Bid Price History

Gates Canyon Stormwater Improvements Project
$8,521,454.00
10/30/2018
558 (J3),558 (J4)
8
* Non-standard items are shaded yellow

Item CodeDescription% of Total ProjectQuantityUnitEngineer's EstimateLow Bidder Item BidAmountAverage Item BidMedian Item Bid
001.06.001CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) 0.02 1LS$2,000.00$2,000.00 $2,000.00 $2,000.00$2,000.00
001.06.006CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) 0.04 7MTH$500.00$500.00 $3,500.00 $500.00$500.00
001.06.009CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) 0.01 1LS$1,000.00$1,000.00 $1,000.00 $1,000.00$1,000.00
001.07.004PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $15,000) 0.18 1LS$15,000.00$15,000.00 $15,000.00 $15,000.00$15,000.00
001.07.007IMPLEMENTATION OF THE SWPPP 1.73 1LS$80,000.00$147,500.00 $147,500.00 $71,562.50$47,500.00
001.07.021SHORING OF OPEN EXCAVATIONS 8.80 1LS$731,088.00$750,000.00 $750,000.00 $827,876.63$726,051.50
001.08.003OFFICE FACILITIES 0.75 1LS$10,000.00$63,500.00 $63,500.00 $29,812.50$30,000.00
001.09.003MOBILIZATION 9.39 1LS$320,000.00$800,000.00 $800,000.00 $652,877.25$711,079.00
601.09.011TRAFFIC CONTROL 0.49 1LS$50,000.00$41,600.00 $41,600.00 $40,743.25$35,000.00
801.04.021LANDSCAPING 1.12 1LS$160,000.00$95,220.00 $95,220.00 $102,764.00$87,250.00
801.05.003IRRIGATION SYSTEM 0.79 1LS$161,000.00$67,300.00 $67,300.00 $57,178.13$57,500.00
 TEMPORARY SOUND BARRIER 0.49 1LS$18,000.00$41,400.00 $41,400.00 $44,845.50$46,182.00
 SCE WORK (ALLOWANCE OF $25,000) 0.29 25000AL$1.00$1.00 $25,000.00 $1.00$1.00
 RELOCATE SITE FURNITURE 0.16 1LS$20,000.00$13,890.00 $13,890.00 $15,703.75$11,945.00
 PRE-TREATMENT DEVICE 1.10 1LS$76,700.00$94,150.00 $94,150.00 $130,028.75$122,500.00
 MECHANICAL WORK 17.63 1LS$1,799,699.00$1,502,070.00 $1,502,070.00 $1,642,654.38$1,690,670.00
 CISTERN STORAGE SYSTEM 22.71 1LS$2,049,795.00$1,935,232.00 $1,935,232.00 $2,358,017.69$2,311,459.75
 INTERPRETIVE SIGN 0.05 1LS$5,000.00$4,400.00 $4,400.00 $10,237.50$5,500.00
 ELECTRICAL WORK 15.25 1LS$1,075,000.00$1,299,320.00 $1,299,320.00 $1,210,730.13$1,284,179.50
 DIVERSION DRAINAGE SYSTEM 7.86 1LS$304,120.00$669,586.00 $669,586.00 $794,088.06$664,483.00
 DRYWELLS (A, B1, B2, B3, B4) 5.23 1LS$628,600.00$445,610.00 $445,610.00 $562,017.63$551,540.00
 CONTROL HOUSE 4.70 1LS$361,823.00$400,200.00 $400,200.00 $398,660.00$400,100.00
 CISTERN DISCHARGE PIPE & PUMP WELL 0.99 1LS$59,280.00$83,976.00 $83,976.00 $122,271.38$108,222.50
 JOBS COORDINATOR (ALLOWANCE OF $20,000) 0.23 20000AL$1.00$1.00 $20,000.00 $1.00$1.00
 Total Percent100   Total Amount$8,521,454.00