Bid Price History

Baldwin Lake and Tule Pond Restoration Project
$32,172,345.00
05/19/2026
567 (A5)
3
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.01 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.003CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.03 18MTH$500.00$500.00 $9,000.00 $500.00$500.00
001.06.007CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.16 1LS$20,000.00$50,000.00 $50,000.00 $30,937.33$32,812.00
001.06.013PARTNERING (ALLOWANCE OF $30,000) 0.09 30000AL$1.00$1.00 $30,000.00 $1.00$1.00
001.07.003IMPLEMENTATION OF BMPS 1.94 1LS$150,000.00$625,000.00 $625,000.00 $783,517.00$625,000.00
001.07.023PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $5000) 0.02 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
001.07.025IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 0.31 1LS$338,000.00$100,000.00 $100,000.00 $261,943.00$100,000.00
001.08.005OFFICE FACILITIES 0.25 18MTH$5,000.00$4,500.00 $81,000.00 $7,420.67$7,762.00
001.09.003MOBILIZATION 7.55 1LS$1,865,000.00$2,430,000.00 $2,430,000.00 $1,370,947.33$1,500,000.00
300.01.003CLEARING AND GRUBBING 0.23 1LS$59,500.00$75,000.00 $75,000.00 $88,846.17$87,500.00
300.01.003CLEARING AND GRUBBING 0.11 1LS$20,500.00$35,000.00 $35,000.00 $88,846.17$87,500.00
300.01.005ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) 0.16 35EA$1,000.00$1,450.00 $50,750.00 $1,714.50$1,718.50
300.01.005ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) 0.15 35EA$1,000.00$1,400.00 $49,000.00 $1,714.50$1,718.50
300.01.014TREE REMOVAL (13"-24" DIAMETER) 1.59 128EA$1,000.00$4,000.00 $512,000.00 $3,928.83$4,245.50
300.01.014TREE REMOVAL (13"-24" DIAMETER) 0.38 48EA$1,000.00$2,575.00 $123,600.00 $3,928.83$4,245.50
300.01.057REMOVE EXISTING CHAIN LINK FENCE 0.01 51LF$70.00$50.00 $2,550.00 $64.67$50.00
300.01.067CONCRETE REMOVAL (REINFORCED) 0.03 16CY$495.00$650.00 $10,400.00 $1,337.00$850.00
300.01.067CONCRETE REMOVAL (REINFORCED) 0.02 7CY$495.00$1,050.00 $7,350.00 $1,337.00$850.00
300.04.013STRUCTURE EXCAVATION (RETAINING WALL) 1.02 4420CY$40.00$74.00 $327,080.00 $122.00$100.00
300.05.002IMPORTED BORROW 1.70 9130CY$100.00$60.00 $547,800.00 $73.33$60.00
301.02.003CRUSHED AGGREGATE BASE 0.52 1230CY$50.00$135.00 $166,050.00 $150.67$150.00
303.01.014STRUCTURE CONCRETE (RETAINING WALL) 6.76 870CY$1,230.00$2,500.00 $2,175,000.00 $1,828.00$1,984.00
303.01.041BAR REINFORCING STEEL 0.64 147200LB$2.50$1.40 $206,080.00 $2.13$2.00
303.01.065WATERPROOFING MEMBRANE 1.43 28840SF$9.00$16.00 $461,440.00 $12.33$15.00
303.01.309CATCH BASIN PER STD PLAN 300, W=21 0.09 1EA$25,000.00$30,000.00 $30,000.00 $56,200.33$64,601.00
303.01.346MANHOLE PER STD PLAN 320 0.06 1EA$20,000.00$20,000.00 $20,000.00 $20,398.33$20,000.00
