Naples Island Pump Stations Rehabilitation - Phase II
$5,297,000.00
04/08/2025
826 (C2)
5
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.05 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.003CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.05 5MTH$500.00$500.00 $2,500.00 $500.00$500.00
001.06.007CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.02 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.66 1LS$10,000.00$35,000.00 $35,000.00 $16,505.00$12,525.00
001.07.003IMPLEMENTATION OF BMPS 0.66 1LS$20,000.00$35,000.00 $35,000.00 $32,399.00$35,000.00
001.07.023PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) 0.06 1LS$3,000.00$3,000.00 $3,000.00 $3,000.00$3,000.00
001.07.025IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 0.66 1LS$45,000.00$35,000.00 $35,000.00 $19,879.00$15,000.00
001.07.043PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) 0.06 1LS$3,000.00$3,000.00 $3,000.00 $3,000.00$3,000.00
001.07.045IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN 0.38 1LS$25,000.00$20,000.00 $20,000.00 $14,275.80$15,000.00
001.08.005OFFICE FACILITIES 0.57 6MTH$20,000.00$5,000.00 $30,000.00 $5,727.80$5,000.00
001.09.003MOBILIZATION 5.66 1LS$500,000.00$300,000.00 $300,000.00 $422,358.80$450,000.00
300.01.003CLEARING AND GRUBBING 3.78 1LS$500.00$200,000.00 $200,000.00 $46,171.00$6,800.00
303.01.003STRUCTURE CONCRETE 0.57 4CY$7,000.00$7,500.00 $30,000.00 $7,474.40$8,000.00
303.01.115DRILL AND BOND DOWEL (EPOXY CARTRIDGE) 0.49 129LF$290.00$200.00 $25,800.00 $180.60$200.00
601.09.011TRAFFIC CONTROL 0.66 1LS$24,500.00$35,000.00 $35,000.00 $120,889.40$90,000.00
801.04.021LANDSCAPING 0.38 1LS$2,950.00$20,000.00 $20,000.00 $10,440.00$3,900.00
801.05.003IRRIGATION SYSTEM 0.45 1LS$16,000.00$24,000.00 $24,000.00 $19,666.80$24,000.00
 REMOVE EXISTING CONCRETE 0.19 1LS$32,000.00$10,000.00 $10,000.00 $57,887.00$10,000.00
 REPLACE ROOFING MATERIALS 0.71 375SF$46.00$100.00 $37,500.00 $128.80$100.00
 SHORING OF OPEN EXCAVATIONS FOR NAPLES PUMP STATION 2.83 1LS$45,000.00$150,000.00 $150,000.00 $47,839.60$20,000.00
 SHORT CIRCUIT, COORDINATION, AND ARC-FLASH STUDY 0.38 2EA$5,000.00$10,000.00 $20,000.00 $8,349.20$6,996.00
 SHORING OF OPEN EXCAVATIONS FOR CORDOVA WALK PUMP STATION 2.27 1LS$40,000.00$120,000.00 $120,000.00 $40,619.80$20,000.00
 SOUTHERN CALIFORNIA EDISON WORK (ALLOWANCE OF $20,000) 0.38 20000AL$1.00$1.00 $20,000.00 $1.00$1.00
 TELEMETRY CABINET WITH ANTENNA AND WIRE/CONDUIT 0.94 2EA$31,000.00$25,000.00 $50,000.00 $14,499.00$11,751.00
 SUMP PUMP CONTROL PANEL AND WIRE/CONDUIT 1.89 2EA$50,000.00$50,000.00 $100,000.00 $37,316.80$35,000.00
 TEMPORARY PUMP CONTROL PANEL AND WIRE/CONDUIT FOR CORDOVA WALK PUMP STATION 0.19 1LS$75,000.00$10,000.00 $10,000.00 $18,731.60$20,000.00
 TEMPORARY PUMP CONTROL PANEL AND WIRE/CONDUIT FOR NAPLES PUMP STATION 0.19 1LS$60,000.00$10,000.00 $10,000.00 $18,731.60$20,000.00
