Bid Price History

Las Flores Mesa Water Main Improvements
$3,691,251.50
08/25/2026
629 (G6)
5
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.07 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.003CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.11 8MTH$500.00$500.00 $4,000.00 $500.00$500.00
001.06.007CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.03 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.08 1LS$10,000.00$2,892.00 $2,892.00 $76,060.40$30,000.00
001.07.003IMPLEMENTATION OF BMPS 0.29 1LS$10,000.00$10,607.00 $10,607.00 $32,972.60$35,000.00
001.07.021SHORING OF OPEN EXCAVATIONS 0.87 1LS$125,000.00$32,164.00 $32,164.00 $70,402.80$80,000.00
001.07.043PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) 0.08 1LS$3,000.00$3,000.00 $3,000.00 $3,000.00$3,000.00
001.07.045IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN 0.04 1LS$20,000.00$1,446.00 $1,446.00 $14,739.20$14,600.00
001.08.005OFFICE FACILITIES 1.20 9MTH$8,500.00$4,932.00 $44,388.00 $11,151.40$7,000.00
001.09.003MOBILIZATION 5.11 1LS$200,000.00$188,660.00 $188,660.00 $329,232.00$375,000.00
300.01.003CLEARING AND GRUBBING 0.23 1LS$800.00$8,585.00 $8,585.00 $63,907.00$50,000.00
300.01.014TREE REMOVAL (13"-24" DIAMETER) 0.13 1EA$5,200.00$4,660.00 $4,660.00 $6,057.00$4,900.00
300.01.015TREE REMOVAL (25"+ DIAMETER) 0.13 1EA$7,600.00$4,660.00 $4,660.00 $8,653.00$7,000.00
300.01.065CONCRETE REMOVAL (NON-REINFORCED) 0.03 1CY$1,720.00$1,065.00 $1,065.00 $2,193.00$2,500.00
300.01.067CONCRETE REMOVAL (REINFORCED) 0.15 2CY$2,000.00$2,706.00 $5,412.00 $2,619.20$2,706.00
300.02.003UNCLASSIFIED EXCAVATION 0.32 35CY$495.00$335.00 $11,725.00 $708.00$335.00
301.02.005CRUSHED MISCELLANEOUS BASE 0.17 5CY$1,040.00$1,258.00 $6,290.00 $883.40$500.00
302.05.013AC PAVEMENT 0.07 1TON$4,230.00$2,745.00 $2,745.00 $3,121.00$2,745.00
302.06.003PCC PAVEMENT 0.43 5CY$2,775.00$3,206.00 $16,030.00 $2,170.80$2,500.00
303.01.003STRUCTURE CONCRETE 0.10 2CY$5,000.00$1,927.00 $3,854.00 $4,839.40$3,500.00
303.01.041BAR REINFORCING STEEL 0.13 1158LB$12.00$4.25 $4,921.50 $8.33$4.40
303.01.613CONCRETE SLOUGH WALL 0.12 1CY$5,000.00$4,330.00 $4,330.00 $7,321.00$4,330.00
303.01.617MASONRY RETAINING WALL PER STD PLAN 618 0.98 287SF$200.00$125.50 $36,018.50 $130.90$125.00
303.01.618PCC FOOTING FOR MASONRY RETAINING WALL 0.87 8CY$1,200.00$4,023.00 $32,184.00 $3,163.60$3,500.00
303.05.005PCC CURB, TYPE A1-VAR 0.12 9LF$100.00$486.00 $4,374.00 $378.00$400.00
