Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) 0.04 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.07 17MTH$500.00$500.00 $8,500.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.01 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.07.004PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) 0.04 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
001.07.007IMPLEMENTATION OF THE SWPPP 0.17 1LS$60,000.00$20,000.00 $20,000.00 $162,833.33$173,500.00
001.08.005OFFICE FACILITIES 0.37 17MTH$4,000.00$2,500.00 $42,500.00 $3,071.67$2,750.00
001.09.003MOBILIZATION 7.13 1LS$600,000.00$825,433.75 $825,433.75 $1,213,670.24$1,104,931.33
 P-151 STUMP REMOVAL (12"-21") DIAMETER 0.01 3EA$400.00$400.00 $1,200.00 $448.33$450.00
 P-151 STUMP REMOVAL(22"-30") DIAMETER 0.03 7EA$600.00$500.00 $3,500.00 $649.17$675.00
 P-101 CONCRETE WHEEL STOP REMOVAL 0 2EA$100.00$155.00 $310.00 $485.83$425.00
 P-101 DOOR STOP REMOVE AND REPLACE 0 2EA$1,500.00$125.00 $250.00 $795.83$775.00
 P-608 FUEL RESISTANT SEALCOAT 0.66 16930SY$5.00$4.50 $76,185.00 $4.41$4.90
 P-610 0" CONCRETE CURB 0.06 146LF$18.00$47.00 $6,862.00 $39.00$39.00
 P-152 SCARIFY AND RECOMPACT EXISTING BASE 0.15 1259SY$10.00$13.50 $16,996.50 $8.52$8.50
 P-152 SUBGRADE PREPARATION 2.26 174377SY$3.00$1.50 $261,565.50 $1.30$1.45
 P-152 UNCLASSIFIED EXCAVATION & EXPORT 7.90 30500CY$30.00$30.00 $915,000.00 $36.82$37.05
 P-152 UNCLASSIFIED FILL 0.16 1083CY$15.00$17.00 $18,411.00 $12.80$13.15
 P-155 CBR TESTING OF SOIL-LIME MIXTURE 0.80 15EA$1,250.00$6,200.00 $93,000.00 $3,105.00$2,525.00
 P-155 HYDRATED LIME (EQUIVALENT) 12.88 7458TON$244.00$200.00 $1,491,600.00 $213.47$215.40
 P-155 LIME-TREATED SUBGRADE (12" THICK) 7.90 174377SY$5.25$5.25 $915,479.25 $3.99$4.13
 P-208 AGGREGATE BASE COURSE 12.95 22391CY$65.00$67.00 $1,500,197.00 $80.33$76.50
 P-610 TIE-DOWN ANCHOR IN AC PAVEMENT 1.95 501EA$330.00$450.00 $225,450.00 $441.50$367.50
 P-620 REFLECTIVE MEDIA 0.05 1467LB$3.00$4.00 $5,868.00 $4.15$4.00
 P-620 BLACK MARKING (1 COAT) 0.15 35760SF$1.00$0.50 $17,880.00 $0.53$0.50
 P-403 ASPHALT MIX PAVEMENT SURFACE COURS 17.85 26842TON$100.00$77.00 $2,066,834.00 $99.83$99.50
 P-501 6" CONCRETE PAVEMENT 2.07 3582SY$80.00$67.00 $239,994.00 $81.92$81.85
 P-501 7" CONCRETE PAVEMENT 1.57 2145SY$90.00$85.00 $182,325.00 $91.67$93.50
 P-602 EMULSIFIED ASPHALT PRIME COAT 1.40 49862GAL$2.60$3.25 $162,051.50 $4.03$4.08
 P-605 JOINT SEALING FILLER 0.54 5924LF$5.00$10.50 $62,202.00 $10.43$10.65
 P-608 ASPHALT SURFACE TREATMENT 0.12 3154SY$5.00$4.50 $14,193.00 $6.34$6.25
