | $20,000.00 | $15,000.00 |
$15,000.00
| $11,550.00 | $15,000.00 |
| | IMPLEMENTATION OF DEWATERING PLAN FOR NAPLES PUMP STATION (ALLOWANCE OF $25,000) |
0.47
| 25000 | AL | $1.00 | $1.00 |
$25,000.00
| $1.00 | $1.00 |
| | IMPLEMENTATION OF DEWATERING PLAN FOR CORDOVA WALK PUMP STATION (ALLOWANCE OF $25,000) |
0.47
| 25000 | AL | $1.00 | $1.00 |
$25,000.00
| $1.00 | $1.00 |
| | INJECT CRACK (CHEMICAL GROUT) |
0.47
| 1 | LS | $12,500.00 | $25,000.00 |
$25,000.00
| $38,142.60 | $36,463.00 |
| | INTRUSION ALARM PANEL WITH DOOR CONTACT SWITCH AND WIRE/CONDUIT |
1.89
| 2 | EA | $8,000.00 | $50,000.00 |
$100,000.00
| $25,552.20 | $20,000.00 |
| | LIGHTING AND WIRE/CONDUIT FOR CORDOVA WALK PUMP STATION |
0.94
| 1 | LS | $35,000.00 | $50,000.00 |
$50,000.00
| $50,864.20 | $51,648.00 |
| | LIGHTING AND WIRE/CONDUIT FOR NAPLES PUMP STATION |
0.94
| 1 | LS | $35,000.00 | $50,000.00 |
$50,000.00
| $165,295.20 | $54,287.00 |
| | MAIN PUMP CONTROL PANEL AND WIRE/CONDUIT |
4.72
| 5 | EA | $60,000.00 | $50,000.00 |
$250,000.00
| $61,947.60 | $35,000.00 |
| | MISCELLANEOUS ELECTRICAL WORKS FOR CORDOVA WALK PUMP STATION |
1.51
| 1 | LS | $131,195.00 | $80,000.00 |
$80,000.00
| $263,312.60 | $188,075.00 |
| | MISCELLANEOUS ELECTRICAL WORKS FOR NAPLES PUMP STATION |
1.51
| 1 | LS | $164,237.00 | $80,000.00 |
$80,000.00
| $219,237.60 | $250,000.00 |
| | METERED MAIN SERVICE PANEL AND CONDUIT/WIRE |
0.94
| 1 | LS | $20,000.00 | $50,000.00 |
$50,000.00
| $138,000.20 | $151,000.00 |
| | METERED MAIN SERVICE PEDESTAL WITH CONCRETE FOUNDATION AND WIRE/CONDUIT |
0.94
| 1 | LS | $60,000.00 | $50,000.00 |
$50,000.00
| $63,465.80 | $65,000.00 |
| | MICROTUNNELING (DIRECTIONAL BORING) FOR NAPLES PUMP STATION |
1.27
| 450 | LF | $150.00 | $150.00 |
$67,500.00
| $207.60 | $200.00 |
| | MANUAL TRANSFER SWITCH |
1.89
| 2 | EA | $30,000.00 | $50,000.00 |
$100,000.00
| $21,313.20 | $15,000.00 |
| | MISCELLANEOUS MECHANICAL WORKS |
3.78
| 1 | LS | $400,000.00 | $200,000.00 |
$200,000.00
| $362,846.40 | $364,150.00 |
| | MINI POWER CENTER/ZONE AND WIRE/CONDUIT |
2.83
| 2 | EA | $75,000.00 | $75,000.00 |
$150,000.00
| $38,684.40 | $30,000.00 |
| | OPERATIONAL TESTS |
0.47
| 1 | LS | $50,000.00 | $25,000.00 |
$25,000.00
| $34,706.80 | $30,000.00 |
| | PREPARATION OF DEWATERING PLAN FOR CORDOVA WALK PUMP STATION (STIPULATED UNIT PRICE OF $2,500) |
0.05
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | PREPARATION OF DEWATERING PLAN FOR NAPLES PUMP STATION (STIPULATED UNIT PRICE OF $2,500) |
0.05
| 1 | LS | $2,500.00 | $2,500.00 |
$2,500.00
| $2,500.00 | $2,500.00 |
| | PORTABLE GENERATOR RENTAL FOR CORDOVA WALK PUMP STATION |
0.57
| 6 | MO | $5,000.00 | $5,000.00 |
$30,000.00
| $16,409.20 | $6,314.00 |
| | PORTABLE GENERATOR RENTAL FOR NAPLES PUMP STATION |
0.57
| 6 | MO | $5,000.00 | $5,000.00 |
$30,000.00
| $16,409.20 | $6,314.00 |
| | PRESSURE TANSDUCER ENCLOSURE AND WIRE/CONDUIT |
0.94
| 2 | EA | $15,000.00 | $25,000.00 |
$50,000.00
| $24,491.40 | $25,000.00 |
| | REMOVAL AND DISPOSAL OF LBP/LCP WASTE |
0.34
| 1 | LS | $50,000.00 | $18,200.00 |
$18,200.00
| $32,281.20 | $25,000.00 |
| | Total Percent | 100 | | | | Total Amount | $5,297,000.00 | | |