Stage One november 2009 Images
Installed metal beam guardrail along the east side of The Old Road south of Hasley Canyon Road.
Cast-in-drilled-hole for Castaic Creek Bridge retrofit middle of Interstate 5 freeway.
Construct handicapped ramp at the northeast corner of Hasley Canyon Road and The Old Road.
Hydro-seed the slopes along the east side of The Old Road south of Hasley Canyon Road.
Hydro-seed the slopes behind the sound wall at the southwest corner of Hasley Canyon Road and The Old Road.
Placement of forms for cast-in-drilled-hole concrete pile walls for Castaic Creek Bridge retrofit middle of Interstate 5 freeway.
Placement of reinforcing steel for cast-in-drilled-hole concrete pile walls for Castaic Creek Bridge retrofit middle of Interstate 5 freeway.
|
|