 TEMPORARY SUMP PUMP CONTROL PANEL AND WIRE/CONDUIT FOR CORDOVA WALK PUMP STATION 0.19 1LS$50,000.00$10,000.00 $10,000.00 $15,804.40$15,763.00
 TEMPORARY SUMP PUMP CONTROL PANEL AND WIRE/CONDUIT FOR NAPLES PUMP STATION 0.19 1LS$50,000.00$10,000.00 $10,000.00 $12,218.00$12,000.00
 TRASH RACK 4.72 1LS$450,000.00$250,000.00 $250,000.00 $259,648.60$250,000.00
 16-INCHES VERTICAL MIXED FLOW PUMP WITH ELECTRIC MOTOR AT CORDOVA WALK PUMP STATION 7.55 2EA$250,000.00$200,000.00 $400,000.00 $230,738.00$208,000.00
 16-INCHES VERTICAL MIXED FLOW PUMP WITH ELECTRIC MOTOR AT NAPLES PUMP STATION 11.33 3EA$300,000.00$200,000.00 $600,000.00 $213,691.40$200,457.00
 3-INCH PVC SCHEDULE 80 CONDUIT FOR NAPLES PUMP STATION 1.76 465LF$200.00$200.00 $93,000.00 $185.10$100.00
 3" LAYER OF LANDSCAPE MULCH AS TOP DRESS 0.08 400SF$1.50$10.00 $4,000.00 $15.20$10.00
 4-INCH PVC SCHEDULE 80 CONDUIT FOR CORDOVA WALK PUMP STATION 0.32 85LF$200.00$200.00 $17,000.00 $288.40$200.00
 4-INCH PVC SCHEDULE 80 CONDUIT FOR NAPLES PUMP STATION 0.60 160LF$200.00$200.00 $32,000.00 $207.40$200.00
 90 DAY PLANT ESTABLISHMENT PERIOD 0.09 1LS$2,000.00$5,000.00 $5,000.00 $5,825.20$6,000.00
 ACCESS HATCH 0.19 1LS$120,000.00$10,000.00 $10,000.00 $60,214.20$24,400.00
 ANNUNCIATOR PANEL AND WIRE/CONDUIT 0.94 2EA$60,000.00$25,000.00 $50,000.00 $42,014.20$45,000.00
 AGRONOMIC SOIL REPORT 0.05 1LS$300.00$2,500.00 $2,500.00 $3,104.20$1,021.00
 BUBBLER PANEL AND WIRE/CONDUIT 0.94 2EA$18,000.00$25,000.00 $50,000.00 $30,626.40$30,000.00
 CLASS A TOPSOIL 0.14 15CY$75.00$500.00 $7,500.00 $258.60$200.00
 CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $35,000) 0.66 35000AL$1.00$1.00 $35,000.00 $1.00$1.00
 CENTRAL CONTROLLER AND WIRE/CONDUIT 1.32 2EA$80,000.00$35,000.00 $70,000.00 $52,777.00$55,000.00
 CONCRETE SEATWALL 0.40 28LF$150.00$750.00 $21,000.00 $863.40$850.00
 DECORATIVE BOULDERS 0.09 1LS$3,500.00$5,000.00 $5,000.00 $7,993.60$7,118.00
 DEMOLITION 2.83 1LS$400,000.00$150,000.00 $150,000.00 $268,067.20$198,250.00
 DISTRIBUTION PANEL AND WIRE/CONDUIT 3.78 2EA$25,000.00$100,000.00 $200,000.00 $58,584.20$50,000.00
 DISCHARGE PIPES PAINTING AND COATING 1.13 1LS$75,000.00$60,000.00 $60,000.00 $87,074.20$60,000.00
 GAS DETECTION PANEL WITH COMBUSTIBLE GAS SENSORS AND WIRE/CONDUIT 1.89 2EA$9,500.00$50,000.00 $100,000.00 $31,884.00$28,750.00
 FURNISH SPARE SUMP PUMP 1.13 2EA$35,000.00$30,000.00 $60,000.00 $39,673.40$36,000.00
 FURNISH AND INSTALL SUMP PUMP AND ACCESSORIES 3.11 1LS$150,000.00$165,000.00 $165,000.00 $132,585.20$120,000.00
 FLOAT SWITCH ENCLOSURE AND WIRE/CONDUIT 0.94 2EA$18,000.00$25,000.00 $50,000.00 $22,799.40$24,572.00
 GROUND ROD COPPER-CLAD (3/4" DIAMETER BY 10') 0.19 4EA$200.00$2,500.00 $10,000.00 $1,319.20$1,021.00
 GROUND WELL 0.19 2EA$275.00$5,000.00 $10,000.00 $2,426.00$2,000.00