 P-620 WHITE MARKING ( 2 COATS) 0.01 311SF$5.00$4.00 $1,244.00 $3.05$3.13
 P-620 YELLOW MARKING (1 COAT) 0.01 490SF$1.25$2.00 $980.00 $1.16$1.00
 P-620 YELLOW MARKING (2 COATS) 0.29 16555SF$2.50$2.00 $33,110.00 $1.93$2.00
 P-610 6" PCC GATE TRACK 0.05 48SF$15.00$110.00 $5,280.00 $54.67$35.00
 P-610 VARIABLE HEIGHT CURB AT HANGAR 0.14 108LF$25.00$145.00 $15,660.00 $298.33$44.50
 P-610 3" CONCRETE CURB 0.06 107LF$20.00$60.00 $6,420.00 $709.17$47.50
 P-610 4" CONCRETE PAVEMENT 0.12 1236SF$10.00$11.00 $13,596.00 $12.13$11.25
 P-610 6" CONCRETE CURB 0.13 467LF$22.00$33.00 $15,411.00 $37.00$37.00
 P-610 CONCRETE CURB AND GUTTER 0.28 461LF$30.00$70.00 $32,270.00 $51.83$48.50
 P-610 CONCRETE WALL WITH GUTTER 0.67 470LF$60.00$165.00 $77,550.00 $257.83$207.50
 P-610 TIE DOWN ANCHOR IN PCC PAVEMENT 0.13 48EA$25.00$310.00 $14,880.00 $385.17$355.00
 P-620 GRIND PAVEMENT FOR MARKINGS REMOVAL 0.06 3000SF$4.00$2.50 $7,500.00 $2.63$2.50
 P-620 HEAL THE BAY MARKING (1 COAT) 0.02 10EA$75.00$225.00 $2,250.00 $207.67$222.50
 PREPARATION OF SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $2,500) 0.02 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 PREPARATION OF SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $2,500) 0.02 1LS$2,500.00$2,500.00 $2,500.00 $2,500.00$2,500.00
 S-100 LOW PROFILE BARRICADES PHASE 3 0.19 1284LF$25.00$17.00 $21,828.00 $11.48$10.00
 S-100 LOW PROFILE BARRICADES PHASE 1 0.21 1426LF$25.00$17.00 $24,242.00 $16.42$16.00
 S-100 LOW PROFILE BARRICADES PHASE 2 0.23 1544LF$25.00$17.00 $26,248.00 $11.46$10.50
 U-100 PAY FRONTIER COMMUNICATIONS INVOICE (ALLOWANCE) 0.17 20000AL$1.00$1.00 $20,000.00 $1.00$1.00
 U-100 PAY SCE INVOICE (ALLOWANCE) 0.65 75500AL$1.00$1.00 $75,500.00 $1.00$1.00
 U-100 RELOCATE FRONTIER FACILITIES 0.27 1LS$27,000.00$31,000.00 $31,000.00 $30,008.33$28,525.00
 U-100 RELOCATE SCE FACILITIES 0.86 1LS$93,000.00$100,000.00 $100,000.00 $85,438.33$92,500.00
 W-900 POTHOLE WATER MAIN 0.04 2EA$3,500.00$2,400.00 $4,800.00 $2,761.67$2,200.00
 W-900 RELOCATE WATER MAIN (8" DIAMETER) 0.28 250LF$125.00$130.00 $32,500.00 $151.33$145.00
 W-900 TAPPING VALVES 0.09 2EA$5,000.00$5,400.00 $10,800.00 $4,358.33$4,500.00
 W-900 ABANDON WATER MAIN (8" DIAMETER) 0.02 240LF$28.00$11.00 $2,640.00 $21.83$20.00
 D-701 12" HDPE PIPE 0.21 244LF$50.00$100.00 $24,400.00 $97.00$100.00
 D-701 12" RCP 2500D 1.13 1050LF$80.00$125.00 $131,250.00 $130.33$122.50
 D-701 18" RCP, 2500D 0.28 295LF$100.00$110.00 $32,450.00 $113.17$110.00