303.02.005AIR PLACED CONCRETE (INCL WIRE MESH) 1.21 390CY$1,300.00$1,000.00 $390,000.00 $1,061.33$1,000.00
304.03.003CHAIN LINK FENCE, 8' HIGH 0.03 44LF$90.00$250.00 $11,000.00 $266.33$250.00
306.01.11936" CSP, 12 GAGE 0.03 25LF$400.00$375.00 $9,375.00 $941.67$700.00
306.01.12918" RCP, 2000 D 0.16 196LF$550.00$265.00 $51,940.00 $570.00$500.00
306.01.12927" RCP, 2000 D 0.04 40LF$700.00$300.00 $12,000.00 $828.00$750.00
306.01.12948" RCP, 2000 D 0.07 45LF$650.00$500.00 $22,500.00 $786.11$650.00
306.01.12948" RCP, 2000 D 0.07 59LF$650.00$400.00 $23,600.00 $786.11$650.00
306.01.12948" RCP, 2000 D 0.14 98LF$650.00$450.00 $44,100.00 $786.11$650.00
306.01.12936" RCP, 2000 D 0.34 313LF$550.00$350.00 $109,550.00 $630.67$500.00
306.01.38027" CONCRETE COLLAR 0.01 1EA$3,000.00$3,750.00 $3,750.00 $8,436.67$6,500.00
306.01.38048" CONCRETE COLLAR 0.01 1EA$4,000.00$4,000.00 $4,000.00 $11,146.33$8,000.00
306.01.38048" CONCRETE COLLAR 0.01 1EA$4,000.00$4,000.00 $4,000.00 $11,146.33$8,000.00
306.01.38018" CONCRETE COLLAR 0.01 1EA$2,000.00$3,500.00 $3,500.00 $6,451.33$5,000.00
306.01.503RESTORATION OF PERMANENT SURFACING 0.12 1LS$20,000.00$40,000.00 $40,000.00 $34,090.67$40,000.00
601.09.011TRAFFIC CONTROL 3.98 1LS$320,000.00$1,279,000.00 $1,279,000.00 $1,182,287.67$1,279,000.00
801.04.021LANDSCAPING 1.43 1LS$636,317.12$460,000.00 $460,000.00 $391,015.33$348,671.50
801.04.021LANDSCAPING 0.54 1LS$166,589.80$175,000.00 $175,000.00 $391,015.33$348,671.50
801.05.003IRRIGATION SYSTEM 0.93 1LS$368,560.00$300,000.00 $300,000.00 $241,446.00$235,338.00
801.05.003IRRIGATION SYSTEM 0.43 1LS$165,167.75$138,000.00 $138,000.00 $241,446.00$235,338.00
801.06.003PLANT ESTABLISHMENT PERIOD 0.11 1LS$103,911.70$35,000.00 $35,000.00 $61,956.00$50,000.00
 DIFFUSED AERATION SYSTEM 0.17 1LS$30,000.00$55,000.00 $55,000.00 $155,499.00$55,000.00
 DECORATIVE GUARDRAIL AT TULE POND 1.34 94LF$275.00$4,600.00 $432,400.00 $2,235.33$1,106.00
 DECORATIVE SITE CONCRETE PAVING 0.68 1LS$159,770.00$220,000.00 $220,000.00 $206,008.00$220,000.00
 DECORATIVE BOULDERS 0.02 20EA$75.00$300.00 $6,000.00 $436.50$342.50
 DECORATIVE BOULDERS 0.14 135EA$75.00$335.00 $45,225.00 $436.50$342.50
 DECOMPOSED GRANITE SURFACING 0.02 777SF$15.00$10.00 $7,770.00 $16.33$10.00
 CROWN REDUCTION, TREE 0.19 1LS$58,000.00$62,500.00 $62,500.00 $96,768.67$63,750.00
 CROWN REDUCTION, TREE 0.20 1LS$21,500.00$65,000.00 $65,000.00 $96,768.67$63,750.00
 GENERAL CONDITIONS 0.19 1LS$750,000.00$60,000.00 $60,000.00 $268,028.67$60,000.00
 FLAT COBBLE CURB AT BOAT LAUNCH 0.02 76LF$150.00$105.00 $7,980.00 $390.00$215.00
 EXCAVATION OF SEDIMENT FROM BALDWIN LAKE 0.59 38260TON$33.00$5.00 $191,300.00 $33.25$26.25
 EXCAVATION OF SEDIMENT FROM BALDWIN LAKE 2.18 31185TON$33.00$22.50 $701,662.50 $33.25$26.25
 EXCAVATION OF SEDIMENT FROM TULE POND 0.68 8755TON$33.00$25.00 $218,875.00 $127.00$80.00
