Bid Price History

Eaton Wash Dam and Reservoir Post Fire Cleanout - 2026
$9,991,675.00
06/15/2026
(-)
6
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.03 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.003CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.01 2MTH$500.00$500.00 $1,000.00 $500.00$500.00
001.06.007CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.01 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.16 1LS$134,000.00$16,000.00 $16,000.00 $14,666.67$11,000.00
001.07.003IMPLEMENTATION OF BMPS 0.30 1LS$20,000.00$30,000.00 $30,000.00 $75,758.33$67,500.00
001.08.005OFFICE FACILITIES 0.75 3MTH$6,700.00$25,000.00 $75,000.00 $16,741.67$17,500.00
001.09.003MOBILIZATION 4.10 1LS$300,000.00$410,000.00 $410,000.00 $1,023,666.67$1,030,000.00
300.01.003CLEARING AND GRUBBING 0.75 1LS$62,000.00$75,000.00 $75,000.00 $95,333.33$67,500.00
300.13.003PORTABLE SCALES 0.75 1LS$209,000.00$75,000.00 $75,000.00 $126,666.67$137,500.00
601.09.011TRAFFIC CONTROL 0.75 1LS$220,000.00$75,000.00 $75,000.00 $123,916.67$112,500.00
 SEDIMENT DISPOSAL FEE (ALLOWANCE OF $2,000,000) 20.02 2000000AL$1.00$1.00 $2,000,000.00 $1.00$1.00
 STABILIZED ACCESS RAMP (ALLOWANCE OF $50,000) 0.50 50000AL$1.00$1.00 $50,000.00 $1.00$1.00
 TRANSPORTATION OF ORGANICS (SCHOLL CANYON) 3 16000TON$33.00$18.75 $300,000.00 $24.79$22.50
 TRANSPORTATION OF ORGANICS (SUNSHINE CANYON) 3.88 16000TON$40.00$24.25 $388,000.00 $31.38$32.13
 TRANSPORTATION OF SEDIMENT (SHELDON PIT) 14.05 104000TON$13.00$13.50 $1,404,000.00 $16.53$16.10
 TRANSPORTATION OF SEDIMENT (UNITED ROCK) 10.10 104000TON$12.00$9.70 $1,008,800.00 $13.18$12.35
 TWO STREET SWEEPERS 2.64 55DAYS$4,000.00$4,800.00 $264,000.00 $5,083.33$5,000.00
 PREPARATION OF THE SPILL PREVENTION AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) 0.03 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 PREPARATION OF THE FIRE PREVENTION PLAN (STIPULATED UNIT PRICE OF $2,500) 0.03 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 PREPARATION OF THE RESERVOIR DEWATERING PLAN (STIPULATED UNIT PRICE OF $2,500) 0.03 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 ORGANICS DISPOSAL FEE (ALLOWANCE OF $2,300,000) 23.02 2300000AL$1.00$1.00 $2,300,000.00 $1.00$1.00
 MAINTENANCE OF TIRE WASH 0.90 3MTH$10,000.00$30,000.00 $90,000.00 $35,000.00$22,500.00
 IMPLEMENTATION OF THE RESERVOIR DEWATERING PLAN 0.75 1LS$50,000.00$75,000.00 $75,000.00 $450,833.33$150,000.00
 INSTALLATION OF TIRE WASH 1.30 2EA$70,000.00$65,000.00 $130,000.00 $67,666.67$57,500.00
 EXCAVATION, PROCESSING, AND LOADING 10.21 240000TON$32.00$4.25 $1,020,000.00 $7.88$8.50
 DRONE SURVEY 0.22 22000AL$1.00$1.00 $22,000.00 $1.00$1.00
 CONTROL OF FUGITIVE DUST 0.30 55DAYS$1,400.00$550.00 $30,250.00 $2,991.67$3,250.00
 TWO WATER TRUCKS 1.42 55DAYS$2,400.00$2,575.00 $141,625.00 $4,129.17$4,350.00
 Total Percent100   Total Amount$9,991,675.00