Bid Price History

Mulholland Highway and Stokes Canyon Road, et al.
$4,970,000.00
01/30/2018
586 (A7),626 (A1),625 (J3),625 (J2),625 (H6),625 (H5),625 (H4),625 (H3),589 (D5),589 (D4),589 (D3),589 (D2),589 (C5),589 (C4),589 (C3),589 (C2),589 (B5),588 (J4),588 (J3),588 (H4),586 (F7),586 (E7),586 (E6),586 (D7),586 (D6),586 (C7),586 (C6),586 (B7)
4
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) 0.04 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.03 3MTH$500.00$500.00 $1,500.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.02 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.07.004PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) 0.10 1LS$5,000.00$5,000.00 $5,000.00 $5,000.00$5,000.00
001.07.007IMPLEMENTATION OF THE SWPPP 3.27 1LS$15,000.00$162,600.00 $162,600.00 $51,650.00$15,500.00
001.09.003MOBILIZATION 6.38 1LS$150,000.00$317,184.54 $317,184.54 $301,546.14$270,592.27
300.01.003CLEARING AND GRUBBING 0.85 1LS$20,000.00$42,000.00 $42,000.00 $22,150.00$20,000.00
300.01.065CONCRETE REMOVAL (NON-REINFORCED) 0.03 2CY$700.00$850.00 $1,700.00 $1,087.50$600.00
300.02.003UNCLASSIFIED EXCAVATION 2.84 940CY$100.00$150.00 $141,000.00 $163.00$160.00
300.03.005SHOULDER GRADING 0.26 3MI$5,000.00$4,300.00 $12,900.00 $9,300.00$8,450.00
300.05.002IMPORTED BORROW 0.81 505CY$65.00$80.00 $40,400.00 $54.18$55.10
301.02.005CRUSHED MISCELLANEOUS BASE 0.08 46CY$350.00$88.00 $4,048.00 $146.75$126.00
302.01.005COLD MILL AC PAVEMENT (0 - 1-1/2") 0.25 7805SF$1.00$1.60 $12,488.00 $1.81$1.63
302.01.007COLD MILL AC PAVEMENT (> 1-1/2 - 3") 2.04 241863SF$0.25$0.42 $101,582.46 $0.39$0.41
302.05.013AC PAVEMENT 2.14 1066TON$160.00$100.00 $106,600.00 $112.85$103.70
302.05.016AC PAVEMENT(DRIVEWAYS) 0.52 137TON$150.00$187.00 $25,619.00 $241.95$251.00
302.05.017AC PAVEMENT(INVERTED SHOULDERS) 1.54 534TON$200.00$143.00 $76,362.00 $158.85$159.00
302.05.018AC PAVEMENT(DIGOUTS) 0.11 42TON$150.00$135.00 $5,670.00 $183.10$142.50
302.05.025DOUBLE ADJUST MANHOLE 0.27 12EA$1,000.00$1,100.00 $13,200.00 $1,075.00$1,100.00
302.09.003ASPHALT RUBBER HOT MIX 30 14201TON$94.00$105.00 $1,491,105.00 $104.09$103.68
302.09.005ASPHALT RUBBER HOT MIX (TEST STRIP) 1.13 500TON$100.00$112.00 $56,000.00 $123.50$119.00
302.10.003ASPHALT RUBBER AND AGGREGATE MEMBRANE 3.18 26333SY$6.00$6.00 $157,998.00 $5.55$5.50
302.15.003CIR AC PAVEMENT, 3" THICK 18.81 116830SY$5.00$8.00 $934,640.00 $9.55$9.60
302.15.007EMULSIFIED RECYCLING AGENT 9.13 698TON$700.00$650.00 $453,700.00 $610.50$611.00
304.06.003REMOVE AND DISPOSE OF EXISTING GUARDRAIL (INCLUDING POSTS) 0.77 2565LF$10.00$15.00 $38,475.00 $10.82$14.00
304.06.009TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE 0.21 42640LB$0.35$0.25 $10,660.00 $3.02$0.24
304.06.013METAL BEAM GUARD RAILING (STEEL POST W/ PLASTIC BLOCK) 0.52 414LF$50.00$63.00 $26,082.00 $60.08$61.15
304.06.019MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK) 0.76 620LF$50.00$61.00 $37,820.00 $59.34$60.50
304.06.025FLARED TERMINAL SYSTEM (TYPE X-TENSION- W/ STEEL POSTS) 0.42 3EA$4,500.00$7,000.00 $21,000.00 $6,907.50$7,000.00
304.06.033IN-LINE TERMINAL SYSTEM (TYPE X-TENSION - W/ STEEL POST) 7.18 51EA$4,500.00$7,000.00 $357,000.00 $6,871.25$6,850.00
304.06.037IN-LINE TERMINAL SYSTEM (TYPE SKT-SP-MGS) 0.43 4EA$4,500.00$5,300.00 $21,200.00 $5,095.00$5,040.00
304.06.043MIDWEST GUARDRAIL SYSTEM END ANCHOR ASSEMBLY (TYPE SFT) PER STD PLAN A77S1 0.02 1EA$1,000.00$1,175.00 $1,175.00 $1,245.25$1,187.50
304.06.047MIDWEST GUARDRAIL SYSTEM BURIED POST END ANCHOR PER STD PLAN A77T2 0.12 1EA$1,000.00$6,000.00 $6,000.00 $3,023.25$2,400.00
304.06.051TRANSITION RAILING (TYPE WB) 0.40 4EA$4,000.00$4,950.00 $19,800.00 $4,660.00$4,695.00
304.06.053ANCHOR BLOCK FOR TRANSITION RAILING CONNECTION PER STD PLAN A77U3 0.28 4EA$2,200.00$3,425.00 $13,700.00 $5,081.25$5,450.00
312.01.017INSTALL FIRE HYDRANT LOCATION RPM 0.03 25EA$20.00$61.00 $1,525.00 $65.25$60.50
601.09.011TRAFFIC CONTROL 3.88 1LS$170,000.00$193,000.00 $193,000.00 $229,000.00$186,500.00
601.09.017FLASHING ARROW SIGN 0.02 1EA$5,000.00$1,150.00 $1,150.00 $1,755.00$1,685.00
601.09.019CHANGEABLE MESSAGE SIGN 0.10 2EA$5,000.00$2,500.00 $5,000.00 $3,160.00$3,200.00
 CIRACP MIX DESIGN (STIPULATED UNIT PRICE OF $10,000) 0.20 1LS$10,000.00$10,000.00 $10,000.00 $10,000.00$10,000.00
 AC DIKE, TYPE C PER CALTRANS STD PLAN A87B 0.05 433LF$12.00$6.00 $2,598.00 $10.78$11.55
 AC DIKE, TYPE A PER CALTRANS STD PLAN A87B 0.01 40LF$30.00$8.00 $320.00 $15.78$15.05
 ADJUST GUARDRAIL 0.61 3208LF$25.00$9.50 $30,476.00 $14.41$9.25
 AC DIKE, TYPE F PER CALTRANS STD PLAN A87B 0.06 446LF$15.00$7.00 $3,122.00 $11.28$11.55
 ADJUST GUARDRAIL AT BURIED END POST 0.07 4EA$500.00$900.00 $3,600.00 $893.25$882.50
 Total Percent100   Total Amount$4,970,000.00