 ELECTRICAL WORK 0.03 1LS$4,208.00$11,000.00 $11,000.00 $80,195.67$69,312.00
 ELECTRICAL WORK 0.33 1LS$67,518.00$105,000.00 $105,000.00 $80,195.67$69,312.00
 INTERPRETIVE SIGNAGE 0.03 5EA$1,500.00$2,000.00 $10,000.00 $9,130.67$7,392.00
 INLET STRUCTURE PVC CONNECTION 0.02 1EA$1,000.00$5,500.00 $5,500.00 $11,468.00$5,500.00
 IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN 2.33 1LS$750,000.00$750,000.00 $750,000.00 $524,381.00$707,000.00
 IMPLEMENTATION OF THE SOIL MANAGEMENT PLAN 0.05 1LS$264,000.00$15,000.00 $15,000.00 $70,018.67$50,000.00
 IMPLEMENTATION OF THE DEWATERING PLAN 3.96 1LS$1,500,000.00$1,275,000.00 $1,275,000.00 $1,378,787.00$1,275,000.00
 NPDES MONITORING AND REPORTING 0.17 12MTH$3,200.00$4,500.00 $54,000.00 $11,347.33$10,000.00
 NUMBER OF WORKING DAYS (ADDITIVE ALTERNATIVE NO. 1) 0.09 1WD$0.01$30,000.00 $30,000.00 $620,000.00$30,000.00
 NUMBER OF WORKING DAYS (BASE ITEMS) 23.22 1WD$0.01$7,470,000.00 $7,470,000.00 $8,380,000.00$7,950,000.00
 MAINTENANCE AND REMOVAL OF TEMPORARY SOUND BARRIER 0.02 1LS$5,000.00$5,000.00 $5,000.00 $18,963.33$10,000.00
 PREPARATION OF THE NOISE MITIGATION PLAN (STIPULATED UNIT PRICE OF $5,000)  0.02 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
 PREPARATION OF THE DEWATERING PLAN (STIPULATED UNIT PRICE OF $5,000) 0.02 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
 PREPARATION OF AIR MONITORING PLAN (RULE 1466) (STIPULATED UNIT PRICE OF $5000) 0.02 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
 OUTLET STRUCTURE 0.39 2EA$70,000.00$62,000.00 $124,000.00 $138,663.33$85,000.00
 OUTLET STRUCTURE 0.28 1EA$70,000.00$90,000.00 $90,000.00 $138,663.33$85,000.00
 OUTLET STRUCTURE (DRAIN 2 & 3) 0.39 1EA$90,000.00$125,000.00 $125,000.00 $178,608.33$125,000.00
 RECONSTRUCT PAVED HAUL ROUTE 0.78 1LS$320,000.00$250,000.00 $250,000.00 $220,201.67$220,000.00
 PRESSURE MANHOLE SHAFT PER STD PLAN 329 0.02 1EA$12,000.00$5,000.00 $5,000.00 $22,522.00$7,000.00
 PREPARATION OF THE SURFACE WATER DIVERSION PLAN (STIPULATED UNIT PRICE OF $5,000) 0.02 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
 PREPARATION OF THE SOIL MANAGEMENT PLAN (STIPULATED UNIT PRICE OF $5,000) 0.02 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
 SHORING OF OPEN EXCAVATIONS 0.02 5050LF$85.00$1.00 $5,050.00 $60.67$20.00
 RIP RAP AT BOAT LAUNCH 0.02 195SF$26.00$25.00 $4,875.00 $51.33$25.00
 REMOVE EXISTING STONE WALL 0.47 1LS$275,000.00$150,000.00 $150,000.00 $282,043.67$346,131.00
 TRANSPORTATION OF SEDIMENT FROM BALDWIN LAKE (CLASS III LANDFILL) 6.54 38260TON$82.00$55.00 $2,104,300.00 $54.50$52.00
 TRANSPORTATION OF SEDIMENT FROM BALDWIN LAKE (CLASS III LANDFILL) 6.59 31185TON$82.00$68.00 $2,120,580.00 $54.50$52.00