304.02.007METAL HAND RAILINGS PER STD PLAN 606 0.30 37LF$450.00$299.00 $11,063.00 $362.80$299.00
306.01.141IMPORTED TRENCH BACKFILL 0.10 10CY$39.00$355.00 $3,550.00 $439.00$400.00
306.01.213ABANDON WATERMAIN 2.87 1LS$25,000.00$105,855.00 $105,855.00 $56,471.00$50,000.00
306.01.221AIR RELEASE AND VACUUM VALVE ASSEMBLY, 2" 0.72 1EA$11,500.00$26,582.00 $26,582.00 $17,126.40$14,750.00
306.01.221AIR RELEASE AND VACUUM VALVE ASSEMBLY, 1" 0.42 1EA$6,500.00$15,635.00 $15,635.00 $11,487.00$14,500.00
306.01.227GATE VALVE, 150 PSI WWP, 8" 0.52 7EA$4,000.00$2,716.00 $19,012.00 $5,543.20$5,000.00
500.00.015VIDEO INSPECTION 0.03 1LS$10,000.00$1,056.00 $1,056.00 $14,292.20$8,000.00
601.09.011TRAFFIC CONTROL 4.47 1LS$170,000.00$165,000.00 $165,000.00 $151,865.00$135,000.00
 SCE 4-INCH PVC SCHD 80 CONDUIT WITH FITTINGS AND SUPPORTS 0.08 15LF$110.00$202.00 $3,030.00 $200.40$200.00
 SHORT-CIRCUIT, COORDINATION, AND ARC-FLASH STUDY 0.47 1LS$5,000.00$17,528.00 $17,528.00 $24,615.60$15,000.00
 SOUTHERN CALIFORNIA EDISON (ALLOWANCE $15,000) 0.41 15000AL$1.00$1.00 $15,000.00 $1.00$1.00
 TEMPORARY SUPPLY LINE 1.43 1LS$35,000.00$52,620.00 $52,620.00 $76,064.00$52,620.00
 TECHNICAL WORKSHOPS 0.40 1LS$8,000.00$14,645.00 $14,645.00 $10,052.00$8,000.00
 TESTING, DOCUMENTATION AND COMMISSIONING 0.45 1LS$18,000.00$16,455.00 $16,455.00 $12,230.00$16,455.00
 UNCLASSIFIED EXCAVATION (TRENCH) 0.28 15CY$240.00$699.00 $10,485.00 $790.40$699.00
 1-INCH PVC COATED RMC WITH FITTINGS AND SUPPORTS 0.09 50LF$135.00$64.00 $3,200.00 $193.20$250.00
 1-INCH PVC SCHD 80 CONDUIT WITH FITTINGS AND SUPPORTS 0.02 20LF$90.00$32.25 $645.00 $112.25$50.00
 3-INCH PVC COATED RMC WITH FITTINGS AND SUPPORTS 0.22 50LF$150.00$160.00 $8,000.00 $369.20$351.00
 3-INCH PVC SCHD 80 CONDUIT WITH FITTINGS AND SUPPORTS 0.06 20LF$100.00$108.25 $2,165.00 $163.65$108.25
 8" WATERMAIN, HAZARD RESILIENT DUCTILE IRON PIPE, CLASS 52 37.73 3147LF$450.00$442.50 $1,392,547.50 $591.50$575.00
 AUTOMATIC TRANSFER SWITCH WITH QUICK-CONNECT PANEL 1.38 1LS$50,000.00$50,972.00 $50,972.00 $63,504.40$60,000.00
 BLOCK WALL REMOVAL - (PORTION) 0.04 4LF$400.00$360.00 $1,440.00 $941.60$998.00
 CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $2,000) 0.05 2000AL$1.00$1.00 $2,000.00 $1.00$1.00
 DISPOSAL OF LEAD CONTAINING PAINT WASTE 0.45 1LS$10,000.00$16,645.00 $16,645.00 $17,134.00$16,645.00
 ELECTRICAL DEMOLITION 0.75 1LS$15,000.00$27,510.00 $27,510.00 $24,507.00$25,000.00
 DRILL AND BOND ANCHOR (EPOXY CARTRIDGE) 0.12 37LF$250.00$124.00 $4,588.00 $235.00$300.00
