Hacienda Channel - La Plata Avenue Drain
$2,292,502.00
05/11/2021
678 (A5),678 (A6)
10
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) 0.09 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.13 6MTH$500.00$500.00 $3,000.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.04 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.06.011IMPLEMENTATION OF THE LTWHP 0.22 1LS$10,000.00$5,000.00 $5,000.00 $17,382.40$8,000.00
001.07.003IMPLEMENTATION OF BMPS 0.44 1LS$10,000.00$10,000.00 $10,000.00 $30,836.10$19,555.50
001.07.009RESTORATION OF EXISTING IMPROVEMENTS 1.31 1LS$14,400.00$30,000.00 $30,000.00 $106,700.00$30,000.00
001.07.021SHORING OF OPEN EXCAVATIONS 1.31 1LS$278,560.00$30,000.00 $30,000.00 $198,301.10$110,000.00
001.08.005OFFICE FACILITIES 1.37 7MTH$5,000.00$4,500.00 $31,500.00 $5,418.30$4,300.00
001.09.003MOBILIZATION 4.36 1LS$250,000.00$100,000.00 $100,000.00 $126,529.90$112,500.00
301.03.003TRENCH BACKFILL SLURRY (CLASS 100-E-100) 10.08 1541CY$200.00$150.00 $231,150.00 $176.80$187.50
303.01.309CATCH BASIN PER STD PLAN 300, W=10 0.44 1EA$12,200.00$10,000.00 $10,000.00 $15,717.30$13,750.00
303.01.309CATCH BASIN PER STD PLAN 300, W=7 0.39 1EA$11,400.00$9,000.00 $9,000.00 $12,623.60$10,000.00
306.01.013SUPPORT FOR 8" OR LESS WATERLINE 0.92 7EA$1,000.00$3,000.00 $21,000.00 $4,036.50$2,382.50
306.01.013SUPPORT FOR 15" OR LESS WATERLINE 0.52 4EA$1,500.00$3,000.00 $12,000.00 $4,462.20$2,500.00
306.01.019SUPPORT FOR 8" AND LESS SEWER 0.26 2EA$1,000.00$3,000.00 $6,000.00 $4,266.00$3,255.00
306.01.311REMODEL SEWER HOUSE CONNECTION 0.99 57LF$360.00$400.00 $22,800.00 $507.00$350.00
306.01.319PCC BLANKET PROTECTION FOR SEWER 0.33 15CY$1,000.00$500.00 $7,500.00 $1,053.10$750.00
306.01.38030" CONCRETE COLLAR 0.46 3EA$2,300.00$3,500.00 $10,500.00 $3,175.00$3,000.00
306.01.38018" CONCRETE COLLAR 1.31 15EA$1,600.00$2,000.00 $30,000.00 $1,900.00$2,000.00
306.01.38024" CONCRETE COLLAR 0.31 2EA$2,000.00$3,500.00 $7,000.00 $2,500.00$2,550.00
306.01.503RESTORATION OF PERMANENT SURFACING 8.72 1LS$195,315.00$200,000.00 $200,000.00 $198,277.00$200,000.00
601.09.011TRAFFIC CONTROL 1.31 1LS$110,000.00$30,000.00 $30,000.00 $81,548.00$45,000.00
 MANHOLE PER STD PLAN 322 (MOD) 3.84 8EA$9,000.00$11,000.00 $88,000.00 $11,852.20$10,500.00
 MANHOLE PER STD PLAN 321 (MOD) 1.74 4EA$8,000.00$10,000.00 $40,000.00 $11,730.00$10,000.00
 JUNCTION STRUCTURE PER DETAIL F 1.05 4EA$5,500.00$6,000.00 $24,000.00 $7,420.70$5,500.00
 JUNCTION STRUCTURE PER DETAIL E 2.09 8EA$5,500.00$6,000.00 $48,000.00 $8,481.60$6,750.00
 GROUNDWATER DEWATERING (ALLOWANCE OF $150,000) 6.54 150000AL$1.00$1.00 $150,000.00 $1.00$1.00
 ABANDON EXISTING MANHOLE 0.26 3EA$2,000.00$2,000.00 $6,000.00 $5,400.00$3,250.00
 MANHOLE PER STD PLAN 320 (MOD) 0.39 1EA$8,000.00$9,000.00 $9,000.00 $11,530.90$10,000.00
 24" DUAL WALL POLYPROPYLENE PIPE 0.73 28LF$300.00$600.00 $16,800.00 $625.00$450.00
 30" DUAL WALL POLYPROPYLENE PIPE 23.99 2075LF$340.00$265.00 $549,875.00 $360.20$372.50
 36" DUAL WALL POLYPROPYLENE PIPE 7.23 603LF$450.00$275.00 $165,825.00 $421.60$385.50
 TRANSITION STRUCTURE PER STD PLAN 340 (MOD) 0.79 2EA$8,500.00$9,000.00 $18,000.00 $9,720.20$7,100.00
 18" DUAL WALL POLYPROPYLENE PIPE 0.67 22LF$410.00$700.00 $15,400.00 $611.30$500.00
 48" DUAL WALL POLYPROPYLENE PIPE 15.36 804LF$480.00$438.00 $352,152.00 $509.00$485.00
 Total Percent100   Total Amount$2,292,502.00