Bid Price History

Lower Encinal Pump Station Improvements
$2,914,500.00
09/09/2025
(-)
10
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.002CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) 0.09 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.14 8MTH$500.00$500.00 $4,000.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $2,000) 0.07 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.86 1LS$10,000.00$25,000.00 $25,000.00 $23,259.50$20,000.00
001.07.003IMPLEMENTATION OF BMPS 0.86 1LS$30,000.00$25,000.00 $25,000.00 $32,411.30$25,941.50
001.07.023PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) 0.10 1LS$3,000.00$3,000.00 $3,000.00 $3,000.00$3,000.00
001.07.025IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 0.86 1LS$15,000.00$25,000.00 $25,000.00 $14,636.10$12,680.50
001.07.037REMOVAL AND DISPOSAL OF LBP/LCP 0.86 1LS$10,000.00$25,000.00 $25,000.00 $34,911.40$27,000.00
001.07.043PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) 0.10 1LS$3,000.00$3,000.00 $3,000.00 $3,000.00$3,000.00
001.07.045IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN 0.86 1LS$20,000.00$25,000.00 $25,000.00 $27,938.40$17,530.50
001.07.047PREPARATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $3000) 0.10 1LS$3,000.00$3,000.00 $3,000.00 $3,000.00$3,000.00
001.07.049IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN 0.86 1LS$10,000.00$25,000.00 $25,000.00 $31,046.40$20,030.50
001.07.051REMOVAL AND DISPOSAL OF NON-HAZARDOUS ASBESTOS WASTE 0.86 1LS$10,000.00$25,000.00 $25,000.00 $17,419.40$16,280.50
001.08.005OFFICE FACILITIES 3.09 9MTH$5,500.00$10,000.00 $90,000.00 $5,187.20$5,150.00
001.09.003MOBILIZATION 3.43 1LS$150,000.00$100,000.00 $100,000.00 $198,508.40$157,000.00
304.03.003CHAIN LINK FENCE, 8' HIGH 0.96 56LF$250.00$500.00 $28,000.00 $493.50$500.00
601.09.011TRAFFIC CONTROL 1.20 1LS$5,000.00$35,000.00 $35,000.00 $16,404.20$12,500.00
 TEMPORARY BYPASS 1.72 1LS$50,000.00$50,000.00 $50,000.00 $72,478.40$62,500.00
 RESIDENTIAL STREET REPAIR (ALLOWANCE OF $50,000) 1.72 50000AL$1.00$1.00 $50,000.00 $1.00$1.00
 REMOVE AND DISPOSE OF EXISTING CHAIN LINK FENCE AND GATES 0.34 1LS$4,000.00$10,000.00 $10,000.00 $9,158.70$9,000.00
 REINFORCED CONCRETE PAD 3.40 18CY$2,000.00$5,500.00 $99,000.00 $2,929.70$2,744.00
 PUMP STATION BUILDING & ASSOCIATED COMPONENTS 17.16 1LS$600,000.00$500,000.00 $500,000.00 $639,032.60$525,000.00
 PERMIT AND INSPECTION FEE (ALLOWANCE OF $5,000) 0.17 5000AL$1.00$1.00 $5,000.00 $1.00$1.00
 PORTABLE GENERATOR 3.43 1LS$150,000.00$100,000.00 $100,000.00 $142,455.40$140,567.50
 MECHANICAL PIPING & ASSOCIATED APPURTENANCES 27.45 1LS$380,000.00$800,000.00 $800,000.00 $887,722.20$870,000.00
 INSTALL TEMPORARY 5000 GALLON POTABLE WATER STORAGE TANK 0.86 1LS$10,000.00$25,000.00 $25,000.00 $19,430.20$19,500.00
 INITIAL VIDEO INSPECTION 0.34 1LS$15,000.00$10,000.00 $10,000.00 $8,734.00$5,000.00
 FINAL VIDEO INSPECTION 0.34 1LS$15,000.00$10,000.00 $10,000.00 $8,634.00$6,250.00
 ELECTRICAL EQUIPMENT & ASSOCIATED COMPONENTS 15.44 1LS$560,000.00$450,000.00 $450,000.00 $675,301.80$626,173.50
 EXISTING PUMP STATION BUILDING & SITE DEMOLITION AND REMOVAL 6.86 1LS$100,000.00$200,000.00 $200,000.00 $190,905.40$85,000.00
 DESIGN OF SHORING FOR OPEN EXCAVATIONS 1.20 1LS$10,000.00$35,000.00 $35,000.00 $19,604.20$10,000.00
 CHAIN LINK GATE 0.86 1EA$6,000.00$25,000.00 $25,000.00 $17,618.10$20,000.00
 MECHANICAL IMPROVEMENTS 3.43 1LS$250,000.00$100,000.00 $100,000.00 $267,831.00$80,000.00
 Total Percent100   Total Amount$2,914,500.00