 FINAL TESTING 0.32 1LS$15,000.00$11,927.00 $11,927.00 $7,768.00$10,000.00
 FIRE HYDRANT ASSEMBLY PER DETAIL 1 ON SHT 7 2.04 2EA$25,000.00$37,590.00 $75,180.00 $29,678.00$37,590.00
 FIRE HYDRANT ASSEMBLY PER DETAIL 1 ON SHT 7 W/ BARRICADES 1.12 1EA$27,000.00$41,365.00 $41,365.00 $35,973.00$40,000.00
 FURNISH AND INSTALL LEAK DETECTION SYSTEM (ALLOWANCE OF $75,000) 2.03 75000AL$1.00$1.00 $75,000.00 $1.00$1.00
 FLEXIBLE EXPANSION JOINT, DOUBLE BALL, 8" 0.55 2EA$20,000.00$10,147.00 $20,294.00 $12,489.40$12,500.00
 FIRE HYDRANT ASSEMBLY PER DETAIL 3 ON SHT 6 4 4EA$23,000.00$36,890.00 $147,560.00 $27,228.00$30,000.00
 GROUND WELL 0.03 1EA$2,000.00$1,198.00 $1,198.00 $4,345.60$1,198.00
 GROUND ROD COPPER-CLAS (3/4 DIAMETER BY 10) 0.03 2EA$750.00$573.00 $1,146.00 $1,623.00$573.00
 TRENCH BACKFILL SAND 0.10 5CY$25.00$745.00 $3,725.00 $479.80$415.00
 INTERCONNECTION TO EXISTING WATER TANK 0.82 1EA$30,000.00$30,105.00 $30,105.00 $28,021.00$30,105.00
 INTERCONNECTION TO EXISTING WATERMAIN 0.93 3EA$20,000.00$11,430.00 $34,290.00 $14,951.00$15,000.00
 INITIAL VIDEO INSPECTION 0.03 1LS$10,000.00$1,056.00 $1,056.00 $9,612.20$8,000.00
 METERED MAIN SWITCHBOARD 1.92 1LS$125,000.00$70,700.00 $70,700.00 $122,400.00$135,000.00
 LIGHTING WITH WIRE/CONDUIT 0.23 1LS$2,000.00$8,408.00 $8,408.00 $11,189.60$12,000.00
 MISCELLANEOUS METAL 0.15 64LB$80.00$89.00 $5,696.00 $146.20$64.00
 MISCELLANEOUS ELECTRICAL WORK 1.39 1LS$20,000.00$51,215.00 $51,215.00 $33,626.00$35,000.00
 NO. 250 KCMIL CONDUCTOR 0.61 1120LF$40.00$20.00 $22,400.00 $21.40$20.00
 NO. 4 AWG CONDUCTOR 0.06 380LF$25.00$5.50 $2,090.00 $57.50$10.00
 MOTOR CONTROL CENTER 9.30 1LS$125,000.00$343,132.00 $343,132.00 $291,326.40$323,000.00
 NO. 6 AWG CONDUCTOR 0.02 150LF$25.00$5.25 $787.50 $47.65$10.00
 OPERATION AND MAINTENANCE MANUALS 0.22 1LS$8,000.00$8,172.00 $8,172.00 $4,897.00$5,000.00
 PCC GUTTER 0.08 6LF$80.00$514.00 $3,084.00 $455.00$500.00
 PREPARE AS-BUILT DRAWINGS 0.22 1LS$8,000.00$7,965.00 $7,965.00 $4,475.00$3,510.00
 RECONNECT EXISTING WATER SERVICE 3.41 20EA$4,500.00$6,285.00 $125,700.00 $6,297.00$6,285.00
 RECONNECT EXISTING SAMPLING STATION 0.29 1EA$15,000.00$10,840.00 $10,840.00 $7,478.00$7,000.00
 REMOVE AND DISPOSE EXISTING ABOVE GROUND WATER MAIN 2 2926LF$15.00$25.25 $73,881.50 $27.45$25.25
 REMOVE EXISTING WOOD FENCE 0.04 9LF$60.00$160.00 $1,440.00 $203.00$200.00
 SCADA/PLC SYSTEM AND ANTENNA WITH CABLES AND CONDUCTORS 2.39 1LS$50,000.00$88,155.00 $88,155.00 $135,939.00$150,000.00
 Total Percent100   Total Amount$3,691,251.50