Project Schedule
Project as a whole:
Construction activities started in late August 2007 and are scheduled to be completed in February 2010.
By clicking on the thumbnail image on the left, users can view the Department's high level project schedule.
Activities to the left of the data date (blue vertical line) have been completed. Activities to the right of the data date are pending.
Two Week Look Ahead:
The following construction activities have been scheduled for the next two weeks (02/11/2010 to 02/25/2010) as part of the Stage 3 and 4 construction:
- Construction of the Hasley Canyon northbound off-ramp
- Re-striping the I-5 freeway lanes.
- Construction of 8 ft high chain link fence along the east side of the project.
- Construction of the Castaic Creek Bridge unstaged approach slabs middle of the I-5 freeway
|
|