 TRANSPORTATION OF SEDIMENT FROM TULE POND (CALIFORNIA HAZARDOUS WASTE) 2.99 8755TON$93.00$110.00 $963,050.00 $97.67$100.00
 TEMPORARY HAUL ROUTE 0.54 1LS$45,000.00$175,000.00 $175,000.00 $185,504.33$175,000.00
 TEMPORARY CONSTRUCTION FENCING 1.55 1LS$75,388.00$500,000.00 $500,000.00 $472,251.33$500,000.00
 WATER TRUCK 0.42 100DAY$1,200.00$1,350.00 $135,000.00 $1,337.33$1,350.00
 ULTRASONIC ALGAE CONTROL TRANSDUCER 0.62 1LS$88,000.00$200,000.00 $200,000.00 $134,389.00$103,167.00
 TREE PROTECTION FENCING 0.23 1LS$15,000.00$75,000.00 $75,000.00 $181,250.00$218,750.00
 TREE RELOCATION 0.14 18EA$1,000.00$2,500.00 $45,000.00 $9,080.33$3,500.00
 AIR MONITORING (RULE 1466) 0.19 240DAYS$2,000.00$250.00 $60,000.00 $809.00$250.00
 AGRONOMIC SOIL REPORT 0 1LS$2,500.00$275.00 $275.00 $6,122.67$4,433.00
 AGRONOMIC SOIL REPORT 0 1LS$2,500.00$500.00 $500.00 $6,122.67$4,433.00
 AGGREGATE SURFACING COBBLE - TYPE 1 0.06 8011SF$2.00$2.50 $20,027.50 $4.50$5.00
 AGGREGATE SURFACING COBBLE - TYPE 2 0.08 8097SF$2.50$3.00 $24,291.00 $5.33$6.00
 AGGREGATE SURFACING COBBLE - TYPE 3 0.02 1LS$15,000.00$8,000.00 $8,000.00 $19,622.00$21,000.00
 ABANDON EXISTING 18" CMP 0.01 1LS$12,000.00$2,000.00 $2,000.00 $22,170.33$29,511.00
 ABANDON EXISTING 18" RCP 0.02 1LS$6,000.00$6,000.00 $6,000.00 $23,054.00$20,000.00
 ABANDON EXISTING 48" RCP 0.01 1LS$8,000.00$4,000.00 $4,000.00 $19,774.67$16,000.00
 6" PERFORATED PVC PIPE (INC. FILTER MATERIAL AND FILTER FABRIC) 0.30 1950LF$50.00$50.00 $97,500.00 $56.67$50.00
 CLASS "A" TOPSOIL 0.02 34CY$69.00$150.00 $5,100.00 $330.00$400.00
 BOULDER FOR LAKE WALL TOP (COPING) 0.81 1869SF$40.00$140.00 $261,660.00 $171.67$140.00
 BENCH TYPE 1 0.22 3EA$12,420.00$24,000.00 $72,000.00 $19,912.67$24,000.00
 BENTONITE CLAY LINER 0.02 9TON$560.00$850.00 $7,650.00 $1,424.67$1,550.00
 BENTONITE CLAY LINER 1.27 453TON$560.00$905.00 $409,965.00 $1,424.67$1,550.00
 CONSTRUCTION OF TEMPORARY SOUND BARRIER 0.09 250LF$150.00$115.00 $28,750.00 $326.33$250.00
 CONNECTOR PIPE SCREEN (CPS) 0.02 1EA$3,000.00$5,000.00 $5,000.00 $6,143.67$5,000.00
 CONCRETED RIPRAP (CLASS IV) 0.21 204CY$500.00$325.00 $66,300.00 $757.67$600.00
 CONCRETE CURB AT DECORATIVE CUSTOM GUARDRAIL 0.02 94LF$25.00$80.00 $7,520.00 $203.33$255.00
 COBBLE FOR FLAT COBBLE CURB AT BOAT LAUNCH (CLADDING) 0.05 152SF$40.00$105.00 $15,960.00 $157.67$105.00
 COBBLE FOR FLAT COBBLE CURB AT BOAT LAUNCH (COPING) 0.05 152SF$40.00$105.00 $15,960.00 $131.00$105.00
 COBBLE FOR LAKE WALL HORIZONTAL TOP (COPING) 0.07 158SF$40.00$138.00 $21,804.00 $186.33$138.00
 COBBLE FOR LAKE WALL VERTICAL FACE (CLADDING) 2.61 8410SF$40.00$100.00 $841,000.00 $160.33$100.00
 COBBLE FOR SLOPED SHOTCRETE SHELF (EMBEDDED CLADDING) 0.13 4110SF$20.00$10.00 $41,100.00 $91.67$20.00
 Total Percent100   Total Amount$32,172,345.00