 D-702 12" CSP SLOTTED DRAIN 0.14 70LF$225.00$225.00 $15,750.00 $241.33$232.50
 D-751 CONNECT TO EXISTING INLET PER SPPWC 335 0.04 1EA$3,000.00$4,400.00 $4,400.00 $3,048.50$2,945.50
 D-751 INLET SPPWC 304 DOUBLE GRATE WITH APRON 0.26 3EA$12,000.00$10,000.00 $30,000.00 $11,171.67$11,500.00
 D-751 INLET SPPWC 304 SINGLE GRATE NO APRON 0.11 2EA$7,500.00$6,500.00 $13,000.00 $6,781.83$6,845.50
 D-751 INLET SPPWC 304 SINGLE GRATE WITH APRON 0.33 5EA$10,000.00$7,700.00 $38,500.00 $8,410.83$8,850.00
 D-751 JUNCTION STRUCTURE SPPWC 304 NO APRON 0.05 1EA$7,500.00$6,300.00 $6,300.00 $8,081.83$7,595.50
 D-751 JUNCTION STRUCTURE SPPWC 331 0.13 4EA$5,000.00$3,700.00 $14,800.00 $3,043.33$2,980.00
 D-751 PCC APRON 3-FT AROUND EXISTING INLET 0.01 1EA$800.00$1,600.00 $1,600.00 $1,892.67$1,650.00
 D-752 STONE TRENCH 0.02 24CY$100.00$115.00 $2,760.00 $208.00$207.50
 D-752 8" THICK STONE LAYER 0.03 88SY$50.00$36.00 $3,168.00 $57.40$52.20
 D-752 OUTLET STRUCTURE 0.12 1EA$10,000.00$14,200.00 $14,200.00 $14,531.67$14,595.00
 D-754 CONCRETE GUTTER AT SLOTTED DRAIN 0.04 268SF$10.00$16.00 $4,288.00 $16.78$16.00
 D-754 CONCRETE RIBBON GUTTER 1.48 26397SF$12.00$6.50 $171,580.50 $10.23$10.95
 DISPOSAL OF LEAD WASTE/DEBRIS 0.01 1LS$5,000.00$1,600.00 $1,600.00 $2,136.67$1,800.00
 F-162 RESTORE AIRPORT FENCE 0.03 1LS$2,500.00$3,500.00 $3,500.00 $8,989.17$4,750.00
 F-162 TEMPORARY GATE 0.05 1LS$3,500.00$5,250.00 $5,250.00 $5,364.17$5,625.00
 IMPLEMENTATION OF SITE-SPECIFIC HEALTH AND SAFETY PLAN 0.10 1LS$5,000.00$12,000.00 $12,000.00 $4,793.33$3,750.00
 IMPLEMENTATION OF SITE-SPECIFIC LEAD COMPLIANCE PLAN 0.01 1LS$15,000.00$850.00 $850.00 $2,058.33$1,500.00
 P-101 4" X 4" WOOD CURB REMOVAL 0.04 489LF$5.00$9.50 $4,645.50 $11.50$7.50
 P-101 ADJUST DRAIN OUTLET TO GRADE 0.04 1EA$1,200.00$4,100.00 $4,100.00 $2,767.50$3,000.00
 P-101 ADJUST ELECTRICAL PULLBOX TO GRADE 0.14 2EA$2,000.00$7,900.00 $15,800.00 $6,258.33$7,000.00
 P-101 ADJUST FIRE HYDRANT ASSEMBLY TO GRADE 0.02 1EA$3,000.00$2,200.00 $2,200.00 $3,708.33$2,850.00
 P-101 ADJUST MONITORING WELL TO GRADE 0.01 2EA$1,200.00$620.00 $1,240.00 $1,407.50$1,537.50
 P-101 ADJUST SEWER CLEAN-OUT TO GRADE 0.07 9EA$800.00$960.00 $8,640.00 $1,047.50$980.00
 P-101 ADJUST SEWER MANHOLE TO GRADE 0.07 7EA$1,000.00$1,200.00 $8,400.00 $1,439.17$1,400.00
 P-101 ADJUST TAXIWAY LIGHT TO GRADE 0.16 4EA$1,500.00$4,500.00 $18,000.00 $3,870.83$4,000.00
 P-101 ASPHALT CONCRETE PAVEMENT REMOVAL 6.03 174463SY$2.00$4.00 $697,852.00 $3.93$3.75
 P-101 ASPHALT PAVEMENT SAWCUTTING 0.13 7644LF$3.00$2.00 $15,288.00 $3.18$3.13
