Item Code | Description | % of Total Project | Quantity | Unit | Engineer's Estimate | Low Bidder Item Bid | Amount | Average Item Bid | Median Item Bid |
001.06.001 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) |
0.02
| 1 | LS | $2,000.00 | $2,000.00 |
$2,000.00
| $2,000.00 | $2,000.00 |
001.06.006 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) |
0.04
| 7 | MTH | $500.00 | $500.00 |
$3,500.00
| $500.00 | $500.00 |
001.06.009 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) |
0.01
| 1 | LS | $1,000.00 | $1,000.00 |
$1,000.00
| $1,000.00 | $1,000.00 |
001.07.004 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $15,000) |
0.18
| 1 | LS | $15,000.00 | $15,000.00 |
$15,000.00
| $15,000.00 | $15,000.00 |
001.07.007 | IMPLEMENTATION OF THE SWPPP |
1.73
| 1 | LS | $80,000.00 | $147,500.00 |
$147,500.00
| $71,562.50 | $47,500.00 |
001.07.021 | SHORING OF OPEN EXCAVATIONS |
8.80
| 1 | LS | $731,088.00 | $750,000.00 |
$750,000.00
| $827,876.63 | $726,051.50 |
001.08.003 | OFFICE FACILITIES |
0.75
| 1 | LS | $10,000.00 | $63,500.00 |
$63,500.00
| $29,812.50 | $30,000.00 |
001.09.003 | MOBILIZATION |
9.39
| 1 | LS | $320,000.00 | $800,000.00 |
$800,000.00
| $652,877.25 | $711,079.00 |
601.09.011 | TRAFFIC CONTROL |
0.49
| 1 | LS | $50,000.00 | $41,600.00 |
$41,600.00
| $40,743.25 | $35,000.00 |
801.04.021 | LANDSCAPING |
1.12
| 1 | LS | $160,000.00 | $95,220.00 |
$95,220.00
| $102,764.00 | $87,250.00 |
801.05.003 | IRRIGATION SYSTEM |
0.79
| 1 | LS | $161,000.00 | $67,300.00 |
$67,300.00
| $57,178.13 | $57,500.00 |
| TEMPORARY SOUND BARRIER |
0.49
| 1 | LS | $18,000.00 | $41,400.00 |
$41,400.00
| $44,845.50 | $46,182.00 |
| SCE WORK (ALLOWANCE OF $25,000) |
0.29
| 25000 | AL | $1.00 | $1.00 |
$25,000.00
| $1.00 | $1.00 |
| RELOCATE SITE FURNITURE |
0.16
| 1 | LS | $20,000.00 | $13,890.00 |
$13,890.00
| $15,703.75 | $11,945.00 |
| PRE-TREATMENT DEVICE |
1.10
| 1 | LS | $76,700.00 | $94,150.00 |
$94,150.00
| $130,028.75 | $122,500.00 |
| MECHANICAL WORK |
17.63
| 1 | LS | $1,799,699.00 | $1,502,070.00 |
$1,502,070.00
| $1,642,654.38 | $1,690,670.00 |
| CISTERN STORAGE SYSTEM |
22.71
| 1 | LS | $2,049,795.00 | $1,935,232.00 |
$1,935,232.00
| $2,358,017.69 | $2,311,459.75 |
| INTERPRETIVE SIGN |
0.05
| 1 | LS | $5,000.00 | $4,400.00 |
$4,400.00
| $10,237.50 | $5,500.00 |
| ELECTRICAL WORK |
15.25
| 1 | LS | $1,075,000.00 | $1,299,320.00 |
$1,299,320.00
| $1,210,730.13 | $1,284,179.50 |
| DIVERSION DRAINAGE SYSTEM |
7.86
| 1 | LS | $304,120.00 | $669,586.00 |
$669,586.00
| $794,088.06 | $664,483.00 |
| DRYWELLS (A, B1, B2, B3, B4) |
5.23
| 1 | LS | $628,600.00 | $445,610.00 |
$445,610.00
| $562,017.63 | $551,540.00 |
| CONTROL HOUSE |
4.70
| 1 | LS | $361,823.00 | $400,200.00 |
$400,200.00
| $398,660.00 | $400,100.00 |
| CISTERN DISCHARGE PIPE & PUMP WELL |
0.99
| 1 | LS | $59,280.00 | $83,976.00 |
$83,976.00
| $122,271.38 | $108,222.50 |
| JOBS COORDINATOR (ALLOWANCE OF $20,000) |
0.23
| 20000 | AL | $1.00 | $1.00 |
$20,000.00
| $1.00 | $1.00 |
| Total Percent | 100 | | | | Total Amount | $8,521,454.00 | | |