Bid Price History

Santa Anita Debris Dam Seismic Strengthening Project
$20,464,616.50
05/15/2025
(-)
10
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.01 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.003CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.04 15MTH$500.00$500.00 $7,500.00 $500.00$500.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.17 1LS$43,590.00$34,000.00 $34,000.00 $33,660.00$28,250.00
001.07.005PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $2,500) 0.01 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.07.007IMPLEMENTATION OF THE SWPPP 1.58 1LS$53,200.00$324,000.00 $324,000.00 $219,717.41$247,576.41
001.07.021SHORING OF OPEN EXCAVATIONS 0.17 1LS$8,180.00$35,000.00 $35,000.00 $85,330.00$45,500.00
001.07.045IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN 0.05 1LS$50,000.00$10,000.00 $10,000.00 $21,730.00$20,000.00
001.08.005OFFICE FACILITIES 0.37 15MTH$10,000.00$5,000.00 $75,000.00 $11,810.53$6,950.00
001.09.003MOBILIZATION 10.26 1LS$572,925.00$2,100,000.00 $2,100,000.00 $1,973,671.36$2,162,830.01
300.01.003CLEARING AND GRUBBING 0.24 1LS$57,290.00$50,000.00 $50,000.00 $127,413.00$68,065.00
300.01.063AC PAVEMENT REMOVAL 0.10 27630SF$2.46$0.75 $20,722.50 $1.54$1.08
300.02.003UNCLASSIFIED EXCAVATION 1.74 8927CY$22.36$40.00 $357,080.00 $48.40$40.00
304.02.013CABLE RAILING (CALTRANS STD PLAN B11-47) 0.05 71LF$40.99$150.00 $10,650.00 $265.27$260.50
306.01.3086" DUCTILE IRON PIPE 0.13 50LF$163.60$520.00 $26,000.00 $526.80$275.00
500.00.015VIDEO INSPECTION 0.08 1LS$16,370.00$15,510.00 $15,510.00 $16,156.00$11,880.00
 PERMEABLE ZONE MATERIAL 1.05 2691CY$178.41$80.00 $215,280.00 $132.40$143.50
 PREPARATION OF THE NOISE MITIGATION PLAN (STIPULATED PRICE OF $15,000) 0.07 1LS$15,000.00$15,000.00 $15,000.00 $15,000.00$15,000.00
 PREPARATION OF THE FUGITIVE DUST CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) 0.01 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 PREPARATION OF THE SURFACE WATER DIVERSION PLAN (STIPULATED UNIT PRICE OF $10,500) 0.05 1LS$10,500.00$10,500.00 $10,500.00 $10,500.00$10,500.00
 PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $5,000) 0.02 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
 PREPARATION OF THE SPILL PREVENTION AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) 0.01 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 REMOVABLE BOLLARD 0.03 2EA$3,275.00$3,000.00 $6,000.00 $3,394.73$3,000.00
 REMOVAL AND DISPOSAL OF LBP/LCP WASTE 0.07 1LS$5,000.00$14,000.00 $14,000.00 $33,043.00$25,550.00
 REMOVE EXISTING LONGITUDINAL GUTTER 0.02 77LF$32.75$40.00 $3,080.00 $35.70$29.50
 REMOVE EXISTING CHAIN LINK FENCE AND PIPE GATE 0.03 266LF$16.35$20.00 $5,320.00 $20.20$20.00