 P-101 BOLLARD/GUARD POST REMOVAL 0 2EA$250.00$160.00 $320.00 $615.00$335.00
 P-101 CHAIN LINK FENCE REMOVAL COMPLETE 0.06 91LF$15.00$74.00 $6,734.00 $51.25$54.50
 P-101 CONCRETE LIGHT POLE PEDESTAL REMOVAL 0 1EA$1,500.00$500.00 $500.00 $1,185.83$957.50
 P-101 CONCRETE PAVEMENT SAWCUTTING 0 3LF$15.00$20.00 $60.00 $166.71$82.50
 P-101 CONCRETE PAVEMENT/GUTTER/PAD REMOVAL 0.08 74CY$500.00$130.00 $9,620.00 $198.93$204.00
 P-101 CONCRETE REMOVAL 2-1/2 THICK 0.15 1859SY$20.00$9.50 $17,660.50 $11.68$11.50
 P-101 ADJUST CONCRETE PANEL (SEGMENTED CIRCLE) TO GRADE 0.11 8EA$500.00$1,650.00 $13,200.00 $1,513.33$1,550.00
 P-101 4" GUARD POST REMOVE AND REPLACE 0.02 1EA$1,000.00$2,100.00 $2,100.00 $1,700.00$1,850.00
 P-101 DOWNSPOUT CHANNEL REMOVE AND REPLACE 0.02 1EA$100.00$1,800.00 $1,800.00 $1,383.33$1,500.00
 P-101 DUCT MARKER REMOVE AND REPLACE 0.03 2EA$200.00$1,800.00 $3,600.00 $1,480.00$1,500.00
 P-101 ELECTRICAL CABINET REMOVAL COMPLETE 0.03 1LS$1,000.00$3,500.00 $3,500.00 $3,455.83$3,400.00
 P-101 ELECTRICAL CONDUIT REMOVE AND REPLACE 0.07 1LS$1,500.00$8,500.00 $8,500.00 $7,615.83$8,000.00
 P-101 ELECTRICAL HANDHOLE/PULLBOX REMOVE AND REPLACE 0.99 7EA$2,500.00$16,400.00 $114,800.00 $12,473.50$14,000.00
 P-101 FENCE POST FOOTING (ABANDONED) REMOVAL 0.02 1EA$100.00$2,800.00 $2,800.00 $1,325.83$802.50
 P-101 GATE SENSOR LOOPS REMOVE AND REPLACE 0.07 2EA$3,000.00$3,900.00 $7,800.00 $3,234.17$3,550.00
 P-101 GRATED YARD INLET REMOVAL 0.01 1EA$50.00$610.00 $610.00 $1,385.00$1,150.00
 P-101 PCC FOOTING LOWERING BY CHIPPING 0.01 25SF$25.00$65.00 $1,625.00 $125.17$113.00
 P-101 ADJUST WATER MANHOLE TO GRADE 0.04 1EA$2,500.00$4,600.00 $4,600.00 $2,175.00$1,675.00
 P-101 ADJUST WATER VALVE TO GRADE 0.02 8EA$700.00$310.00 $2,480.00 $930.83$850.00
 P-208 GRANULAR SHOULDER 0.35 1618SY$17.00$25.00 $40,450.00 $17.79$21.00
 P-401 ASPHALT SURFACE COURSE 1.30 1809TON$130.00$83.00 $150,147.00 $106.67$106.00
 P-101 SLURRY SEAL REMNANTS ON PCC REMOVAL 0.01 165SF$37.00$10.00 $1,650.00 $18.20$16.60
 P-101 TIE DOWN CABLE REMOVAL 0.31 2238LF$3.00$16.00 $35,808.00 $7.84$3.78
 P-101 TIE-DOWN ANCHOR REMOVAL (1-FT DIAMETER) 0.29 1112EA$40.00$30.00 $33,360.00 $51.67$43.00
 P-101 TIE-DOWN ANCHOR REMOVAL (3-FT DIAMETER) 0.06 37EA$150.00$175.00 $6,475.00 $141.17$140.00
 P-101 WATER METER/VALVE BOX REMOVE AND REPLACE 0.04 5EA$2,500.00$1,030.00 $5,150.00 $1,459.17$1,500.00
 P-151 CLEARING AND GRUBBING 0.29 5557SY$1.00$6.00 $33,342.00 $5.85$6.00
 Total Percent100   Total Amount$11,582,000.00