 GEOTECHNICAL REPORT FOR SHORING AND BRACING FOR NAPLES PUMP STATION 0.28 1LS$20,000.00$15,000.00 $15,000.00 $11,651.60$15,000.00
 GEOTECHNICAL REPORT FOR SHORING AND BRACING FOR CORDOVA WALK PUMP STATION 0.28 1LS$20,000.00$15,000.00 $15,000.00 $11,550.00$15,000.00
 IMPLEMENTATION OF DEWATERING PLAN FOR NAPLES PUMP STATION (ALLOWANCE OF $25,000) 0.47 25000AL$1.00$1.00 $25,000.00 $1.00$1.00
 IMPLEMENTATION OF DEWATERING PLAN FOR CORDOVA WALK PUMP STATION (ALLOWANCE OF $25,000) 0.47 25000AL$1.00$1.00 $25,000.00 $1.00$1.00
 INJECT CRACK (CHEMICAL GROUT) 0.47 1LS$12,500.00$25,000.00 $25,000.00 $38,142.60$36,463.00
 INTRUSION ALARM PANEL WITH DOOR CONTACT SWITCH AND WIRE/CONDUIT 1.89 2EA$8,000.00$50,000.00 $100,000.00 $25,552.20$20,000.00
 LIGHTING AND WIRE/CONDUIT FOR CORDOVA WALK PUMP STATION 0.94 1LS$35,000.00$50,000.00 $50,000.00 $50,864.20$51,648.00
 LIGHTING AND WIRE/CONDUIT FOR NAPLES PUMP STATION 0.94 1LS$35,000.00$50,000.00 $50,000.00 $165,295.20$54,287.00
 MAIN PUMP CONTROL PANEL AND WIRE/CONDUIT 4.72 5EA$60,000.00$50,000.00 $250,000.00 $61,947.60$35,000.00
 MISCELLANEOUS ELECTRICAL WORKS FOR CORDOVA WALK PUMP STATION 1.51 1LS$131,195.00$80,000.00 $80,000.00 $263,312.60$188,075.00
 MISCELLANEOUS ELECTRICAL WORKS FOR NAPLES PUMP STATION 1.51 1LS$164,237.00$80,000.00 $80,000.00 $219,237.60$250,000.00
 METERED MAIN SERVICE PANEL AND CONDUIT/WIRE 0.94 1LS$20,000.00$50,000.00 $50,000.00 $138,000.20$151,000.00
 METERED MAIN SERVICE PEDESTAL WITH CONCRETE FOUNDATION AND WIRE/CONDUIT 0.94 1LS$60,000.00$50,000.00 $50,000.00 $63,465.80$65,000.00
 MICROTUNNELING (DIRECTIONAL BORING) FOR NAPLES PUMP STATION 1.27 450LF$150.00$150.00 $67,500.00 $207.60$200.00
 MANUAL TRANSFER SWITCH 1.89 2EA$30,000.00$50,000.00 $100,000.00 $21,313.20$15,000.00
 MISCELLANEOUS MECHANICAL WORKS 3.78 1LS$400,000.00$200,000.00 $200,000.00 $362,846.40$364,150.00
 MINI POWER CENTER/ZONE AND WIRE/CONDUIT 2.83 2EA$75,000.00$75,000.00 $150,000.00 $38,684.40$30,000.00
 OPERATIONAL TESTS 0.47 1LS$50,000.00$25,000.00 $25,000.00 $34,706.80$30,000.00
 PREPARATION OF DEWATERING PLAN FOR CORDOVA WALK PUMP STATION (STIPULATED UNIT PRICE OF $2,500) 0.05 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 PREPARATION OF DEWATERING PLAN FOR NAPLES PUMP STATION (STIPULATED UNIT PRICE OF $2,500) 0.05 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 PORTABLE GENERATOR RENTAL FOR CORDOVA WALK PUMP STATION 0.57 6MO$5,000.00$5,000.00 $30,000.00 $16,409.20$6,314.00
 PORTABLE GENERATOR RENTAL FOR NAPLES PUMP STATION 0.57 6MO$5,000.00$5,000.00 $30,000.00 $16,409.20$6,314.00
 PRESSURE TANSDUCER ENCLOSURE AND WIRE/CONDUIT 0.94 2EA$15,000.00$25,000.00 $50,000.00 $24,491.40$25,000.00
 REMOVAL AND DISPOSAL OF LBP/LCP WASTE 0.34 1LS$50,000.00$18,200.00 $18,200.00 $32,281.20$25,000.00
 Total Percent100   Total Amount$5,297,000.00