 REMOVE EXISTING STAFF GAGE POSTS 0.01 9EA$408.89$300.00 $2,700.00 $380.20$323.00
 REMOVE EXISTING TREES 0.16 16EA$7,453.13$2,000.00 $32,000.00 $2,923.45$2,662.50
 REMOVE EXISTING INTAKE TOWER, CATWALK, AND STAIRWAY 0.49 1LS$49,100.00$100,000.00 $100,000.00 $88,794.20$84,100.00
 SPILLWAY WALL BUTTRESS COMPLETE IN PLACE 29.32 1LS$4,816,380.00$6,000,000.00 $6,000,000.00 $4,821,882.54$4,450,000.00
 SPLASH WALL 0.03 1CY$1,000.00$6,700.00 $6,700.00 $2,945.00$1,475.00
 STRUCTURE & ROADWAY FOUNDATION PREPARATION 0.73 2478CY$49.10$60.00 $148,680.00 $101.44$52.50
 TEMPORARY SOUND BARRIER 0.32 1000LF$596.25$65.00 $65,000.00 $307.40$304.00
 TOE DRAIN WEIR VAULT 0.11 1LS$16,370.00$22,000.00 $22,000.00 $93,557.87$69,250.00
 TRUCK WHEEL STOP 0.01 1EA$820.00$1,700.00 $1,700.00 $1,599.00$1,450.00
 TREE PRUNING ($30,000 ALLOWANCE) 0.15 30000AL$1.00$1.00 $30,000.00 $1.00$1.00
 18" WIDE CONCRETE V-DITCH 0.46 627LF$25.00$150.00 $94,050.00 $112.02$130.00
 12"X12" PVC CATCH BASIN 0.01 1EA$1,640.00$2,800.00 $2,800.00 $2,474.57$2,500.00
 4" CPVC GATE VALVE 0.01 1EA$1,640.00$2,400.00 $2,400.00 $6,432.30$5,050.00
 4" PVC PIPE 0.02 30LF$82.00$160.00 $4,800.00 $209.50$169.00
 3' WIDE CONCRETE V-DITCH 0.09 75LF$49.07$235.00 $17,625.00 $236.90$222.00
 48" RCP & APPURTENANCES 0.53 150LF$676.20$720.00 $108,000.00 $749.19$745.47
 5' TALL CHAIN LINK FENCE 0.14 170LF$60.00$170.00 $28,900.00 $158.27$146.00
 48" POOL DRAIN CIPP LINER 1.44 330LF$1,391.30$893.00 $294,690.00 $1,030.59$945.95
 8" NON-PERFORATED HDPE PIPE & APPURTENANCES 0.04 122LF$73.69$70.00 $8,540.00 $136.70$105.00
 8" PERFORATED HDPE PIPE & APPURTENANCES 0.07 289LF$81.83$50.00 $14,450.00 $48.10$44.00
 8" CLEANOUT RISER 0.12 4EA$823.00$6,100.00 $24,400.00 $3,319.20$3,006.00
 8" DUCK BILL CHECK VALVE 0.03 1EA$3,270.00$6,800.00 $6,800.00 $5,571.30$5,000.00
 AS-BUILT SCHEDULE (STIPULATED UNIT PRICE OF $1,000) 0 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
 BAT EXCLUSION DEVICES ($10,000 ALLOWANCE) 0.05 10000AL$1.00$1.00 $10,000.00 $1.00$1.00
 AUTOMATED DATA ACQUISITION SYSTEM (ADAS) 0.35 1LS$163,680.00$72,000.00 $72,000.00 $250,119.70$115,950.00
 CATWALK & STAIRWAY COMPLETE IN PLACE 0.90 1LS$47,960.00$184,000.00 $184,000.00 $173,087.60$167,858.00
 CATWALK STRUCTURAL (STEEL, PLATE, HANDRAILING) 2.69 1LS$182,740.00$550,000.00 $550,000.00 $506,150.00$397,500.00
 BUTTRESS FILL 4.44 16505CY$29.81$55.00 $907,775.00 $52.00$44.50
 CHANNEL WALL REPAIR 0.04 1LS$8,180.00$7,500.00 $7,500.00 $17,369.59$7,760.00
 CRUSHED ROCK 3.47 3548CY$104.34$200.00 $709,600.00 $161.73$157.50
 CONTROL BUILDING 3.42 1LS$286,450.00$700,000.00 $700,000.00 $888,627.48$700,500.00
 DELETED (BID ITEM 70) 0 1LS$0.00$0.00 $0.00 $0.00$0.00
 DELETED (BID ITEM 49) 0 1LS$0.00$0.00 $0.00 $0.00$0.00
 DECOMPOSED GRANITE PAVEMENT, 8" THICK 0.45 3660SF$130.00$25.00 $91,500.00 $15.99$17.00
 DECOMMISSION EXISTING PIEZOMETERS 0.14 3EA$8,183.33$9,500.00 $28,500.00 $6,718.70$5,100.00
 DAVIT CRANE 0.04 1LS$7,370.00$9,000.00 $9,000.00 $48,415.65$32,350.00
 DELETED (BID ITEM 61) 0 1LS$0.00$0.00 $0.00 $0.00$0.00
 DELETED (BID ITEM 63) 0 1LS$0.00$0.00 $0.00 $0.00$0.00
 ELECTRICAL WORK 2.22 1LS$899,990.00$454,000.00 $454,000.00 $702,898.50$644,662.00
 DOWNSTREAM RIPRAP (CLASS IV) 2.77 7571CY$225.00$75.00 $567,825.00 $208.92$215.00
 FIXED METAL BOLLARD 0.04 5EA$2,456.00$1,830.00 $9,150.00 $2,678.11$2,177.00
 GROUTED ROCK CURB & GUTTER 0.02 32LF$1,000.00$150.00 $4,800.00 $1,204.65$176.50
 IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN 0.73 15MTH$3,000.00$10,000.00 $150,000.00 $11,533.85$9,250.00
 IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN ($300,000 ALLOWANCE) 1.47 300000AL$1.00$1.00 $300,000.00 $1.00$1.00
 INSTALLATION OF WILDLIFE EXCLUSIONARY FENCING 0.34 3500LF$10.00$20.00 $70,000.00 $12.06$8.75
 INSTRUMENTATION 2.08 1LS$447,190.00$425,000.00 $425,000.00 $561,982.00$613,000.00
 INTAKE TOWER COMPLETE IN PLACE 7.33 1LS$916,730.00$1,500,000.00 $1,500,000.00 $1,396,449.03$1,552,500.00
 INSTALLATION OF ESA FENCING 0.08 2000LF$6.00$8.50 $17,000.00 $10.57$8.25
 INTAKE TOWER GATE & ACTUATOR 1.12 1LS$81,840.00$230,000.00 $230,000.00 $283,923.60$210,000.00
 INTAKE TOWER TRASH RACK COMPLETE IN PLACE 2.17 1LS$16,370.00$445,000.00 $445,000.00 $252,696.53$138,000.00
 INTAKE TRASH RACK 0.61 5EA$128,492.00$25,000.00 $125,000.00 $100,750.92$107,355.59
 MAINTENANCE AND REMOVAL OF TEMPORARY SOUND BARRIER 0.15 1000LF$80.00$30.00 $30,000.00 $32.58$20.00
 MAINTENANCE AND REMOVAL OF WILDLIFE EXCLUSIONARY FENCING 0.19 3500LF$2.00$11.00 $38,500.00 $13.91$10.50
 MAINTENANCE AND REMOVAL OF ESA FENCING 0.07 2000LF$2.00$7.50 $15,000.00 $18.54$5.18
 LONGITUDINAL GUTTER 0.07 73LF$81.78$200.00 $14,600.00 $223.70$207.50
 METAL BEAM GUARD RAILING 0.26 405LF$65.48$131.00 $53,055.00 $147.25$148.00
 NEW STAFF GAGE BOARDS 0.08 6EA$52,171.67$2,800.00 $16,800.00 $2,396.00$2,400.00
 NOISE MONITORING AND REPORTING 0.29 15MTH$6,000.00$4,000.00 $60,000.00 $5,260.38$4,000.00
 MSE RETAINING WALLS 1.47 1500SF$223.59$200.00 $300,000.00 $190.75$185.00
 OGEE WEIR COMPLETE IN PLACE 2 1LS$380,110.00$410,000.00 $410,000.00 $622,311.90$315,000.00
 PCC CURB & GUTTER, TYPE B2 0.06 124LF$1,000.00$106.00 $13,144.00 $124.92$117.50
 PCC CURB & GUTTER, TYPE A2 0.05 98LF$50.00$105.00 $10,290.00 $159.20$130.00
 PCC PAVEMENT & PCC WALKWAY 3.23 1202CY$819.83$550.00 $661,100.00 $794.31$762.50
 UPSTREAM RIPRAP (CLASS V) 2.15 8792CY$260.00$50.00 $439,600.00 $187.49$174.00
 WATER TRUCK 2.29 260DAY$2,000.00$1,800.00 $468,000.00 $1,366.00$1,361.50
 Total Percent100   Total Amount$20,464,616.50